EGR 312 - 20 1 Project Management Planning Techniques Project manager responsible for developing project implementation plan. Duties includes: Defining tasks Making estimates (cost and timing) Preparing schedules Preparing budgets
2
EGR 312 - 20 2 Project Management Recall the house construction example: Task Definition: Description Duration(days) Precedence Step A: Prepare site. 5- Step B: Build foundation. 8A Step C: Frame walls and roof. 15B Step D: Rough in Plumbing 12C Step E: Rough in Electrical 10C Step F: HVAC Venting 8C Step G: Drywall 11D,E,F Step H: Finish Electrical 5G Step I: Finish Plumbing 4 G Step J: Finish HVAC 2H Step K: Install Kitchen 8H,I Step L: Install Baths 14 H,I Step M: Paint 5J,K,L Step N: Landscape 5J,K,L
3
EGR 312 - 20 3 Project Management Recall: Precedence Diagram Tasks must sometimes be performed in series, or may at times be performed in parallel. For the house example, let each node represent a project task/job. Each node is identified by a job letter and duration. Now we can determine how long it will take to finish the project … H,5J,2 B,8A,5C,15 D,12 G,11 I,4 E,10 F,8 K,8 L,14 N,5 M,5
4
EGR 312 - 20 4 Project Management Critical Path H,5J,2 B,8A,5C,15 D,12 G,11 I,4 E,10 F,8 K,8 L,14 N,5 M,5
5
EGR 312 - 20 5 Project Management Timing – Gantt Chart Tasks and task durations are often represented as Gantt Charts. Task precedence knowledge is shown graphically on the time line. Task NameDuration Apr 6, 09Apr 13, 09 MTWTFMTWTF
6
EGR 312 - 20 6 Expediting/Crashing CPM – Critical Path Method Can normal task times be reduced? Is there an increase in direct costs? Additional manpower Additional machines Overtime, etc… Can there be a reduction in indirect costs? Less overhead costs Less daily rental charges Bonus for early completion Avoid penalties for running late Avoid cost of late startup CPM addresses these cost trade-offs.
7
EGR 312 - 20 7 CPM – Critical Path Method Example: Overhead cost = $5/day Step 1. Draw the precedence diagram
8
EGR 312 - 20 8 CPM – Critical Path Method Enumerative Approach: Reduce job D by 1 day: Total cost improves by ________________ Reduce job H by 1 day: Total cost improves by ________________ Reduce job A by 2 days: Total cost improves by ________________ Precedence diagram & critical path A,10 B,5C,3 D,4 E,3 F,6 G,5 H,5
9
EGR 312 - 20 9 CPM – Critical Path Method (cont.) Reduce job A by an additional day and job B by 1 day?: Total cost improves by ________________ Reduce job A by an additional day and job C by 1 day?: Total cost improves by ________________ A,10 B,5C,3 D,4 E,3 F,6 G,5 H,5
10
EGR 312 - 20 10 CPM – Critical Path Method (cont.) Any additional cost reductions possible? Overall improvement = ______________________________ A,8* B,5C,3 D,3* E,3 F,6 G,5 H,4* * task time after crashing