Download presentation
Presentation is loading. Please wait.
Published byDoreen Knight Modified over 8 years ago
1
In Chapter 5: Scheduling the Project From Action Plan and WBS to Gantt chart and project network. Gantt Chart Project Network Activity-on-arrow Activity-on-node CPM and PERT Risk analysis involves determining the likelihood that a project can be completed on time Statistics Simulation 6/4/2016Ardavan Asef-Vaziri5-1
2
In Chapter 5: Scheduling the Project 6/4/2016Ardavan Asef-Vaziri5-2
3
History Late 1950s Critical Path Method (CPM) Dupont De Nemours Inc. developed the method Deterministic activity durations Program Evaluation and Review Technique (PERT) U.S. Navy, Booz-Allen Hamilton, and Lockeheed Aircraft Probabilistic activity durations 6/4/2016Ardavan Asef-Vaziri5-3
4
The Language of PERT/CPM Activity Task or set of tasks Takes time and needs resources Precedence Relationships The immediate predecessor activities Event Completion of one or more activities (to allow the next activity or activities to start) Zero duration, zero resource Milestones Significant events – showing completion of a significant portion of the project 6/4/2016Ardavan Asef-Vaziri5-4
5
The Language of PERT/CPM Network Diagram of nodes connected by directed arcs Shows technological relationships among activities Path A set of connected activities such that each activity on both sides is connected to one and only one other activity (with exception!). Critical Path A path where a delay in any of its activities will delay the project The longest path on the network The shortest time to complete the project Critical Time The total time to complete all activities on the critical path 6/4/2016Ardavan Asef-Vaziri5-5
6
Two Types of Network Diagrams Activity-on-Arrow Network (Arrow Diagramming Method) Easier to show events and milestones More compatible with network theory techniques Sometimes requires dummy (artificial) activities Activity-on-Node Network (Precedence Diagramming Method) Easier representation No dummy activity 6/4/2016Ardavan Asef-Vaziri5-6
7
Activity on Arrow Network An Activity is an arc with two nodes at its beginning and its end 6/4/2016Ardavan Asef-Vaziri5-7 a b c d
8
AoA: Activity Predecessors A list of immediate predecessors is needed. 6/4/2016Ardavan Asef-Vaziri5-8 TaskPredecessor abcabc -- a b abc TaskPredecessor abcdabcd --- -- b a a b d c
9
AoA: Activity Predecessors 6/4/2016Ardavan Asef-Vaziri5-9 TaskPredecessor abcdabcd --- a a b d c TaskPredecessor abcdabcd --- -- a,b,c a b d c
10
AoA May Need Dummy Activity Two activities have the same starting and ending nodes A single activity connects to two or more nodes 6/4/2016Ardavan Asef-Vaziri5-10 TaskPredecessor abcdabcd --- a b,c a b d c Try this: a,b c and a,d e
11
AoA: A Power Plant Construction Project 6/4/2016Ardavan Asef-Vaziri5-11 TaskDescriptionPredecessor abcdefghijabcdefghij Design & engineering Select site Select vendor Select personnel Prepare site Manufacture generator Prepare operation manual Install generator Train operators Obtain license --- a b c e,f d,g h,i
12
6/4/2016Ardavan Asef-Vaziri5-12 a b cf d g e h i j AoA: A Power Plant Construction Project a:- b:a c:a d:a e: b f:c g:c h:e,f i: d,g j: h,i
13
6/4/2016Ardavan Asef-Vaziri5-13 Draw AoN Network a:- b:a c:a d:a e: b f:c g:c h:e,f i: d,g j: h,i
14
Draw AOA 6/4/2016Ardavan Asef-Vaziri5-14
15
Transform into AON 6/4/2016Ardavan Asef-Vaziri5-15 1234567 a = 6 b = 2g = 9 h = 9 k = 6 d = 4 c = 5 e = 3 i = 4 f = 8 j = 7 a:- b:- c:- d:a e: a f:c g:b,e,f h:c i: b,e,f j: h k:d,i
16
Draw AoN Network 6/4/2016Ardavan Asef-Vaziri5-16 a:- b:- c:- d:a e: a f:c g:b,e,f h:c i: b,e,f j: h k:d,i
17
Critical Path and Critical time The critical path is the shortest time in which a project can be completed If a critical activity is delayed, the entire project will be delayed. There may be more than one critical path. Brute force approach to finding critical path: 1.identify all possible paths from start to finish 2.sum up duration of activities on each path 3.largest total indicates critical path 6/4/2016Ardavan Asef-Vaziri5-17
18
Critical Path Method: The Network A1 A3 A4 A6 A5 A2 4 3 6 4 2 3 E S Find the Critical Path.
19
Critical Path Method: Paths A1A3A4A6A5A2 4 3 6 4 2 3 ES 10 Critical Path is the longest path 118 How many path? It is the shortest time to complete the project
20
Forward Path; Earliest Starts A1 A3 A4 A6 A5 A2 4 3 6 4 2 3 E S 0 0 0 0 0 0 4 3 3 4 4 3 4 410 8 5 5 8 8 11
21
10 30 20 Max = 30 5 35 Forward Path 35
22
Backward Path; Latest Starts A1 A3 A4 A6 A5 A2 4 3 6 4 2 3 E S 0 0 0 0 0 0 4 3 3 4 4 3 4 410 8 5 5 8 8 11 5 5 8 8 8 8 8 4 6 4 6 6 3 3 40 0
23
30 Min = 35 5 35 45 30 Backward Path
24
Activity Slack Slack, or float: The amount of time a noncritical task can be delayed without delaying the project Slack—LFT – EFT or LST – EST EST—Earliest Start Time Largest EFT of all predecessors EFT—Earliest Finish Time EST + duration for this task LFT—Latest Finish Time Smallest LST of following tasks LST—Latest Start Time LFT – duration for this task 6/4/2016Ardavan Asef-Vaziri5-24
25
Computing Slack Times 6/4/2016Ardavan Asef-Vaziri5-25 Task = duration slack = xxxx ESTEFT LSTLFT
26
Critical Path, Slacks A1A3A4A6A5A2 4 3 6 4 2 3 ES 0 0 4 3 3 4 4 10 8 5 8 11 5 8 8 8 4 6 6 3 4 0
27
Slack Times Example Task Pred. Dur. a -- 4 g c,d 1 b -- 3 h e 4 c a 3 i f 5 d a 2 j e,g 6 e b 6 k h,i 1 f b 4 For each task, compute ES, EF, LF, LS, slack 6/4/2016Ardavan Asef-Vaziri5-27
28
Slack Times Example 6/4/2016Ardavan Asef-Vaziri5-28 Start Finish a=4 slack= b=3 slack= c=3 slack= d=2 slack= e=6 slack= f=4 slack= g=1 slack= h=4 slack= i=5 slack= j=6 slack= k=1 slack= Task=dur slack=xxx ESTEFT LFTLST
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.