Presentation is loading. Please wait.

Presentation is loading. Please wait.

By Spokes On A Wheel I-35/Hwy 183 – Interchange Upgrade.

Similar presentations


Presentation on theme: "By Spokes On A Wheel I-35/Hwy 183 – Interchange Upgrade."— Presentation transcript:

1 by Spokes On A Wheel I-35/Hwy 183 – Interchange Upgrade

2 Agenda Introduction Objectives Scope Contracts Financing Schedule Control Labor Possible Problems Questions and Comments

3 Before and After Project Proposal

4 Project Objective Setting OPERABILITY Improve traffic flow Reduce travel time Safety of road users COST Min. the cost of the project SAFETY Max. protection for the public & the workers SCHEDULE Meet or exceed milestones Finish complete project on time I-35 / Hwy 183 Interchange Upgrade DURABILITY Life span Low maintenance Maintainability PUBLIC RELATIONS Community support/involvement Aesthetics Min. environ. impact AVOID CLAIMS/ CHANGE ORDERS

5 Performance Index

6 Scope of Work FUNCTION Decrease travel time from 4 minutes to 45 seconds Decrease reportable accident rate ~ 50% SIZE 5 new overpasses Lane width – 15 ’ Shoulders – 6 ’ (expandability) LIFE SPAN Designed for 30 years COMMUNITY IMPACT Maintain traffic flow I-35 & 183 Interchange Project COST $120 million AESTHETICS Match existing structures and landscape ( “ fit in ” ) CAPACITY Handle ~ 40,000 cars/day SCHEDULE 3 years (including design and construction)

7 Feasibility & Financial Studies Financing From federal funding & gasoline tax proceeds Gasoline tax $0.40/gal Investment period: 33 years Cost Initial cost ~ $120 million Operation & periodic maintenance: $150k/yr Benefits Time saving : $78,000/day Safety saving : $750,000 / year I-35 & 183 Interchange Project

8 Cash Flow Diagram y0 y0 y5y5 y 10 y 15 y 20 y 25 y 30 Discount rate: 12% Benefit ~ $29.22 million / year Present value ~ $235.4 million Discount rate: 12% Outgo ~ $150k / year Present value ~ $1.21million Initial cost $120 million in three years Cost benefit ratio = Gross Benefit/Cost CBR = 1.94 Present value of project cost ~ $121.21million Present value of revenue ~ $235.4 million

9 Contracts Owner--Designer and Owner--QA/QC = negotiated Owner--Contractor = competitively bid Contractor--Subcontractors and Owner--Vendors = negotiated Owner & Contractor should also have contracts with Bonding Agencies (Performance Bonds), Insurance Co., and Legal Firms I-35 & 183 Interchange Project

10 Unit-Price Contract Allows some flexibility for variations in quantity of work Payments made on precise field measurements Price renegotiation if actual vs. estimated deviation of +/- 10% “ Unbalancing the bid ” Item NumberQuantityUnitDescription Unit Price Total Amount 005601000CYReg. Excav.10.0010,000.00 009005000LBReinf. Steel1.005,000.00 2427010ACRESReg. Seed100.001,000.00 2720500HRSFlaggers10.005,000.00 I-35 & 183 Interchange Project

11 Owner - Contractor Contract awarded to lowest responsible bidder (Competitively Bid) - Technical Competence - Bonding Capacity - Previous Contracts - Work Underway - Claims History - Financial Position  Competitively Bid Contracts used for most public work  Based on complete plans and specifications Calendar Day – 730 from start date to traffic Incentives – Job finishes early = $500,000 bonus Penalty – Job finishes late = $10,000/day Disadvantage – Low Bidding I-35 & 183 Interchange Project

12 LEGEND: Task Duration Reviews & Approval Public Meetings/Hearings Completion Planning Schedule

13 Construction Schedule

14 Project Control SAFETY Safety Manager Investigate Accidents Alcohol and Drug Use Control COST Weekly and Monthly Reports Meetings (Owner, Contractor, and QA/QC Firm) Tool: CWB I-35 & 183 Interchange Project TRAFFIC Maintain Traffic at all Times Lane Shutdown QUALITY Material Testing Following Design, Specs QA/QC SCHEDULE Detailed Schedule (CPM) Tool: Primavera Daily Diaries

15 Labor Source I-35 & 183 Interchange Project SNLabor TypeNo.Sourcewhen Needed ActivityDuration 1Carpenters10Open ShopShuttering & Formwork sub structure and super structureM13 -33 2Concrete finishers20Open ShopPile cap, footing, Piers, Decks and other Concrete worksM18-34 3Rod busters17Open ShopPile cap, footing, Piers, Decks and other RC worksM18-34 4Electrical5UnionDecommissioning of Traffic Light, setting temporary controlM13, lights and Installing of new traffic Control lightsM37 5Equipment Operators8UnionAll through the Construction periodM13-37 6Crane Operators2Union Decommissioning of existing structures & construction periodM13-34 7Surveying3UnionSurveying through bridge deck constructionM13-33 8Laborers10Open ShopThrough construction periodM12-37 9Designers (Back up & site modifications)2Open ShopPeak construction periodM22 -37 10Asphalt workers (Pavers, operators and all)7Open ShopConstruction of Detour tracks and Final Road PavementM12, M36 11Flaggers3Open ShopThrough construction periodM12-37 12Superintendent1Open ShopThrough construction periodM12-37 13Plumbing and pipe fitters2Open ShopRequired to set drain pipes before casting bridge deckM27-33 14Landscapers6Open ShopLandscaping ActivitiesM37 15Striping crew5Open ShopLane Markings, Traffic Line painting, Road edge marking M36-37 Total101

16 100 80 40 20 % Cumulative Labor utilization Estimated Labor Cumulative Labor 60 0

17 POSSIBLE PROBLEMS I-35 & 183 Interchange Project

18 ACTIONS TO PREVENT OR MITIGATE PROBLEMS Rain – Unusual Amount / Timing Implement a 4 days-10 hours W.D. Build effective drainage systems Overtime and double shifts Alcohol / Drug Abuse Background check Random testing Guidance/Education meetings Firing or Rehabilitation therapies Traffic Accidents (Interfering Const.) Maximize the distance between traffic flow and workers Permanent barriers Truck mounted attenuators I-35 & 183 Interchange Project Delay in Material Delivery More materials on site Larger lag time between delivery & use of mat. Identify alternative source Contractor Bankruptcy Bonding Pre-qualifications Specify time for new contractor

19 Questions and Comments


Download ppt "By Spokes On A Wheel I-35/Hwy 183 – Interchange Upgrade."

Similar presentations


Ads by Google