Published byJoanna Perry Modified over 8 years ago
1
PRESENTATION FOR POLO SETTIMO TORINESE PROJECT Nov.25 th.2009
2
Presentation for NPST 1.Previous Minute Meeting (27 th.Oct) 2.General Description 3.Schedule 4.Critical Points
3
1.Foundation fixed out of Building 101. Issues Previous Minute Meeting (28 th.Oct) 1.The foundations for Silos of 101 have not been confirmed yet. Status 2.Hangar East 2.The hanger east had been started on Nov.13th, HQCEC have require ROSSO to prepare the detail time schedule. And the new tank and pump station will finish connection with existing system before Dec.10 th, then, the interference will be avoided.
4
3.Anticipate the start of compressed air, MV Cabinet and Industrial Water in the hangar. Previous Minute Meeting (28 th.Oct) 3.Following civil construction time schedule of hangar east we will organize the work. 4.Facade panels: they are ordered and in production. Delayed is the “moke up” to fix monitoring quality and procedure. 4.According to the job site situation, the progress of façade is following the time schedule. Issues Status
5
General Description 1.In 102~106, Inside wall finished 70%, water proof of roof finished 70%, outside wall finished 65%. 2.The prefabricated parts in 101 finished 60%. 3.Civil work of Hangar East started on Nov.13 th. 4.BUSI start the site work since 19 th.Oct.2009, and finish 5 lines in 104 piping trench. 5.EUSEBI finished the foundation of tank and continued the underground piping and sprinkler system. 6.The progress for underground piping are following the schedule 7.Cerrato started the crane beam installation today.
6
Schedule of 102~106 Trenches & Equipment Foundations in 103NT & 104 102 103-T Trench 1 Trench 2 Trench 3 Main Trench 103-NT 104 105 106 Trench in 103-NT Trench 1 in 104: Finished Trench 2 in 104: Finished Trench 3 in 104: Finished Main trench in 104: 10th Dec Trench in 103-NT: 5 th.Oct.2009~24 th.Dec.2009, From 1st Dec can start the work for piping
7
103-T 103-NT 104 105 106 Schedule of 102~106 Process Equipment Foundations 102 Foundations in 102: 1 st.Dec.2009 ~ 15 th.Jan.2009 Foundations in 105: 15 th.Dec.2009 ~ 30 st.Dec.2009 Creel room in 102: 1°Main steel structure: 7 th.Dec.2009 ~ 20 th.Jan.2010 2°External wall: 25 th.Dec.2009 ~ 30 th. Jan.2010
8
Schedule of 102~106 Internal Partition Wall 106 103-T 103-NT 104 105 102 Step 1: Finished Step 2: Working, will finish on 30 th.Nov.2009 Step 3: 28 th.Nov.2009 ~ 15 th.Dec.2009
9
Schedule of 102~106 Roof Construction Area 1: will finish before 1 st.Dec.2009 Area 2: will finish before 5 th.Dec.2009 Area 3: will finish before 15 th.Dec.2009 Part 2: 9 th.Nov.2009 ~ 24 th.Dec.2009 Area 3 Area 2 Area 1 Part 2 Part 1: Water-proof of tegula and installation of suspended ceiling finished. For other roof work: Part 1 Area 4 Area 4: will finish before 20 th.Dec.2009
10
Schedule of 102~106 External Wall Step 1: 12 th.Sep.2009 ~ 15 th.Dec.2009 Step 2: 20 th.Sep.2009 ~ 25 th.Dec.2009 Step 3: 25 th.Nov.2009 ~ 5 th.Jan.2010 Step 4: 15 th.Dec.2009 ~ 19 th.Jan.2010 Time schedule Actual work: Finished
11
Schedule of 102~106 Floor Construction Step 1: 7 th.Dec.2009 ~ 13 th.Dec.2009 Step 2: 14 th.Dec.2009 ~ 15 th.Dec.2009 Step 3: 16 th.Dec.2009 ~ 20 th.Dec.2009 Step 4: 21 th.Dec.2009 ~ 23 th.Dec.2009 106 103-T 103-NT 104 105 102 Step 5: 28 st.Dec.2009 ~ 31 st.Dec.2009 Step 3 Step 7 Step 6 Step 8 Step 9 Step 1 Step 5 Step 2 Step 6: 4 th.Jan.2009 ~ 11 th.Jan.2009 Step 7: 12 th.Jan.2009 ~ 13 th.Jan.2009 Step 8: 14 th.Jan.2009 ~ 15 th.Jan.2009 Step 9: 18 th.Jan.2009 ~ 20 th.Jan.2009 Step 10: 21 st.Jan.2009 ~ 22 nd.Jan.2009 Step 10 Step 4
12
Schedule of 102~106 Fire Fighting System 106 103-T 103-NT 104 105 102 102: 18 st.Nov.2009 ~ 5 th.Dec.2009 103-T: 23 th.Nov.2009 ~ 2 nd.Dec.2009 103NT: 30 th.Nov.2009 ~ 11 th.Dec.2009 106: 8 th.Dec.2009 ~ 29 th.Dec.2009 105: 7 th.Dec.2009 ~ 25 th.Dec.2009 104: 10 th.Dec.2009 ~ 29 th.Dec.2009
13
Schedule of 102~106 Electrical System Installation 103-T: 16 th.Nov.2009 ~ 7 th.Jan.2010 106: 15 th.Dec.2009 ~ 30 th.Jan.2010 104: 27 th.Nov.2009 ~ 13 th.Jan.2010 105: 27 th.Nov.2009 ~ 13 th.Jan.2010 106 103-T 103-NT 104 105 102 102: 9 th.Dec.2009 ~ 23 rd.Jan.2010 103-NT: 3 rd.Dec.2009 ~ 19 th.Jan.2010
14
Schedule of 102~106 Piping System Installation 103-T: 11 th.Nov.2009 ~ 1 st.Jan.2010 106: 16 th.Dec.2009 ~ 19 th.Jan.2010 104:11 th.Nov.2009 ~ 13 th.Jan.2010 105: 19 th.Oct.2009 ~ 9 th.Dec.2009 106 103-T 103-NT 104 105 102 102: 4 th.Dec.2009 ~19 th.Jan.2010 103-NT: 23 rd.Nov.2009 ~ 13 th.Jan.2010
15
Schedule of 102~106 HVAC System Installation 103-T: 14 th.Dec.2009 ~ 7 th.Jan.2010 106: 20 th.Jan.2010 ~ 11 th.Feb.2010 104: 23 rd.Nov.2009 ~ 26 th.Dec.2009 105: 28 th.Dec.2009 ~ 13 th.Jan.2010 106 103-T 103-NT 104 105 102 102: 8 th.Jan.2010 ~11 th.Feb.2010 103-NT: 16 th.Dec.2009 ~ 19 th.Jan.2010
16
Schedule of 101 Civil Work Step 1: finished Step 2: finished Step 3: finished Step 1 Step 2 Step 3 Step 4 Step 5 Step 4: 19 th.Nov.2009 ~ 9 th.Dec.2009 Step 5: 6 th.Dec.2009 ~ 31 st.Dec.2009
17
Schedule of 101 Steel Structure & Crane, Elevator Steel structure for BY2 & BY6 : 7 th.Dec.2009 ~ 30 th.Jan.2010 Steel structure for BY4 & BY7: 15 th.Dec.2009 ~ 25 th.Feb.2010 Crane: 1°Steel beam installation: 25 th.Nov.2009 ~ 11 th.Dec.2009 2°Crane bridge installation: 1 st.Dec.2009 ~ 18 th.Dec.2009 1°Elevator: Available in the end of Feb.2009 2°Elevator: Available in the middle of Mar.2009
18
Schedule of 101 Mezzanine & Silo Foundation Mezzanine: 25 th.Nov.2009 ~ 19 th.Jan.2010 Silo foundation: to be defined
19
Schedule of 101 Floor & External Wall Floor Step 1: 15 th.Dec.2009 ~ 10 th.Jan.2010 Floor Step 2: 11 th.Jan.2010 ~ 25 th.Jan.2010 Discharge Trench: 25 th.Nov.2009 ~ 30 th.Dec.2009 External Wall: 16 th.Nov.2009 ~ 4 th.Mar.2010 Step 1 Step 2
20
Schedule of 101 Utility & Electrical & Fire Fighting System Installation Electrical Power System: 16 th.Nov.2009 ~ 5 th.Feb.2010 Piping System: 7 th.Dec.2009 ~ 28 th.Jan.2010 HVAC System: 14 th.Dec.2009 ~ 20 th.Feb.2010 Fire Fighting System: Mixing Room, 27 th. Dec.2009 ~ 20 th.Jan.2010 Fire Alarm System: 16 th.Nov.2009 ~ 12 th.Feb.2010 Warehouse and others, 4 th.Jan.2010 ~ 29 th.Jan.2010
21
101 102~106 HV Substation Fire Fighting Tanks Fire Fighting Tanks Schedule of Electrical System Civil Work & System Installation HV (10MVA Transformer): 20 th.Oct ~ 25 th.Jan.2010 MV-A/C: 20 th.Oct.2009 ~ 19 th.Feb.2010 Utility MV-A MV-B MV-C MV-D MV-B/D: 20 th.Oct.2009 ~ 2 nd.Feb.2010
22
101 102~106 HV Substation Fire Fighting Tanks Fire Fighting Tanks Schedule of Electrical System Power Supply Date MV Transformer: 25 th.Jan.2010 MV-B & D: 30 th.Jan.2010 Utility MV-A MV-B MV-C MV-D MV-A & C : 5 th.Feb.2010
23
Critical Points 1.Hangar East
24
Hangar Est 1.The interference between the utility building and the existent fire fighting pump station 1. The work activities of Hangar East will be delayed 1.HQCEC(SH) are checking with ROSSO and EUSEBI to find out the solution Status Influence Solutions
25
Thank You