Presentation is loading. Please wait.

Presentation is loading. Please wait.

ME 414: Project #1 Design Team Members: Andy Cash Kyle Bredehoeft Alan Koers Brent Miller Presentation Date: May 5, 2006.

Similar presentations


Presentation on theme: "ME 414: Project #1 Design Team Members: Andy Cash Kyle Bredehoeft Alan Koers Brent Miller Presentation Date: May 5, 2006."— Presentation transcript:

1 ME 414: Project #1 Design Team Members: Andy Cash Kyle Bredehoeft Alan Koers Brent Miller Presentation Date: May 5, 2006

2 Project Definition NASA Requests a quote: To design a heating and ventilation system for an arctic research facility located at the North Pole. Contains four researchers Inside temperature to be maintained at 25 °C Outside temperature is a constant -40 °C No cooling system needed for obvious reasons

3 Design Constraints Ducts formed from rubber coated sheet metal: Sheet Size: 70” x 90” Relative roughness: 2mm Outside Walls 12” thick Inside Walls 8” Register location is fixed Register Size: 6” x 16” Occupants Require 8 liters of fresh air per minute

4 Resistance Network

5 Room #1 Heat Loss & Cost

6 Room #1 Mass Flow Rate

7 Fresh Air Heating

8 Heat Generation from Building Occupants

9 Flowmaster Room Model Return Register Junction Piping

10 Flowmaster Model

11 Flowmaster Results

12 Housing Layout Room 1 Room 2 Room 3 Room 4 Room 5

13 Solid Model Duct Routing FRESH AIR OUTLET FRESH AIR INLET

14 Duct Routing Close-up

15 Duct Work System

16 Building Front Section View

17 Material & Labor Costs Material Costs Sheet Width (in.)70 Sheet Length (in.)90 Total material area needed (in 2 )169,748 Total Number of Sheets27 Cost per Sheet$250.00 Material Cost$6,736.03 Labor Costs Shearing Cost$1,347.21 Bend Forming$4,300.00 Branch Forming$1,000.00 Register Hookups$400.00 Total Material and Labor Cost:$13,783.24

18 800 CFM Fan Curve

19 800 CFM Fan Results

20 Fresh Air Inlet Results

21 800 CFM Pressure Distribution

22

23 800 CFM Velocity Distribution Room Air Velocity Below Comfort Threshold of 0.15 m/s

24 800 CFM Flow Trajectory

25

26 800 CFM Pressure Drop and Air Changes per Hour

27 Blower Comparison Note: 2000 CFM Blower vel_max exceeds 100 m/s Fresh Air Delivery Insufficient

28 Blower Operation Cost/Month

29 Monthly Heating Requirements & Costs Note: Total Bldg Q=14,651 BTU/hr Basement not heated

30 Risk Assessment and Contingency Event of Furnace or Blower Failure 1)Gather at Central Bldg Location 2)Start Generator and Resistance heater Likelihood ImpactHighLow High

31 Risk Assessment and Contingency Fresh Air Ventilation System Frost or Other Blockage 1)Remove Blockage 2)Insure Safe Oxygen Levels Likelihood ImpactHighLow High

32 Cost Summary

33 Questions Special Thanks to: Billy Holland Professor Toksoy


Download ppt "ME 414: Project #1 Design Team Members: Andy Cash Kyle Bredehoeft Alan Koers Brent Miller Presentation Date: May 5, 2006."

Similar presentations


Ads by Google