1
Traci Peterson Structural Option Senior Thesis Presentation The Del Monte Center at The North Shore The Pennsylvania State University Department of Architectural EngineeringSpring 2005
2
Outline of Presentation Project overview Depth Study –Redesign of lateral system Architecture Breadth Study –Construction management –Mechanical Conclusions
3
The Del Monte Center at The North Shore 375 North Shore Drive, Pittsburgh, PA
4
Project Overview Pittsbu rgh's North Shore Location of Building
5
Project Overview Building Statistics –Dates of Construction –Occupancy/Function –Size –Cost
6
Project Overview Project Team –Continental/Nationwide Realty Investors –Strada –Continental Building Systems –Atlantic Engineering Services –Allen & Shariff Corporation –Limbach Facility services
7
Project Overview Structural System –Frame –Foundation –Floor System
8
Project Overview 1” expansio n joint
9
Project Overview Location of Bracing: Fram e E Fram e D Lateral System –Bracing (North-South Direction):
10
Project Overview Bracing (East-West Direction) Fram e E Fram e D Frames A & D Frames B & E Frames C & F
11
Depth Study Lateral System Redesign –Alternative #1 –Alternative #2 Exposed bracing Modified windows
12
Depth Study Design Criteria –Codes –Methods
13
Depth Study Loads –Dead –Live –Snow –Wind –Seismic Load combinations –1.4D –1.2D+1.6L+0.5S –1.2D+1.6S+(0.5L or 0.8W) –1.2D+1.6W+0.5L+0.5S
14
Depth Study STAAD.pro 2002 –“Select Optimized” command
15
Depth Study Existing System Total Weight of System = 426.7 k Frames A & D Frames B & E Frames C & F
16
Depth Study Alternative #1- Moment Frames Total Weight of System = 358.5 k Frames A & D Frames B & E Frames C & F
17
Depth Study Alternative #1- Moment Frames –Drift
18
Depth Study Alternative #2- Full Bay Bracing Total Weight of System = 200.8 k Frames A & D Frames B & E Frames C & F
19
Depth Study Results system total weight (kips) existing462.7 Alternative #1 (moment frames) 358.5 Alternative #2 (chevrons) 200.8
20
Architecture Alternative #2- chevrons –Modified Windows –Exposed Bracing
21
Architecture Alternative #2 with modified windows
22
Architecture Alternative #2 with exposed bracing
23
Architecture
25
Breadth Study Construction Management materia l erectio n total Existing system $121,6 21.47 $20,73 9.04 $142,36 0.51 Alternat ive #1 $102,1 65.09 $12,19 4 $114,3 59.09 Alternat ive #2 $57,228.57 $25,452.56 $82,68 1.13 Cost of Structural Steel W-shapes:
26
Breadth Study Construction Management –Existing beam to column connections Given: –Bolted double angle –ASTM A325 ¾” slip-critical bolts –Designed for summation of: »½ uniform load capacity of member »10k axial force Determined: –¼” angle –5 rows of bolts –$63 each
27
Breadth Study Construction Management –Existing bracing connections Given: –Bolted/welded shear end-plate connections –Fillet welds Determined: –3/16” weld –2 rows of bolts –$55 each
28
Breadth Study Construction Management –Moment connections Determined: –Single-plate web connection: »3/8” x 12” »5 7/8” bolts »2 5/16” fillet welds –Tension flange-plate: »1” x 10-1/4” »5/16” fillet welds (6” along each side, 10-1/4” along end) –Compression flange-plate: »13/16” x 12.5” »5/16” fillet weld (6” along each side) –No doublers or stiffeners required –$250 each
29
Breadth Study Construction Management Existing System $20,000 Alternative #1 $28,000 Alternative #2 $19,000 Total Cost of Connections (material, fabrication, & installation):
30
Breadth Study Construction Management –Alternative #2, with modified windows brick + $52,400.26 stone + $86,686.21 glass - $127,989. 76 total + $11,096.7 1 Building Envelope Costs (as compared to existing design):
31
Breadth Study Construction Management Existing System $162,361 Alternative #1 $142,359 Alternative #2 (with bracing exposed) $101,681 Alternative #2 (with modified windows) $112,780 Total Costs:
32
Breadth Study Mechanical –Carrier s “Hourly Analysis Program 4.2” (HAP) Mechanical system components –10 packaged water-cooled air conditioning units –2 cooling towers (1 for each unit) –3 hydronic unit heaters –2 hydronic cabinet unit heaters –1 electric unit heater –4 hot water boilers Current utility rates –Department of Energy s website
33
Breadth Study Mechanical –Results of HAP analysis: Annual energy costs savings = $2,856
34
Conclusions Existing System $162,361 Alternative #1 $142,359 Alternative #2 (with bracing exposed) $101,681 Alternative #2 (with modified windows) $112,780 Total Costs: $112,780 - $101,681 = $11,000 $11,000 / ($2,856/year) = 4 years
35
Conclusions Existing system is most expensive system studied Least expensive system to build has chevron braces left exposed Least expensive system over time has concealed chevron braces Modifying windows disrupts architectural aesthetics of building Moment frame system costs less than existing system, & preserves large windows For moment frame system, recommendation is to increase expansion joint to 2”
36
Thank You