Traci Peterson Structural Option Senior Thesis Presentation The Del Monte Center at The North Shore The Pennsylvania State University Department of Architectural.

Similar presentations


Presentation on theme: "Traci Peterson Structural Option Senior Thesis Presentation The Del Monte Center at The North Shore The Pennsylvania State University Department of Architectural."— Presentation transcript:

1 Traci Peterson Structural Option Senior Thesis Presentation The Del Monte Center at The North Shore The Pennsylvania State University Department of Architectural EngineeringSpring 2005

2 Outline of Presentation  Project overview  Depth Study –Redesign of lateral system  Architecture  Breadth Study –Construction management –Mechanical  Conclusions

3 The Del Monte Center at The North Shore 375 North Shore Drive, Pittsburgh, PA

4 Project Overview Pittsbu rgh's North Shore Location of Building

5 Project Overview  Building Statistics –Dates of Construction –Occupancy/Function –Size –Cost

6 Project Overview  Project Team –Continental/Nationwide Realty Investors –Strada –Continental Building Systems –Atlantic Engineering Services –Allen & Shariff Corporation –Limbach Facility services

7 Project Overview  Structural System –Frame –Foundation –Floor System

8 Project Overview 1” expansio n joint

9 Project Overview Location of Bracing: Fram e E Fram e D  Lateral System –Bracing (North-South Direction):

10 Project Overview  Bracing (East-West Direction) Fram e E Fram e D Frames A & D Frames B & E Frames C & F

11 Depth Study  Lateral System Redesign –Alternative #1 –Alternative #2  Exposed bracing  Modified windows

12 Depth Study  Design Criteria –Codes –Methods

13 Depth Study  Loads –Dead –Live –Snow –Wind –Seismic  Load combinations –1.4D –1.2D+1.6L+0.5S –1.2D+1.6S+(0.5L or 0.8W) –1.2D+1.6W+0.5L+0.5S

14 Depth Study  STAAD.pro 2002 –“Select Optimized” command

15 Depth Study  Existing System Total Weight of System = 426.7 k Frames A & D Frames B & E Frames C & F

16 Depth Study  Alternative #1- Moment Frames Total Weight of System = 358.5 k Frames A & D Frames B & E Frames C & F

17 Depth Study  Alternative #1- Moment Frames –Drift

18 Depth Study  Alternative #2- Full Bay Bracing Total Weight of System = 200.8 k Frames A & D Frames B & E Frames C & F

19 Depth Study  Results system total weight (kips) existing462.7 Alternative #1 (moment frames) 358.5 Alternative #2 (chevrons) 200.8

20 Architecture  Alternative #2- chevrons –Modified Windows –Exposed Bracing

21 Architecture  Alternative #2 with modified windows

22 Architecture  Alternative #2 with exposed bracing

23 Architecture

24

25 Breadth Study  Construction Management materia l erectio n total Existing system $121,6 21.47 $20,73 9.04 $142,36 0.51 Alternat ive #1 $102,1 65.09 $12,19 4 $114,3 59.09 Alternat ive #2 $57,228.57 $25,452.56 $82,68 1.13 Cost of Structural Steel W-shapes:

26 Breadth Study  Construction Management –Existing beam to column connections  Given: –Bolted double angle –ASTM A325 ¾”  slip-critical bolts –Designed for summation of: »½ uniform load capacity of member »10k axial force  Determined: –¼” angle –5 rows of bolts –$63 each

27 Breadth Study  Construction Management –Existing bracing connections  Given: –Bolted/welded shear end-plate connections –Fillet welds  Determined: –3/16” weld –2 rows of bolts –$55 each

28 Breadth Study  Construction Management –Moment connections  Determined: –Single-plate web connection: »3/8” x 12” »5 7/8”  bolts »2 5/16” fillet welds –Tension flange-plate: »1” x 10-1/4” »5/16” fillet welds (6” along each side, 10-1/4” along end) –Compression flange-plate: »13/16” x 12.5” »5/16” fillet weld (6” along each side) –No doublers or stiffeners required –$250 each

29 Breadth Study  Construction Management Existing System $20,000 Alternative #1 $28,000 Alternative #2 $19,000 Total Cost of Connections (material, fabrication, & installation):

30 Breadth Study  Construction Management –Alternative #2, with modified windows brick + $52,400.26 stone + $86,686.21 glass - $127,989. 76 total + $11,096.7 1 Building Envelope Costs (as compared to existing design):

31 Breadth Study  Construction Management Existing System $162,361 Alternative #1 $142,359 Alternative #2 (with bracing exposed) $101,681 Alternative #2 (with modified windows) $112,780 Total Costs:

32 Breadth Study  Mechanical –Carrier  s “Hourly Analysis Program 4.2” (HAP)  Mechanical system components –10 packaged water-cooled air conditioning units –2 cooling towers (1 for each unit) –3 hydronic unit heaters –2 hydronic cabinet unit heaters –1 electric unit heater –4 hot water boilers  Current utility rates –Department of Energy  s website

33 Breadth Study  Mechanical –Results of HAP analysis:  Annual energy costs savings = $2,856

34 Conclusions Existing System $162,361 Alternative #1 $142,359 Alternative #2 (with bracing exposed) $101,681 Alternative #2 (with modified windows) $112,780 Total Costs: $112,780 - $101,681 = $11,000 $11,000 / ($2,856/year) = 4 years

35 Conclusions  Existing system is most expensive system studied  Least expensive system to build has chevron braces left exposed  Least expensive system over time has concealed chevron braces  Modifying windows disrupts architectural aesthetics of building  Moment frame system costs less than existing system, & preserves large windows  For moment frame system, recommendation is to increase expansion joint to 2”

36 Thank You


Download ppt "Traci Peterson Structural Option Senior Thesis Presentation The Del Monte Center at The North Shore The Pennsylvania State University Department of Architectural."