MyFloridaMarketPlace CRB Meeting MFMP 2.0 Upgrade Status February 23, 2007
2
Page 2 Agenda Review Summary status of upgrade Review Project lifecycle with highlights Review Timeline going forward MFMP 2.0 Training Review results of System Administrator Update on status of Agency training Requester training overview Target audience Confirmation process UAT Status Attendance verification Issue review with priority Status against UAT exit criteria Plan forward – retesting on 2/27 & 2/28 Performance Testing Overview of the process Preliminary results MFMP 2.0 implementation/contingency planning Go/No go criteria Readiness checklist Communication approach Overview of migration weekend
3
Page 3 MFMP 2.0 Upgrade – Plan Status Plan AccomplishmentsIn progressUpcoming Development of 7.1 customized components Review of 8.2 test conditions System Test Pass 1 - 3 Workflow analysis Change Request evaluation Final upgrade scope Design of new key groups/roles/permissions Reporting assessment CR Designs/Development Go Decision – 1/19/07 UAT Training SA Training o Agency Training o UAT Resolution & Retest o Performance Testing/Tuning o Implementation planning Go/No go decision for April 07 3/01/07 3/29/07 Requester Training MFMP 2.0 go-live dress rehearsal (3/5 & 3/19) MFMP 2.0 cutover weekend (3/30-4/2) Test Technical Infrastructure Build Design Deploy 4/2/07 Train
4
Page 4 MFMP 2.0 Upgrade – Plan Dates
5
Page 5 MFMP 2.0 Training System Administration & User Acceptance Training 59 System Administrators trained from 27 agencies 26 testers trained from all CRB agencies Agency training 6 of 27 agencies trained (21%) Over 200 people in the 6 agencies trained Averaging 4.4 out of 5 for satisfaction on training feedback Requester training overview 700 + Registered for training Target audience Infrequent user Requester specific Registration process Web site registration – limited functionality Confirmation process MFMP 2.0 Training
6
Page 6 User Acceptance Testing (UAT) UAT Status Attendance verification Issue review with priority Status against UAT exit criteria Plan forward – retesting on 2/27 & 2/28 Cycle 1 of UAT Complete, Cycle 2 in 2 days
7
Page 7 MFMP 2.0 UAT Exit Criteria IDCriteriaDescriptionInitiatedTarget CompletionActual Completion 1Successful Execution Of Test Conditions for Modified Groups/Roles/ Permissions Review of available functionality and workflow based on newly defined user security structure through system administrator training and acceptance 12-Feb-0716-Feb-07 2Resolve and Close all Blocker and Major Issues identified in UAT Issue resolution will begin 19-Feb-0719-Feb-0728-Feb-07 3Resolve issues that have been mutually determined critical to go- live Issue resolution will begin 19-Feb-0719-Feb-072-Mar-07 4No more than 30 open moderate issues remaining with a corrective action plan for completion SIR resolution will begin 22-Jan-0722-Jan-0728-Feb-07 5No more than 50 open minor issues with a corrective action plan for completion SIR resolution will begin 22-Jan-0722-Jan-0728-Feb-07 6 Obtain UAT sign-offObtain UAT sign-off from UAT user participants 19-Feb-0728-Feb-07 7Obtain UAT sign-offObtain UAT sign-off from Project Director 28-Feb-07
8
Page 8 MFMP 2.0 Performance Testing Summary Performance Testing Overview of the process Testing using tools that simulate production activity Testing for peak load (+) on system, based on the last year activity and specifically FY06 Year End Testing on production hardware Executing between 2/19/07 - 3/29/07 Exit Criteria Two seconds or less average screen to screen response time for common transactions during peak load In 1 hour, complete 200 DO and 190 IR
9
Page 9 MFMP 2.0 Implementation Planning MFMP 2.0 implementation/contingency planning Go/No go criteria 3/1 – Successful System Test and UAT 3/30 – Successful performance test and conversion dress rehearsals Readiness checklist Communication sent on 2/20 to Agency Purchasing and F&A Liaisons Posted to the toolkit: MFMP 2.0/Deployment section Communication approach Starting 2/23 - weekly communications to all users regarding MFMP 2.0 Updates during the conversion weekend will be provided via 1-866-352-3776 MFMP Customer Service Desk will be available 4/2-4/6 from 7:00 AM to 7:00 PM Overview of migration weekend System down at 6:00 PM Thursday, 3/29/07 MFMP 2.0 available 7:00 AM Monday, 4/2/07 25 business days until MFMP 2.0!
10
Page 10 Contingency Planning – Our Plan B! Contingency planning is necessary! Confirmed short term back up plans last CRB (see below) Communication during the execution of a back up plan is critical! Only if necessary, we have an alternate go-live date for MFMP 2.0 4/9/2007 Same transition weekend approach applies – down Thurs after business day and until Monday 4/9/07 Only if necessary we will take an extra day to convert (e.g., include Monday, 4/2 as a non-operational day and go-live on 4/3) What is an alternate launch date after the fiscal year? Initial input = October We will address only if required
11
Page 11 Any closing discussion Cancel the 3/13 CRB Reschedule for 3/29 to discuss final Go/No-Go checkpoint Meeting could either be in person or conference call What’s Next? Thank you! 25 business days until MFMP 2.0!