Z. Papandreou, GlueX Collaboration Meeting, May 11, 2009 1 BCAL Construction First Article work has begun: crew in place
2
Z. Papandreou, GlueX Collaboration Meeting, May 11, 2009 2 Teams JLab Eugene Chudakov, Elton Smith, Tim Whitlach, … Regina George Lolos, Zisis Papandreou, Dan Kolybaba, Keith Wolbaum, Andrei Semenov, students Alberta James Pinfold, Jan Soukup, Gilbert Lachat, Richard Soluk Ross Machine Shop Kevin Lorenz At a glance… Contracts Vendors Fibers: Quality Assurance Mechanical issues Construction preparations Logistics Crew Looking ahead Overview
3
Z. Papandreou, GlueX Collaboration Meeting, May 11, 2009 3 Construction MOU is done First Article - PO (49th module) Full Contruction - RFP (48 modules) Contracts “The mother of all prototypes”
4
Z. Papandreou, GlueX Collaboration Meeting, May 11, 2009 4 Timetable First Article Delivery: Oct 2, 2009 First Four Modules: Feb 10, 2010
5
Z. Papandreou, GlueX Collaboration Meeting, May 11, 2009 5 Fiber Test Preparations Kuraray Contract SCSF-78MJ; (410cm -0/+4)cm 780,590 fibers; maybe too few? First article tests: A. Semenov’s talk (next) New Fibers QA protocol Attenuation length: (a few % of fibers) use photodiode/PMT, measure current use spectrophotometer for select cases setup upgrades: parts; manual scan, eventually automatic Photoelectrons: 90 Sr; SiPM/PMT, manual scan, auto in future Anchor back to Kuraray’s results on attenuation length Fiber track
6
Z. Papandreou, GlueX Collaboration Meeting, May 11, 2009 6 Detector Lab p.e. Module DAQ UV LED fiber coffin SiPM
7
Z. Papandreou, GlueX Collaboration Meeting, May 11, 2009 7 Construction Preparations Facilities Construction 1300 ft 2 ; Fiber & Sensor QA 1100 ft 2 Press/Fiber Sorting area: ready Swaging area: blueprints+safety done, complete on June 1 Detector lab: ready Underground lab: ready Personnel Construction Manager: Dan Kolybaba Undergraduates: Brent Giesbrecht, Shaun Krueger, Lee Sichello (UofR - CoOp), Aimee Heinrichs (UofC), Alana Watson (UofR) Trainers: Kathryn Janzen, George, Zisis Fall 2009: CoOp/Engineering Interships - Interviews May 20 Materials Incidentals: ready Fibers, Lead, Epoxy: timetables in progress
8
Z. Papandreou, GlueX Collaboration Meeting, May 11, 2009 8 Construction Space Layout Main Machine Shop Group Office Swaging Press Fibers Dan Optimal Arrangement! Machine Shop Shop storage Loading Dock, Science Stores
9
Z. Papandreou, GlueX Collaboration Meeting, May 11, 2009 9 Swaging Roller gap adjustments Short & Long lead strips swaged Built test matrix samples Lead Precut to width Rolled or in sheets Purity, uniformity,cleanliness Drop shipped First Article: using surplus lead; major effort: 2 weeks to just clean & cut Safety HEPA vacuum for lead clean up; time consuming and disposal Ventilation, electrical, escape routes wedge gap
10
Z. Papandreou, GlueX Collaboration Meeting, May 11, 2009 10 Cal Babies Small samples: Test roller gap Stack tolerances Unpopulated grooves Clamp-press Fiber pitch
11
Z. Papandreou, GlueX Collaboration Meeting, May 11, 2009 11 Press Frame Located in Edmonton: Disassembly, strapping Crating, shipping Space is ready in Regina Commissioning: Orientation, leveling, retrofitting (gauges), reactivation Target date: June 1 Second press will be built after full contract has been signed
12
Z. Papandreou, GlueX Collaboration Meeting, May 11, 2009 12 Ross Machine Shop “Big Machine” Levelling-indexing Polish ends Taper sides 4 modules at a time “Small machine” Mechanical Liaison Dan Kolybaba at UofR and Kevin Lorenz at Ross Cost Quotes 49th Al plates: this week; machine end of May Fac. of Science Shop
13
Z. Papandreou, GlueX Collaboration Meeting, May 11, 2009 13 Mechanical Issues Regular teleconferences (UofR, JLab, Ross) Engineering drawings that are complete: Aluminum Base and Inner plate BCAL wedge drawings Press frame Other tasks: Module leveling: done Lead storage: in progress Lift-off/Installation? Transport crates construction 2 ton “Cherry Picker”
14
Z. Papandreou, GlueX Collaboration Meeting, May 11, 2009 14 Logistics & Paperwork Transportation Fibers & Lead will be drop shipped to Regina Regina-Newport News Quotes received from two companies Return crates & support beams from NN to Canada? Customs Vendors are responsible for import to Canada Regina is responsible export to USA HST Number 8544.70.90.00 ! (48 times the first module) Paperwork Drawings are complete Construction MOU is done Contract for First Article module has been awarded RFP: Budget for 48 module construction is in progress Regina is a DOE ‘approved non-domestic sole source’ QA Plan - in progress Safety documentation - in progress (Dan & Safety Officer) Student Job ads - ongoing
15
Z. Papandreou, GlueX Collaboration Meeting, May 11, 2009 15 Summary Lead cutting is underway Swaging starts week of May 19 Awaiting fibers and precut lead Fiber First Article checks and report Awaiting Full Construction Contract We’re rock-and-rolling!