Presentation is loading. Please wait.

Presentation is loading. Please wait.

The Status of ESS Accelerator Shielding and Accident Scenarios Lali Tchelidze www.europeanspallationsource.se May 26, 2014.

Similar presentations


Presentation on theme: "The Status of ESS Accelerator Shielding and Accident Scenarios Lali Tchelidze www.europeanspallationsource.se May 26, 2014."— Presentation transcript:

1 The Status of ESS Accelerator Shielding and Accident Scenarios Lali Tchelidze www.europeanspallationsource.se May 26, 2014

2 Outline Prompt radiation shielding design criteria. Accidental cases. Shielding results (with an attention to earth berm shielding on top of the linac). – Skyshine radiation. Conclusions. 2

3 November 2013 Review Recommendations related to beam loss and shielding : ”Basic assumption of 1 W/m used for shielding calculations needs to be confirmed by realistic end-to- end beam simulations, showing sufficient margin. Normal operations scenario should include accidental beam loss scenarios.” “Accidental beam loss: need to establish “worst case” scenarios based on risk analysis and to conduct simulations to determine appropriate shielding and system interlocks for personnel protection.” 3

4 Event classes and exposure limits at ESS Frequency (1/y)NameLimit to rad workersLimit to public H1> 1Normal operation10 mSv/y0.05 mSv/y H210 -2 - 1Anticipated events20 mSv/event0.5 mSv/event H310 -4 - 10 -2 Unanticipated events50 mSv/event5 mSv/event H410 -6 - 10 -4 Design basis accident (DBA) 50 * mSv/event20 mSv/event 4 * Used to be 100 mSv, until SSM (Swedish Radiation Safety Authority) asked to reduce the limit.

5 Normal operation H1 Limit is driven by requirements for activation/hands-on maintenance limits. Adopt 1 W/m (SNS specification above 100 MeV) – dose rates below ~1 mSv/h measured at 30 cm from component surface for 100 day/4 hour irradiation/cooling condition. 1.1 mSv/h At 30 cm 1 W/m 1 GeV protons on beam pipe 100 days/4 hours. FLUKA simulations from I. Strasik et al., Phys. Rev. ST AB 13, 2010. 5

6 Anticipated events H2 Adopt 30 MJ beam spill (LANSCE design criterion) – A burn through at LANSCE at 800 MeV proton coupled cavity linac occurred with an estimated 40 J of beam spill. – At PSI, at 600 MeV proton beam experience showed that leak at vacuum seal occurred at deposited energies of 30 kJ. – TJNAF (Thomas Jefferson National Accelerator Facility), 10 MJ energy spill. – No spill events greater than 10 MJ were identified! 6

7 Beam Spill Limits Summary Comparing (accidents) LANSCE 1.7 mSv/MJ TRIUMF 2.2 mSv/MJ SLAC 0.6 mSv/MJ ESS 0.08 mSv/MJ Frequency (1/y)NameDescriptionExposure limit > 1Normal operation1 W/m10 mSv/y 10 -2 – 1Anticipated events30 * MJ/event20 mSv/event 10 -4 – 10 -2 Unanticipated events 150 * MJ/event50 mSv/event 10 -6 – 10 -4 Design basis accident (DBA) 600 * MJ/event50 mSv/event 3 μSv/h for normal operation 7 * LANSCE design criterion

8 Accident duration as a function of lost beam power 8

9 Outcome of the recommendations 1.Beam spill limits for all event classes H1 – H4 (normal operations – incidents of various types) – ESS-0008309 “Beam Spill Limits for Various Event Classes”. – ESS-0008351 “Hands-on Maintenance Conditions at ESS Accelerator”. Both documents reviewed and approved at SAG. Final step – get an approval at EPG – Scheduled for 2/6/2014. – This will close this recommendation. 9

10 Tools used Verifying that 5 m earth berm shielding is sufficient for all types of events. – Analytical approach. – Monte-Carlo simulations code MARS. 10

11 Normal operation 1 W/m “Sullivan”-s analytic approach Lateral shielding for 1 W/m beam loss. – H=(H 0 /R) exp(-t/0.94λ) – H 0 is a source term, representing a dose equivalent per interacting proton, at 1 m from the interaction point and no attenuation, equals to 0.4 Sv/h. – λ is a hadron attenuation mean free path – t is a thickness of a shield – R is a distance from beam loss to outside of the shield. 5 m earth berm – 0.26 μSv/h (limit is 3 μSv/h). 11

12 Normal operations 1 W/m Monte-Carlo simulations Geometry: – Linac tunnel, tunnel walls and earth berm around it. – Klystron gallery building. – Waveguide penetrations. – Cable penetrations. – Personal emergency exits. – HEBT loading bay. – Smoke evacuations. – Alignment penetrations. – Cryogenic transfer line. 12

13 Earth berm thickness Normal Operation 5 m earth berm - max 8 μSv/h (limit is 3 μSv/h) Berm will be fenced! -Linac length – 450 m. -Proton beam energy 5 MeV – 2 GeV. -Loss distribution: 1 W/m upwards at 3 mrad angle on a 2 mm stainless steel beam pipe. -Tunnel concrete roof thickness – 70 cm. 13

14 Accidents – Analytical solution -Point beam loss is considered: -H=H 0 /R 2 e(-t/λ) -H 0 is a source term, representing a dose equivalent per interacting proton, at 1 m from the interaction point and no attenuation, equals to 1.2 Sv/h. -λ is a hadron attenuation mean free path -t is a thickness of a shield -R is a distance from beam loss to outside of the shield. -5 m earth berm - 17.2 μSv/MJ max dose rate outside of earth berm. -Equivalent to 0.31 Sv/h for full point beam loss. 14

15 Accidents – Monte-Carlo results -Point beam loss upwards with a shallow angle at 2 GeV proton beam energy. -127.8 μSv/MJ max dose rate outside of earth berm. -Equivalent to 2.3 Sv/h for full point beam loss. DET (mSv/h) Side view 15

16 Shielding results - summary NameDescriptionWith 5 m berm (Anal.) With 5 m berm (MC) Exposure limit Normal operation 1 W/mNo limit1250 h limit10 mSv/y Anticipated events 30 MJ/event0.5 mSv/event3.8 mSv/event 20 mSv/event Unanticipated events 150 MJ/event2.6 mSv/event19.2 mSv/event 50 mSv/event Design basis accident (DBA) 600 MJ/event10.3 mSv/event76.8 mSv/event 50 mSv/event No Access on top of berm during operation! 16

17 Earth berm thickness Current observations. -From the accidental prompt dose rate consideration point of view: -The top of the berm has to have no access during operations! -Or the amount of earth berm thickness has to be increased. 17

18 Skyshine Close to public limit (5.7 nSv/h or 50 µSv/y) at the site boundary. Skyshine radiation around ESS site (contribution from the linac, excluding the A2T, 2013) 18

19 Earth berm thickness Current observations. -From the accidental prompt dose rate consideration point of view: -The top of the berm has to have no access during operations! -Or the amount of earth berm thickness has to be increased. -From the skyshine prompt dose rate consideration point of view: -The amount of earth berm thickness might need to be increased. -We are building an accelerator tunnel allowing placement of up to 7 meters of earth berm on top of it if necessary! 19

20 Preliminary to detailed shield design -Things that affect the final shielding configuration: -Level of details in the geometry description. -Accelerator component and shield material - material’s composition. -Beam loss assumptions. -We expect the total berm thickness to decrease in the detailed design stage, but as a back-up strategy we have a possibility of increasing the thickness to 7 meters. 20

21 Sensitivity to linac components (Example) DET (mSv/h) Side view across the tunnel. 2 mm stainless steel 20 cm copper A factor of 5-10 less total dose equivalent outside of berm shielding when a bulk copper is considered! 21

22 Shielding towards the klystron gallery DET (mSv/h) Top view at 2 m < 0.1 µSv/h with no penetrations. 54 µSv/h max – with penetrations and no extra shield. 3 µSv/h max – with penetrations and extra shield block. Equivalent to 28.8 mSv/event for DBA (limit – 50 mSv). 22

23 Outcome of the recommendations 1.Beam spill limits for all event classes H1 – H5 (normal operations – incidents of various types) – ESS-0008309 “Beam Spill Limits for Various Event Classes”. – ESS-0008351 “Hands-on Maintenance Conditions at ESS Accelerator”. Both documents reviewed and approved at SAG. Next/final step – get an approval at EPG. 2.Shielding reports. Normal operations: Technical note ESS-0007143 “ESS Linac Shielding Strategy and Calculations” – reviewed and approved internally and externally (March, 2013). Accidental cases: Technical note ESS-0011759 ” Earth berm shielding for accidental beam losses” – reviewed internally. 23

24 Summary Recommendation about establishing accident scenarios and assigning beam spill limits to them. (ESS-0008309 & ESS-0008351) Recommendation about verifying that the earth berm shielding is enough for accident scenarios. (ESS-0007143 & ESS-0011759 ) 24

25 Thank you!


Download ppt "The Status of ESS Accelerator Shielding and Accident Scenarios Lali Tchelidze www.europeanspallationsource.se May 26, 2014."

Similar presentations


Ads by Google