1
Software Measurement and Analysis Team Assignment 13 Team 04
2
Agenda Member Introduce Combination of Wideband Delphi to generates schedule, budget and resource 1 2 3 4 Estimates for the Viking project
3
Members NameRole Hoàng Thị Kim DângLeader Thái Thanh NhãSub Trần Tiễn HưngMember Từ Huỳnh ThắngMember Chu Thị Thu HươngMember Trần Thị Mộng HàMember
4
Agenda Member Introduce Combination of Wideband Delphi to generates schedule, budget and resource 1 2 3 4 Estimates for the Viking project
5
Traditional Schedule Big Requirements Up Front Use WBS to decompose the project into tasks Use Estimating Technique to estimate tasks Expert Judgment (Wideband Delphi) Re-estimating (when more is known) is often not done Must estimate each change, or re-estimate project if f enough change occurs Introduce
6
Agenda Member Introduce Combination of Wideband Delphi to generates schedule, budget and resource 1 2 3 4 Estimates for the Viking project
7
WBS for Viking project
8
Wideband Delphi Assumptions established by team Team discusses assumptions where estimates vary Goal: Team working with same & correct assumptions Estimates for the Viking project
9
Agenda Member Introduce Combination of Wideband Delphi to generates schedule, budget and resource 1 2 3 4 Estimates for the Viking project
10
List all task of Viking project ( base on WBS ) Members estimate time (hour) to complete the task. Members check each other estimate, and adjust to be more suitable and explain in Assumption. After that, teams discuss each task to find the best estimated time for the task. Combination of Wideband Delphi
11
When we have estimated numbers, we will calculate as below: Because > 10 tasks, so team using a complex standard deviation calculation: Compute the SD of each task (or feature): Individual SD = (IndividualWorstCaseEst- IndividualBestCaseEst)/6 Compute each task’s variance: Task variance = Task’s SD 2 Total the variances Take the square root of the total Combination of Wideband Delphi
12
% Confidence Calculation 2% Expected Case - (2 *Standard Deviation) 10% Expected Case - (1.28 * Standard Deviation) 16% Expected Case - (1 * Standard Deviation) 20% Expected Case - (.84 * Standard Deviation) 25% Expected Case - (.67 * Standard Deviation) 30% Expected Case - (.52 * Standard Deviation) 40% Expected Case - (.25 * Standard Deviation) 50% Expected Case 60% Expected Case + (.25 *Standard Deviation) 70% Expected Case + (.52 * Standard Deviation) 75% Expected Case + (.67 * Standard Deviation) 80% Expected Case + (.84 * Standard Deviation) 84% Expected Case + (1 * Standard Deviation) 90%Expected Case + (1.28 * Standard Deviation) 98%Expected Case + (2 * Standard Deviation) Combination of Wideband Delphi
13
% ConfidenceCalculationEffort estimate (hours) 2%Expected Case - (2 *Standard Deviation)1120,4272 10%Expected Case - (1.28 * Standard Deviation)1131,0734 16%Expected Case - (1 * Standard Deviation)1135,2136 20%Expected Case - (.84 * Standard Deviation)1137,5794 25%Expected Case - (.67 * Standard Deviation)1140,0931 30%Expected Case - (.52 * Standard Deviation)1142,3111 40%Expected Case - (.25 * Standard Deviation)1146,3034 50%Expected Case1150 60%Expected Case + (.25 *Standard Deviation)1153,6966 70%Expected Case + (.52 * Standard Deviation)1157,6889 75%Expected Case + (.67 * Standard Deviation)1159,9069 80%Expected Case + (.84 * Standard Deviation)1162,4206 84%Expected Case + (1 * Standard Deviation)1164,7864 90%Expected Case + (1.28 * Standard Deviation)1168,9266 98%Expected Case + (2 * Standard Deviation)1179,5728 Combination of Wideband Delphi
14
% ConfidenceCalculationBudget estimate 2%Expected Case - (2 *Standard Deviation)1409661.2831 10%Expected Case - (1.28 * Standard Deviation)1436819.2212 16%Expected Case - (1 * Standard Deviation)1447380.6416 20%Expected Case - (.84 * Standard Deviation)1453415.7389 25%Expected Case - (.67 * Standard Deviation)1459828.0299 30%Expected Case - (.52 * Standard Deviation)1465485.9336 40%Expected Case - (.25 * Standard Deviation)1475670.1604 50%Expected Case1485100.0000 60%Expected Case + (.25 *Standard Deviation)1494529.8396 70%Expected Case + (.52 * Standard Deviation)1504714.0664 75%Expected Case + (.67 * Standard Deviation)1510371.9701 80%Expected Case + (.84 * Standard Deviation)1516784.2611 84%Expected Case + (1 * Standard Deviation)1522819.3584 90%Expected Case + (1.28 * Standard Deviation)1533380.7788 98%Expected Case + (2 * Standard Deviation)1560538.7169 Budget
15
% ConfidenceCalculationEffort estimate 2%Expected Case - (2 *Standard Deviation)36 10%Expected Case - (1.28 * Standard Deviation)37 16%Expected Case - (1 * Standard Deviation)37 20%Expected Case - (.84 * Standard Deviation)37 25%Expected Case - (.67 * Standard Deviation)37 30%Expected Case - (.52 * Standard Deviation)37 40%Expected Case - (.25 * Standard Deviation)38 50%Expected Case38 60%Expected Case + (.25 *Standard Deviation)38 70%Expected Case + (.52 * Standard Deviation)39 75%Expected Case + (.67 * Standard Deviation)39 80%Expected Case + (.84 * Standard Deviation)39 84%Expected Case + (1 * Standard Deviation)39 90%Expected Case + (1.28 * Standard Deviation)39 98%Expected Case + (2 * Standard Deviation)40 Resource
17
Thanks for your listening!!