1
Work package 3 Analysis of international MSP Instruments Sophie Jacques 3E Support by: Offshore Wind Power in Italy SEANERGY 2020 project Andrea Marchisio APER Italian Renewable Energy Association Supported by
2
Support by: THE SEA AROUND ITALY [CESI Ricerca]
3
Support by: OFFSHORE WIND POWER POTENTIAL IN ITALY SHALLOW WATER (0 m to 30 m) Region Most promising areas [km2] Estimated capacity [MW]Estimated production [GWh/year] Molise0 - 80 - 500 - 100 Apulia75 - 155500 – 1.0001.400 – 2.800 Sicily30 - 60200 - 400600 – 1.200 Sardinia30 - 70200 - 450700 – 1.500 TOTAL135 - 293900 – 1.9002.700 – 5.600 TRANSITIONAL WATER (30 m to 60 m) Region Most promising areas [km2] Estimated capacity [MW]Estimated production [GWh/year] Sicily0 - 400 - 2500 - 800 Sardinia40 - 75250 - 500800 – 1.700 TOTAL40 - 115250 - 750800 – 2.500 DEEP WATER (60 m to 900 m) Region Most promising areas [km2] Estimated capacity [MW]Estimated production [GWh/year] Apulia75 - 155500 – 1.0001.600 – 3.300 Sicily75 - 155500 – 1.0001.600 – 3.300 Sardinia155 - 3101000 – 2.0003.500 – 7.000 TOTAL305 - 6202.000 – 4.0006.700 – 13.600 [CESI Ricerca]
4
Support by: Offshore wind power target at 2020 [Italian NREAP] 680 MW Today installed 0 MW Total capacity of projects under EIA 1.127 MW INSTALLATION TARGET
5
Support by: Support scheme: up to 2013 -> TGCs ; 1 MWh offshore = 1,5 TGC after 2013 -> Competitive price-based tenders Lack of MSP Many subjects involved on permitting In the past, not clear “who-licenses-what” POLICY AND LEGAL FRAMEWORK
6
Support by: NATIONAL COMPETENCE REGIONAL COMPETENCE 387/2003 & 152/2006 244/2007 4/2008 99/2009 The offshore wind farms permitting and EIA are granted by the State (up to now..) PERMITTING AND LICENSING: a brief history Authorization EIA Authorization
7
Support by: PERMITTING AND LICENSING Public Maritime Domain (Navigation Code) granted in concession by the Ministry of Transport through Port Authorities - Compatibility with other maritime activities - Interference with bound navigation routes - Benefits of the initiative Autorizzazione Unica [Single Authorization] granted by the Ministry of Transport (after consultation with the Ministry of Economic Development and the Ministry of Environment) Environmental Impact Assessment granted by the Ministry of Environment (after hearing the Ministry of Cultural Heritage)
8
Support by: Permitting procedure too burdensome Operators must gather more than 40 opinion Binding judgment of Ministry of Cultural Heritage on projects Port Authorities are a military body, lack of competence on wind offshore Regions can delay the conclusion of the permitting procedure No tool which gathers useful info for operators BARRIERS TO DEVELOPMENT
9
Support by: THANKS FOR YOUR ATTENTION Offshore Wind Power in Italy Via Pergolesi, 27 20124 Milano - Italy tel. +39.02.6692673 fax +39.02.67490140 marchisio@aper.it