® August 12, 2009 MTAC General Session August 12, 2009 MTAC General Session Update
2
Agenda Flat Volume Update Program Status ● Deployment Transition to Operations FSS Redirection Update (Phase 1A) Questions
4
Flat Volume Trend 2001 - 2008 RPW FY 2008 vs. 2007 Flat Vol. Decline -11.1% FY07 & FY08 -7.2 Billion Flats FY07 & FY08 -7.2 Billion Flats FY 2007 vs. FY 2006 Flat Vol. Decline -2.6%
5
Flat Volume Trend by Month - FY 2009 RPW -19% +.4% -5% -23% -20% -12% -16% -21% -12%
6
Flat Volume - June FY 2009 RPW -8% -14% -12%
7
Flat Volume by Class - FY 2009 RPW FY 2009 YTD Total Flat Volume Decline - 14% FY 2009 YTD Total Flat Volume Decline - 14% -15.5% -15.6% -6.7%
9
Program Status – Deployment FSS deployment in progress ●Installations & ramp-up continues ●Overall timeline revisions to include redirections Training systems complete - NCED ●Maintenance training starting Field readiness on target ●Focus on preparation and transition to operations
10
Sequencing on 3 FSS 4 th FSS undergoing retrofits Complete mid September Sequencing flats for 37 delivery units & 1,103 routes Route adjustments in FSS offices have eliminated full-time routes Downsized casing equipment capturing delivery space Delivery vehicles have been freed up for redeployment Transition to operations – Dulles VA
11
Columbus – sequencing on FSS #1 since June Sequencing flats for 15 delivery units & 479 routes Route adjustments in progress Columbus FSS # 2 Installation complete Test deck runs complete Begin ramp-up to operations August 9 th Transition to operations – Columbus
12
Kansas City FSS #1 Installation complete Test deck runs complete Begin ramp-up to operations August 28 th Transition to operations – Kansas City Kansas City FSS #2 Installation in progress 73% complete
13
Phoenix (West Valley) FSS #1 - i nstallation complete Test deck runs scheduled August 10 th Begin ramp-up to operations August 30 th Transition to operations – Phoenix (West Valley) FSS # 2 Install 79% FSS # 3 Install 53%
14
Program Status – Moving Forward Finalizing revised deployment / installation schedule Referring to deployment as Phase 1 & 1A ●Phase 1 – original 32 FSS sites ●Phase 1A – redirected FSS sites Starting operational planning for Phase 1A sites
16
Redirection Plan is Complete ● Space reviews complete ● Workroom floor / machine layouts finalized Communication plan in progress ● Assessment of stakeholder level of notification Internal External ● Message, timing & distribution Phase 1A Status – Redirection Plan
17
Industry notification - resources ● MTAC Update ● RIBBs “All things FSS” New FSS locations Zone changes ● PCC Insider Timeline for sharing Phase 1A Plan ● No later than the end of August Phase 1A – Industry Communication
18
National Postal Forum ® ®
19
NPF 2010 – Flats Track Combined Flats Track again this year: “Flats Track for Periodicals, Catalogs and Printers” Certificate program well received Expand offering based on participant’s feedback ● Printers ● Catalogs Reminder – “call for papers” ● Deadline – August 21 st
20
Conclusion