Download presentation
Presentation is loading. Please wait.
Published byLizbeth Greer Modified over 9 years ago
1
ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011 www.rbdck.com
2
Project Details 2 Total Length-423m Carriage way width -7.5m Foot path-1.5m wide on one side only Railway span-42m (ie 11.27+21+10.53) Approach span-134m( 26+4x27) Solid ramp portion Pulikkakadavu side-107m,RE wall-71.65m NH side -140m,RE wall-76m Site Engineer :Santhosh G,KITCO Manager :Jemymathew, RBDCK,9447078783
3
3 Consultant: KITCO Ltd Contractor : Cherian Varkey Construction Company Pvt Ltd Manager in Charge RBDCK: JemyMathew, Contact No. 9447078783 Project Engineer KITCO :Santhosh G Contact No: 9447384217 Site Engineer CVCC: Shaji.M,Contact No:9747004340 Site Engineer :Santhosh G,KITCOManager :Jemymathew, RBDCK,9447078783
4
Progress graph as on 3.6.2011
5
5 SlNo Activity - Description Total Quantity Cumulative progress up to this week (1) Balanc e work (2) Cumulative delay in weeks after Spplagmnt (3) Work plan ned during the week (4) Actual work done during the last week (5) Short fall in the last week (6) Work Planned for next week (7) No of days remaing for completion as per the weekly plan Remarks 1 Re wall towards NH side 100%346627RR work000 19. 3 Approach Span 5 4133---- 4Pier cap2no1336 0 0 0 0 18 5 Pile (Rly)pulikakadavu side 4 4 555 00 0 002 6Pile (Rly)Nh side44555000002 7 Piers (Rly) 2No1346 0 0 0 0 2 nd lift of pier concreting at p1 completed
6
SlNo Activity - Description Total Quantity Cumulative progress up to this week (1) Balanc e work (2) Cumulative delay in weeks after Spplagmnt (3) Work plan ned during the week (4) Actual work done during the last week (5) Short fall in the last week (6) Work Planned for next week (7) No of days remaing for completion as per the weekly plan Remarks 8 R0AD WORK {WBM} towards pulikkakadavu side 100% 90% 0 9 GIRDER (LAND SPAN) P2-P3 span 331100 41 1 st stage stressing over 10P2-P3 span Shuttering of deck slab Concreting of deck slab P2-P3 shutterin g work of the deck slab of P2-P3 in progress Concretin g of deck slab on 10-6- 2011 Heavy rain hampering the work in P2-P3 Span 11 Diaphram wall (P2-P3) Reinforcement work completed Concreting of end diaphragms Concreti ng of two end diaphrag ms complete d successf ully Work completed as planned 12 RR work in the approach portion of Nh side 50 Re wall,Kerb and hand rail towards Pulikkakadavu side completed
7
Activities which cannot be completed without caution 1Pile 10Nos Pier - 2Nos Pier Cap-2 Nos Deck - 3slab
9
Material Stocking Status Coarse Aggreagate (m3)1230Remarks Fine Aggreagate(m3) 13 20. Cement(bag) 25 34 Steel(MT) 7 11 Utility shifting Utilities to be shiftedStatusRemarks BSNL KSEB no hindrance KWA. Others No hindrance i
10
10 Site Engineer :Santhosh.G KITCO Manager :Jemymathew, RBDCK,9447078783 DATE28-5-201130-5-201131-5-201101-06-201102-06-201103-06-2011 Weather hotHotsunny RAINY Climate Labour Details Date Labours RR work at P1 Span P2-P3 Beam work Mechani c and operator s Pier reinforceme nt Total 28-05-201100114015 30-5-201100124016 31-5-201100114016 01-6-201106123021 02-6-.201106123021 03-6-201106123021
11
z Sl. No DateActivity 128-5-20111.Concreting of 1 st end diaphragm of span P2-P3 2.Shuttering work of deck slab of span P2-P3 230-5-20111.Concreting of 2 nd end diaphragm of span P2-P3 2.Shuttering work of deck slab of span P2-P3 331-5-.2011 1.Shuttering work of deck slab of span P2-P3 401-06- 2011 1.Shuttering and reinforcement work of deck slab of span P2-P3 2. RR masonry work near P1 location. 5656 02-6-2011 3-6-2011 1.Shuttering and reinforcement work of deck slab of span P2-P3 2. RR masonry work near P1 location.. 1.Shuttering and reinforcement work of deck slab of span P2-P3 2. RR masonry work near P1 location. Daily Activity Report
12
Work Done during last month Sl NoActivity Week 1 up to 6.6.2011 3 rd Girder of P3-P2 span concreting Week 2 up to 13.6.2011 1)Concreting of Pier P1 Ist lift (Approximately 2m) done. 2)Premix bituminous work Ist layer completed at Pulikkakadavu side at the approach portion. Week 3 up to 20.6.2011 1) 1 st stage stressing completed for all three beams of the span P2-P3 2)Reinforcement and shuttering work of Cross beam or end diaphragm of the span P2-P3 3)Grouting of the ducts of all the beams in the span P2-P3. Week 4 up to 27.5.2011 RR work and 2 nd lift of Pier P1 Week 5 up to 3.6.2011 Diaphram wall concreting and RR work,Stagging work of deck slab
13
SHUTTERING OF DECK SLAB AT P2-P3
14
END DIAPHRAGM CONCRETE P2-P3 SPAN
15
SHUTTERING WORK OF DECK SLAB P2-P3 SPAN
16
HEAVY RAIN AT KORATTY
17
RR MASONRY AT P1-1.6.2011
18
RR MASONRY AT P1 2.6.2011
19
SHUTTERING OF DECK SLAB AT P2-P3
21
Thank you
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.