Housing and Development Forum February 24, 2014 Hearing Timelines
2
Land Use and Planning Permits 8 planners 350 calls a month 16 calls a day for cases & inquiries 96% calls are answered or returned within 1 business day Case loads of 8-22 each planner Average case load of 13.6 cases 12 committees and commissions Plus counter duty PLUS building permit review
3
Hearing Timelines What does this mean to you? To better do our building permit review…we need to be more efficient in order to be more effective.
4
Hearing Timelines We are looking to provide: Predictable timelines Consistent high quality service Better analysis to support decisions Be better prepared at hearings Better address public concerns before problems arise Reduce opposition to projects at public hearings (reduce the number of hearings?)
5
Hearing Timelines Timeline changes we are working towards: Public comment period. Agency review period. Comprehensive staff report. Better quality control review. Give the Planning Commission more time to review the report.
6
Hearing Timelines If you applied today… SunMonTuesWedThurFriSat 24252627281 2345678 9101112131415 16171819202122 23242526272829 303112345 6789101112 Land Use Applications
7
Hearing Timelines Case activity… SunMonTuesWedThurFriSat 2425 File set up 26 Case Assigned 27281 2345678 9101112131415 16171819202122 23242526272829 303112345 6789101112 Land Use Applications
8
Hearing Timelines Completeness Review… SunMonTuesWedThurFriSat 2425 File set up 26 Case Assigned 27 Fully Complete 28 Review Time 1 2345678 9101112131415 16171819202122 23242526272829 303112345 6789101112 Land Use Applications
9
Hearing Timelines Public & Agency Review SunMonTuesWedThurFriSat 2425 File set up 26 Case Assigned 27 Fully Complete 28 Review Time 1 234 Project 5 Review 678 910111213 Site Visit… 1415 16171819202122 23242526272829 303112345 6789101112 Land Use Applications
10
Hearing Timelines Staff analysis & Staff Report SunMonTuesWedThurFriSat 2425 File set up 26 Case Assigned 27 Fully Complete 28 Review Time 1 234 Project 5 Review 678 910111213 Site Visit… 1415 161718 Staff Report 1920 Quality Control 2122 2324 Report Done 2526272829 303112345 6789101112 Land Use Applications
11
Hearing Timelines Staff Report SunMonTuesWedThurFriSat 2425 File set up 26 Case Assigned 27 Fully Complete 28 Review Time 1 234 Project 5 Review 678 910111213 Site Visit… 1415 161718 Staff Report 1920 Quality Control 2122 2324 Report Done 25 Post Sign on Site 262728 Empire Notice 29 303112345 67 Empire Notice 89101112 Land Use Applications
12
Hearing Timelines Distribute Staff Report SunMonTuesWedThurFriSat 2425 File set up 26 Case Assigned 27 Fully Complete 28 Review Time 1 234 Project 5 Review 678 910111213 Site Visit… 1415 161718 Staff Report 1920 Quality Control 2122 2324 Report Done 25 Post Sign on Site 262728 Empire Notice 29 3031 PC get the Report 12345 67 Empire Notice 8 PC Hearing 9101112 Land Use Applications
13
Hearing Timelines What does this mean to you? Plan ahead! Save yourself 2 weeks or more by being aware of our process! Complete submittals prevent delays. Projects with partial submittals won’t be scheduled. Late submittals (or resubmittals) cause delays.
14
Hearing Timelines What do you get out of a structured process? All applicant’s are treated equally. BUT The process rewards applicant’s who are prepared! High quality submittals face less delays. No waiting behind other projects that are unprepared. Improved predictability!
15
Hearing Timelines So why should new timelines for land use permits matter to builders? Better projects mean smoother building permit reviews. Less frustration with land use issues. Clear expectations on both sides of the counter. Staff should be better prepared to serve you.
16
Questions? Hearing Timelines