2
2 Preliminary Pre-Design & Design Prior to Bid Letting For funding allocation and bid comparison Final Construction Post Award For contractor payout
3
3 Preliminary Pre-Design & Design Prior to Bid Letting For funding allocation and bid comparison Pre-Design LRE Design DQE Authorization Estimate Official Estimate
4
Long Range Estimates system Pre-Design; conceptual estimate: used to establish funding levels for the project Generates pay items and quantities you can EXPECT to have, based on project characteristics (typical sections, length, etc.) Design Quantities and Estimates system Design estimate: used to develop the Department’s Official Estimate for bid comparison purposes Contains KNOWN pay items and quantities, based on complete (or nearly complete) plans. 4
5
5
6
LRE uses characteristics of typical section models, applied to a length of roadway, to generate anticipated pay items, quantities, and unit prices. 6
7
District Estimator determines unit prices based on: Pay Item Quantity Project Location Contract Duration Material Cost and availability Labor Cost Equipment Cost Contractor Competition Recent bid prices on similar items are also taken into consideration 7
8
8
9
At 60% - 90% plans, the Designer determines the pay items and quantities comprised in the scope of the project District Estimator determines unit prices for each pay item Both bid-based and cost-based estimating techniques are used 9
10
Estimates are based on Present Day Cost (PDC) Work Program Office applies inflation factors for projects that are scheduled for future years 10
11
11 Annual Work Program Review
12
Goal: To ensure that appropriate funds are budgeted for each year in the 5 Year Work Program Review Criteria: Estimates must be in LRE or DQE Quantifiable and include all scope Within tolerance of Work Program Updated every 6 months Review Schedule: August through November “Exceptions List” completed after each review 12
13
Develop/revise LRE estimate: Pre-Design Phase 1 (30% Plans) Phase 2 (60% Plans) Develop/revise DQE estimate: Phase 3 (90% Plans) Phase 4 (100% Plans) Develop/finalize Authorization Estimate: FHWA authorization of funds Advertisement for bids Work Program Amount (for encumbrance) Develop Official Estimate Perform post-bid analysis Present findings to Awards Committee 13
14
14