15th Tcc / 16th srpc meeting Venue: GOA Date: 29th / 30th April 2011
POWER SYSTEM OPERATION CORPORATION LIMITED SOUTHERN REGIONAL LOAD DESPATCH CENTER BANGALORE 1
2
NEW PROJECTS OF NTPC, NLC, NPCIL & UMPP
SL NO 1 OF TCC
3
NTPC SIMHADRI STAGE - II (2 X 500)
SL NO 1.1 OF TCC
4
NTPC SIMHADRI STAGE - II
MoP conveyed the allocation of Power from Simhadri Stage II to beneficiary states. Units I test synchronised in March 2011 & COD yet to be declared. Units II likely to be commissioned by June 2011 Scheduling of Simhadri Stage II will be done by SRLDC w.e.f COD Data / Speech communication to SRLDC is made operational & under testing Till the date of COD of Simhadri Stage – II Simhadri shall regulate infirm power injection as per SRLDC instruction on real time basis
5
NPCIL KUDANKULAM STAGE 1 (2 X 1000)
SL NO 1.3 OF TCC
6
NPCIL–KUDANKULAM STAGE I
NPCIL informed that for Kudankulam all equipment's are in place at site and the commissioning activities are in full flow. Units I & II are likely to be commissioned by June 2011 & March 2012. In Special TCC held on 3rd Jan NPCIL Informed Reactor of 1st Unit was likely to go critical by March 2011and generation was expected from April 2011 SPS & Speech facilities to be provided - Permission given by TN for placing MUX - SRTS -2 to confirm the status / probable date of completion SEM & SCADA Data Validation to be done by NPCIL – Observed error of 16kV between Field and Scada data at Kudankulam bus Commissioning of Bus Reactor at Kudankulam is essential for ensuring availability of reliable start up supply. The parallel closing of second line between Tirunelvelli – Kudankulam will be at 410 kV and Opened at 425 kV SRPC TN REPLY
7
VALLUR JOINT VENTURE BETWEEN NTPC & TNEB ( 3 X 500)
SL NO 1.4 OF TCC
8
VALLUR JOINT VENTURE BETWEEN NTPC & TNEB (3X500)
Unit sizes of 500 MW. TANTRANSO had informed that commissioning of the 1st unit could be delayed by 2-3 months because of issues regarding the coal handling plant. MoP vide letter dated 28th September 2010 had communicated the allocations to the beneficiaries states as given: Allocation: AP: MW KAR: MW KER: 49.9 MW TN: MW Pondy: 6.7 MW Unallocated: MW Nellore – Allmatty D/C Study Results Nellore – Allmatty D/C Study Report
9
JOINT VENTURE OF NLC& TNEB AT TUTICORN (2 X 500)
SL NO 1.5 OF TCC
10
Joint Venture of NLC & TNEB at Tuticorin
NLC had informed that orders had been placed on M/s BHEL and civil works had commenced. MoP had communicated allocations to the beneficiary States. NLC had informed that with the action plan given by M/s BHEL, Units I & II were scheduled to be commissioned during August 2012 & October 2012 respectively.
11
KAYAMKULAM MW/ 1950 MW SL NO 1.6 OF TCC
12
KAYAMKULAM 1950 MW/1050 MW PLANT
Feasibility report for the project had been finalized by NTPC. Pipeline from Kochi Terminal to Kayamkulam was being developed by M/s GAIL. GoI had circulated drafts on price pooling mechanism. Price of LNG was linked with prices of crude oil. The unit rate was likely to be Rs Rs per unit in the present scenario where crude oil prices ranging between $ 70-80/barrel. Requisition from KPTCL & KSEB received by NTPC. Conditional consent communicated to NTPC by APTRANSCO. TANTRANSCO & Puducherry – Presently price pooling mechanism not very clear, would be interested in case tariff was advantageous.
13
NLC NEW THERMAL POWER PROJECT (2X 500)
SL NO 1.7 OF TCC
14
Neyveli New Thermal Power Project (2x500 MW)
Director (Power ),NLC had informed that the project was likely to take 40 months after PIB approval and was targeted to be commissioned in PIB approval was likely in the next six months. MOP vide letter dated 29th October 2010 had communicated allocation of power from this project PGCIL informed NLC had applied for connectivity. NLC had been requested to apply for LTA also to take up planning of evacuation scheme Tamil Nadu had informed that this being a replacement project since Tamil Nadu was loosing 600 MW , entire 1000 MW from the new project to be allocated to them.
15
Neyveli New Thermal Power Project (2x500 MW)
TNEB’s share was 100% in Neyveli Stage 1. Old plant was commissioned in 1962. Present Evacuation Plan is at 230/110kV Designed for evacuating 600MW. Since 2 x 500MW plant is coming up, inter connection to 400kV is desirable. Wheeling issue
16
KRISHNAPATTANAM UMPP(3960 MW)
SL NO 1.8 OF TCC
17
KRISHNAPATTANAM UMPP(3960 MW)
KRISHNAPATTINAM UMPP 400kV D/C QUAD MOOSE 765 KV TN UMPP Cochin Madugiri
18
KRISHNAPATTANAM UMPP(3960 MW)
The unit configuration had been finalized as 6 x 660 MW and CERC had been approached for revised configuration, clearance awaited. CMD, APTRANSCO had informed that about Rs. 300 Crores had already been invested and progress was their in all the fronts. Project is being developed by Reliance Power Limited. The plant may come up beyond 2014.
19
Schedule Date of Commissioning of the Central Sector/JV Projects
Station Unit Installed Capacity (MW) Original date of commissioning Revised date of commissioning Simhadri Stage - II I,II 500, 500 11th Plan Mar-11, June-11 Kayamkulam I, II & III 1050/1950 12th Plan Vallur JV with TNEB I II III 500+ Oct-11 Dec-11 Dec-12 Neyveli – II (Exp) 250 2006 – 07 Mar-11 Jun-11 Tuticorin JV with TNEB 500 Aug-12 Oct-12 Sirkalli TPP I,II,III 3 X 660 52 Months, 58 Months, 64 Months from GOI approval Kaiga IV 220 Sep – 07 Nov-10 Kudankulam Stage – I 1000 Dec – 07 Dec – 08 Mar-12 Kalpakkam (PFBR) 2010 – 11 Krishnapattanam VI 4000 June 2013 Feb 2015 Cheyyur 2015 – 17
20
PAYMENT OF CHARGES OF TNEB OWNED TRANSFORMERS AT SRIPERUMBUDUR & SALEM
SL NO 2 OF TCC
21
PAYMENT OF CHARGES OF TNEB OWNED Xmers AT SRIPERUMBUDUR & SALEM
Discussed in 13th Commercial Sub-Committee meeting held on 19th July 10 whereas PCKL had agreed to put up a draft computation for the tariff. In the 14th SRPC meeting, it was noted that TCC had agreed that the proposal prepared by PCKL be deliberated in details by the Special Commercial Committee before being put up to TCC/SRPC. Matter was further deliberated in the Special Commercial Sub-Committee meeting held on 29th Sep 10 wherein it was noted that proposal from PCKL was awaited, while APTRANSCO had also submitted their proposal on the issue. Outcome of the 14th commercial Sub – Committee meeting TNEB would compute the charges for the period from to in line with norms prevailed during the period and the Commercial Sub-Committee would validate the same for subsequent approval of TCC/SRPC.
22
MAINTENANCE OF MARCONI MAKE SDH EQUIPMENT
SL NO 3 OF TCC
23
MAINTENANCE OF MARCONI MAKE SDH EQUIPMENT
TN to Expedite Commissioning of their system to Coincide with SR2, PowerGrid Plan Wide band Failure Microwave Details Minutes 12th Jan 10
24
EXISTING WIDEBAND NETWORK UNDER SOUTHERN REGION ULDC PROJECT
Ramagundam Peddapally Durshed Jammikunta Ch. Gutta Shapur Nagar Gazuwaka Vidyut Soudha Warangal Sub-LDC 36 134 11 Hydearbad SLDC (400) 46 Ghanapur 147 Visakapantam SWS 147 Tallapally 99 63 Kakinada Srisailam LBPH 12 N’ Sagar PH Bommur Srisailam PH 217 66 87 Bhimadole 17 VTPS Karnool 104 Vijayawada Sub-LDC Hubli Sub-LDC 20 Somayajula Pally 76 Gooty 58 Ananthapur Davanger Sub-LDC 98 Muddanur 57 Chinakam Pally Sub-LDC (Cuddaph) 302 Kumbalagodi KPTCL SLDC Somanhally CHENNAI SLDC Sriperabudur B’LORE RSCC 181 30 Salem 400 S.P. Koil LEGENDS: 19 156 Kannur Sub-LDC Salem 230 Villianur 111 64 Neyveli-I Pondicherry SCC RSCC Kozhokode B 93 Erode Sub-LDC Panruti SLDC Trichur North Chidambaram Sub-LDC/ SCC Chalakudy 31 Ingur 140 Trichy 230 Myladuthurai 130 Pongalur RTU / Wideband location 26 Kovilvenni Kalamassery SLDC Udumalpet Repeater Station Thiruvarur Adankottai F. O. Link (ULDC) Vaikkam Orthanadu Pallom Pudukottai Thirumayam F. O. Link (APTRANSCO) Kayamkulam Karaikudi M.W. Link (ULDC) Kundara Madurai 400 Sivaganga Paripally M.W. Link (TNEB) Trivandrum North Madurai Sub-LDC VSAT link (KPTCL) Vidyuthi Bhavanam Sub-LDC Colour Code C.S. links (ULDC) CORPORATE LD&C DEPT. Constituents links (ULDC) APTRANSCO links
25
Proposed Solution for replacement of Existing Microwave Links installed under Southern Region ULDC Project Visakapantam SWS B’LORE RSCC CHENNAI SLDC Karnool Muddanur Gooty Ramagundam Vijayawada Sub-LDC Durshed Warangal Sub-LDC Gazuwaka Kakinada Bommur Bhimadole VTPS N’ Sagar PH Tallapally Srisailam PH Srisailam LBPH Shapur Nagar Ch. Gutta Vidyut Soudha Hyderabad SLDC (400) Chinakam Pally Sub-LDC (Cuddaph) Ananthapur Somayajula Pally Somanhally Salem 400 Salem 230 Sriperabudur S.P. Koil Neyveli-I Pondicherry SCC Villianur Myladuthurai Thiruvarur Erode Karaikudi Madurai Madurai 400 Pudukottai Udumalpet Trichy 230 Ingur Kannur Sub-LDC Kozhikode B Chalakudy Pallom Kundara Trivandrum North Vidyuthi Bhavanam Kayamkulam Kalamassery SLDC Trichur North KPTCL SLDC Hubli Sub-LDC Davanger Sub-LDC Ghanapur 11 147 63 66 87 17 99 12 46 134 36 20 76 58 98 57 302 181 19 64 140 156 30 111 93 130 31 26 104 217 Total OPGW = 1214kms Total UGFO = 210 kms LEGEND RSCC SLDC Sub-LDC/ SCC RTU / Wideband location F.O Link (ULDC) F.O. Link (APTRANSCO) OPGW Link (existing) Proposed UGFO link Proposed OPGW link Proposed Radio link VSAT LINK (KPTCL)
26
Constraints In SR System
SL NO 4 OF TCC
27
TRANSMISSION SYSTEMS IN SR IN PROGRESS
KOODANKULAM UNIT 1- JUN 11 UNIT 2- MAR 12 NLY-2 EXPN UNIT1- MAR 11 UNIT-2 JUN 11 NLMNG CHITOOR KOLAR HOODY ALMATHI HASSAN SP-BUDUR S’HALLI HOSUR KALIVENDAPATTU MYSORE BAHOOR KOZHIKODE SALEM NEYVELI ARASUR NLY-EXP NLY2-EXP PUGALUR THRISSUR UDUMALPET TRICHY KARAIKUDI COCHIN MADURAI MULTI-CIRCUIT TOWER ON 220 KV EDAMON-KAYATHAR CORRIDOR EDAMON-TNVL WOULD BE AT 220 KV TO BEGIN WITH EDAMON TRANSMISSION SYSTEMS IN SR IN PROGRESS TIRUNELVELI TRIVANDRUM KOODANKULAM
28
400 KV D/C MYSORE-KOZHIKODE
a) Reduce losses by ~ 8MW b) Enhance margin across constrained S1-S2 corridor. c) Enhanced reliability for N. Kerala (an issue at present) d) Relief for Thrissur(Madakathara) transformer ( Fully loaded) e) Relief on loading of Idukki-LP-Madakathana 220 KV lines g) Enhanced transfer capability to Kerala, opportunity to conserve hydro.
29
400 KV D/C MYSORE-KOZHIKODE STUDY
WITH OUT KOZHIKODE-MYSORE D/C GEN AT IDDUKKI ABOUT 520MW MYSORE NELAMANGALA 173 MWx2 227x2 MW HOOTAGALLY Losses 830.4MW 191 MW 13 MW KADAKOLA KOZHIKODE TK HALLI 104 MW KANIYAMPET 72 MW 48 MW KANAKPURA HORAHALLI 105 MW AREACODE 173 MW 106 MW 139 MW SOMANAHALLI NALLALAM 111 MW TRICHUR KANJIRODE
30
Coal Stock Position SL NO 5 OF TCC DC vs Actual Normative Vs DC
31
DAILY LINKAGE IN 1000 OF TONNES
Coal Stock Position ( As on 27-Apr-11) DAILY LINKAGE IN 1000 OF TONNES ACTUAL IN 1000 OF TONNES IN DAYS APTRANSCO VTS 26 127 5 KTS 18.9 301 16 RYTPS 16.5 97 6 SIMHADRI 23.1 164 7 KAKATIYA 5.8 109 19 ISGS RSTPS 38.1 535 14 TALCHER 52 417 8 KPCL RTPS 25.1 404 BTPS 8.7 TNEB ETPS 6.9 2 MTPS 13.6 73 NCTPS 10.4 59 TTPS 18.5 49 3
32
Issues Related to Transmission Schemes Agreed in Standing Committee
SL NO 6 OF TCC
33
HOSUR-ELECTRONIC CITY 400KV D/C TRANSMISSIN LINE
KOLAR SOMANAHALLI ELECTRONIC CITY HOSUR-ELECTRONIC CITY 400KV D/C TRANSMISSIN LINE 400kV lines YERANDAHALLI In standing committee meeting it is proposed to Utilise the ROW of 220kV Yerandahalli-Hosur line for 400kV Hosur-Electronic City D/C line KPTCL Director (Transmission) had stated that KPTCL would examine some alternate transmission system for Electronic city. HOSUR-ELECTRONIC CITY 400KV D/C TRANSMISSIN LINE 400kV lines In 28th standing committee meeting it is proposed to Utilise the ROW of 220kV Yerandahalli-Hosur line for 400kV Hosur-Electronic City D/C line KOLAR KPTCL Director (Transmission) had stated that KPTCL would examine some alternate transmission system for Electronic city to avoid ROW problems HOSUR ELECTRONIC CITY SOMANAHALLI YERANDAHALLI KPTCL had been requested to explore possibility of establishing 400kV S/S at their existing 220kV S/S at Yerandahalli to solve the ROW problem.
34
400 KV D/C HOSUR-ELECTONIC CITY
PGCIL to do joint survey with KPTCL, if necessary latest stringing methodology would be adopted. KPTCL informed that critical RoW issues existed at two locations. CE (Trans.) Bangalore had been nominated from KPTCL side for joint survey. APTRANSCO had requested to furnish cost implication on account of adoption of unconventional technology.
35
Transmission Capability of HVDC Back to Back stations
SL NO 7 OF TCC
36
Transmission Capability of HVDC Back to Back stations
In 57th OCCM of SRPC, SRLDC had clarified that it would not be able to certify the past cases as PDO was in service during that period and constituents had to take a decision in this regard
37
ULDC Requirements Beyond 2011
SL NO 8 OF TCC
38
LTSA FOR SR –ULDC SCHEME
Maintenance for comprehensive software and hardware maintenance support for EMS/SCADA system supplied under SR-ULDC scheme with two year extension is going to expire on As the upgradation process will take quite a time, as per the request of constituents SRLDC has obtained the quote from M/s GE for extending the AMC by one year with a provision for one more year for further extension if required. SRLDC seeks approval of constituents to go ahead with the proposal with negotiation as the rate quoted by M/s. GE was 30% (Approx) higher than the present AMC charges
39
AMC CHARGES OF SR ULDC SCHEME FOR THE PRESENT AND PROPOSED BY M/S GE
41
Automatic Data Reading (AMR) /Collection
SL NO 10 OF TCC Analysis Details
42
IEGC RELATED ISSUES SL NO 11 OF TCC
43
RGMO SL NO 11.1 OF TCC
44
Units Mandated on RGMO as per IEGC
Description Units Mandated on RGMO as per IEGC Telemetry Status Hydro Thermal total Avaialble Not available Total No of units 194 59 253 231 22 Installed capacity 10888 15600 26488 25996 492 Status of RGMO in SR Confirmation for participation Excemption/ Extention requested to CERC Offer received from OEM/Implementation Unit Not participating in RGMO as declared by the constituents No information with RLDC for status 9 52 64 36 95 256 Installed capacity 4310 6185 8855 1771 5367
45
Mandated And Declared Summary
RGMO RGMO analysis: 1.Droop >30% considered as non response for RGMO 2. Ramagundam Unit #5, 6, & 7 generation is in the range of 102 to 105% 2. On all instances Idukki, Varahi, Nagjhari, Lower Sileru, Sharavati, Sengulam, Kundah –I,II,III are responding for immediate increase and decrease. (Units already in FGMO) 3. In adequate response from thermal generating units 4. Mostly hydro generating units responded (which is under FGMO) 5. In adequate response leading to system insecurity Hence petition will be filed by SRLDC to CERC during next month Case Study Response Summary Mandated And Declared Summary Summary
46
Automatic Demand Management Scheme
SL NO 11.2 OF TCC
47
Automatic Demand Management Schemes
Extracts from IEGC dated 28th April 2010 Clause (d) Quote: The SLDC through respective State Electricity Boards/Distribution Licensees shall also formulate and implement state-of-the-art demand management schemes for automatic demand management like rotational load shedding, demand response (which may include lower tariff for interruptible loads) etc. before , to reduce overdrawl in order to comply para (a) and (b) . A Report detailing the scheme and periodic reports on progress of implementation of the schemes shall be sent to the Central Commission by the concerned SLDC. All the Constituents are requested to Operationalize Unquote: Status
48
Automatic Load Shedding Scheme for Overdrawing Constituents at frequency less than 49.5Hz
SL NO 11.3 OF TCC
49
The Quantum of Load relief through Radial feeder is due for revision.
In the 14th SRPC Meeting held at Cochin, Constituents had agreed to Implement the Load Shedding Scheme for over drawing constituents to avert frequency falling below 49.5 Hz with the following quantum APTRANSCO had been identified 800 MW and tested for remote tripping. TANTRANSCO had been identified 647MW and made operational KSEB had identified MW KAR had identified 384MW ( Max) PONDY to furnish the feeder details. The Quantum of Load relief through Radial feeder is due for revision. Excel Computation Status
50
Arranging Interruptible Loads in four groups
SL NO 11.4 OF TCC
51
Extracts from IEGC dated 28th April 2010
Clause (e) Quote: In order to maintain the frequency within the stipulated band and maintaining the network security, the interruptible loads shall be arranged in four groups of loads, for scheduled power cuts/load shedding, loads for unscheduled load shedding, loads to be shed through under frequency relays/ df/dt relays and loads to be shed under any System Protection Scheme identified at the RPC level. These loads shall be grouped in such a manner that there is no overlapping between different Groups of loads. …………………... AP & Kerala had completed the exercise KPTCL, Pondicherry & Tamil Nadu had initiated the exercise Unquote: Status
52
Demand Estimation SL NO 11.5 OF TCC
53
Extracts from IEGC dated 28th April 2010
Clause 5.3 (e) Quote: While the demand estimation for operational purposes is to be done on a daily/weekly/monthly basis initially, mechanisms and facilities at SLDCs shall be created at the earliest but not later than to facilitate on-line estimation of demand for daily operational use for each 15 minutes block. Constituents are furnishing the block wise forecast Unquote: Status
54
UFR SL NO 11.6 OF TCC
55
AUFR settings and Quantum Implementation Status
Pondicherry – To confirm the status UFR Quantum is due for revision Status
56
Pending Field Inputs SL NO 11.7 OF TCC Pending as on
57
Year wise comparison Details Constituent Mar2008 Mar2009 Mar2010
Apr2011 (20/04/11) APTRANSCO 618 541 640 484 410 KPTCL 800 693 766 334 332 KSEB 25 18 24 TNEB 400 138 129 106 105 SR 1 (POWERGRID) 3 4 26 6 17 SR 2 (POWERGRID) 205 411 729 173 174 NTPC RSTPS 56 32 22 35 31 RGCCP(Kylm) 16 NPCIL KAIGA 40 45 61 63 MAPS 64 37 NLC NLC TS 2 13 30 77 57 NLC TS 1 EXP 1 TOTAL 2217 1950 2493 1371 1266 Details
58
TRANSMISSION SYSTEM FOR EVACUATION OF POWER FROM SIMHADRI-II TPS (2x500 MW) OF NTPC
SL NO 12 OF TCC
59
LILO OF 400KV NUNNA-VTS DC LINE AT NARSRAO PET
TRANSMISSION SYSTEM FOR EVACUATION OF SIMHADRI-II IN 28TH STANDING COMMITTEE MEETING, IT WAS DECIDED THAT IN STEAD OF NEW 400KV SIMHADRI-GAZUWAKA D/C LINE, 400KV GAZUWAKA-VEMAGIRI D/C LINE LILOed AT SIMHADRI PRESENT 400KV VEMAGIRI-NUNNA AP LINES WILL BE CONNECTED TO NARSARAOPET BY DISCONNECTING FROM NUNNA GAZUWAKA MALKARAM SIMHADRI NARSARAOPET VEMAGIRI VTS 400KV GAZUWAKA-VEMAGIRI D/C LINE LILO AT SIMHADRI FOR EVACUATION OF SIMHADRI-II (2x500) POWER LILO OF 400KV NUNNA-VTS DC LINE AT NARSRAO PET
60
SIMHADRI – II TPS EVACUATION
APTRANSCO had accorded concurrence for Open Access for a period of 5 years. Further extension of Open Access would be reviewed w.r.t transmission availability. APTRANSCO had informed that the charges had been worked out on ARR. The other constituents may like to take up the matter with APERC. In the 13th & 14th SRPC meeting, it was noted that since the Regulations on the use of intervening system were likely to be notified by CERC, so there may be not be necessary for approaching APERC in the present scenario. Since Kundankulam & NLC generation has not yet came so if Simhadri II Generation comes up, SR import capability will be reduced to that extent. Allocation: AP: MW KAR: MW KER: 80.9 MW TN: MW Pondy: 10.6 MW Unallocated: 150 MW
61
OPERATION OF TALCHER-KOLAR HVDC TRANSMISSION SYSTEM IN GROUND RETURN MODE
SL NO 13 OF TCC
62
PRDC REPORT EXCERPTS GRM OPERATION IS NOT POSSIBLE WITHOUT BLOCKING DEVICES AT LARGE NUMBER OF LOCATIONS BLOCKING DEVICES SHIFT THE DC NEUTRAL CURRENT TO A DIFFERENT LOCATION INVESTIGATE THOROUGHLY ELECTRODE DESIGN AND LOCATION GRM TO BE LIMITED TO 150 MW BLOCKING DEVICES TO BE PROVIDED AT KOLAR, DB PURA AND BIAL 220KV STATIONS TRIP SINGNAL LOGIC NEEDS MODIFICATION? Sudden Flow Reduction due to High ambient Tal & Low Kolar CEA Letter KPTCL Letter GRM DETAILS SPS 1000 & 450 APPENDIX-IV
63
PROGRESS OF BUS /LINE REACTORS TO BE COMMISSSIONED IN SR
SL NO 14 OF TCC
64
BUS / LINE REACTORS COMMISSIONING BY SR CONSTITUENTS
S. No Bus Name Bus / Line Reactor Original Target Revised Target Date 1* Ramagundam Bus Feb-11 Aug-11 2 Simhadri Nov-10 Mar-11 3 Neyveli – Expn. Apr-11 4 Neyveli TS-II 5 Raichur TPS Dec-10 Dec-11 6 Talaguppa Jun-10 Mar-12 7 Guttur 8 Nelamangala 9 Hoody 10 Hyderabad Line Jun-11 11 Kurnool 12 Vizag Voltages The Bus reactor at NTPC Ramagundam have to be connected to Bus section 1 or 2 instead of Bus section 4 Guttur Line Reactor to be commissioned in addition to Guttur Bus reactor Commissioning of Bus Reactor at Kudankulam is essential for ensuring availability of reliable start up supply
65
IDENTIFICATION OF STRETCHES IN THE STATE SECTOR WHERE INSULATORS ARE TO BE REPLACED DUE TO POLLUTION/FOG/SEA WATER SL NO 16 OF TCC
66
Kali Complex in Karnataka. Tuticorin Area in Tamil Nadu.
HIGHLY SENSITIVE AREA (FREQUENT TRIPPING DUE TO POLLUTION/FOG/SEA WATER) Kali Complex in Karnataka. Tuticorin Area in Tamil Nadu. Coastal Area around Kalpaka in Andhra Pradesh. Tripping in Raichur Switch yard due to tracking of Insulators. All Constituents to take up replacement of Insulators in prone area as well as cleaning up of Insulators in Switch yard which are prone to pollution. TTPS RTPS PCC Meeting
67
OPERATIONALISING OF CHIKKODI-KOLHAPUR 220 KV LINE
SL NO 19 OF TCC
68
OPERATIONALISING OF CHIKKODI-KOLHAPUR 220 KV LINE
Any of the planning issues relating to Operationalizing of Chikkodi –Kolhapur 220 kV line like seeking exemption from CERC on Inter Regional ATC computation etc have to be done by SRPC Secretariat directly .
69
SHUT DOWN OF INTER REGIONAL LINKS
SL NO 20 OF TCC
70
SHUT DOWN OF INTER REGIONAL LINKS
Talcher – Kolar S/D to be availed only during July – December along with S/D of Talcher Stage II Units Concurrence of NLDC & the connected region to be taken for planned outage of IR links Annual Outage Plan of IR links to be concurred by NLDC & Concerned region
71
SHUT DOWN OF 400 KV VIJAYAWADA- NELLORE D/C LINE
SL NO 21 OF TCC BEFORE S/D AFTER S/D AP LETTER
72
SCHEDULING OF TALCHER STPS STAGE II
SL NO 23 OF TCC
73
Scheduling of Talcher Stg II
Committee recommended that the scheduling of Talcher STPS-II be continued to done by SRLDC, as the clauses in the IEGC allow the same and change is not called for.
74
Scheduling of Talcher stg II
Clause 6.4 of IEGC The national interconnected grid is divided into control areas, like Regional ISTS, States, DVC, etc. where the load dispatch centre or system operator of the respective control area controls its generation and/or load to maintain its interchange schedule with other control areas whenever required to do so and contributes to frequency regulation of the synchronously operating system. The Load Despatch Centre of a control area therefore is responsible for coordinating the scheduling of a generating station, within the control area, real time monitoring the station’s operation, checking that there is no gaming (gaming is an intentional mis-declaration of a parameter related to commercial mechanism in vogue, in order to make an undue commercial gain) in its availability declaration or in any other way revision of availability declaration and injection schedule, switching instructions, metering and energy accounting, issuance of UI accounts within the control area, collections/disbursement of UI payments, outageplaning etc Control area definition in IEGC: An electrical system bounded by interconnections (tie lines) , metering and telemetry which controls its generation and/or load to maintain its interchange schedule with other control areas whenever required to do so and contributes to frequency regulation of the synchronously operating system.
75
Why SRLDC ? Minimal to and fro co-ordination between RLDC’s and SLDc’s in case of scheduling process involving surrender ,recall etc. Less time in to and fro communication Right from planning to implementation Talcher II is apart of SR system. Only geographically located in ER system SR boundary is upto Talcher AC I/C & Jeypore end of Gazuwaka line In analogy to 6.4.2c(iii) of IEGC and SoR of IEGC 2010 in para 41.13, the control area jurisdiction of Talcher-II shall be with SRLDC as more than 50% share is to SR constituents. In case of Open Access transaction also the nodal RLDC is that of importing region. On same Anology SRLDC is nodal agency for Talcher-II
76
Continued It plays a vital role in the LGBR of SR
AOH coordination by SRPC OCC SPS already in place for eventualities like unit /pole tripping. Present system is working fine for over 8 years.
77
Extracts from SoR on IEGC dt.18.06.2010
41. Demarcation of responsibilities( Regulation 6.4 of draft grid code regulations) 41.13 This has been done to ensure certainty in the demarcation of responsibilities. The IPP with their business strategy would decide quantum of power to be sold through long term, Medium term and short terms. The connectivity to ISTS and STU system indicates that generator wants to avail this flexibility. As the customer of this type of generator would be in more than one region, RLDC through its communication system would be able to coordinate with more than one regions and also RLDC would be aware of system operating conditions like transmission constraints, Voltage conditions etc and would be in better position to ensure that scheduling to various consumers of the IPP is done optimally on day to day basis. Hence, we have decided that if the host State has more than 50% share of power, then that generating station shall be under the jurisdiction of SLDC, else it shall be under RLDC. Regarding the apprehension of some stakeholders on frequent toggling of control area jurisdiction, it is clarified that the control area jurisdiction is decided on the basis of permanent share of the host State, which will not change frequently, hence frequent toggling would not be there. Moreover, initially when one or two units/ stages of the project will come under commercial operation, the jurisdiction would be more likely with SLDC depending on the share of the host State. On the progressive commissioning of units/ stages, it is more likely that the share of the host State would decrease and become equal to or less than 50%, resulting in shifting of control area jurisdiction from SLDC to RLDC. In future also, when more units are commissioned, it is more likely that the control area jurisdiction will remain with RLDC and there would not be frequent toggling. Regarding the apprehension of some stakeholders about the problem in metering during due to this toggling, it is clarified that the interface meters at CTU and STU interfaces shall be installed as per the CEA regulations on metering. It is further clarified that as switchover of control area would be done expeditiously after the change w.e.f. the next billing period i.e. next week UI accounting there shall not be any problem in energy accounting as anticipated by SLDC, Maharashtra. For inter-State energy accounting, it shall be as per CERC ABT mechanism.
78
LOW FREQUENCY OPERATION
SL NO 24.3 OF TCC SCH VS DRW ABC & 12% FLOW GATE VIOLATION
79
% OF TIME WHEN FREQUECY WAS BETWEEN
FREQUENCY SPECTRUM OF SOUTHERN REGIONAL GRID (APRIL’09 TO 27th APR’11) MONTH FREQUENCY (Hz) % OF TIME WHEN FREQUECY WAS BETWEEN MAX MIN AVG < 48.5 HZ 48.5 TO 49.0 HZ 49.0 TO 49.2 HZ 49.2 TO 49.5 HZ 49.5 TO 50.0 HZ 50.0 TO 50.3 HZ > 50.3 HZ Apr-09 50.93 48.53 49.39 6.7 13.88 39.66 36.65 3.68 0.44 May-09 51.03 48.56 49.72 1.86 2.52 18.32 51.31 21.41 4.58 Jun-09 50.41 48.97 49.57 1.35 3.8 32.5 51.91 9.64 0.8 Jul-09 50.48 49.04 49.66 0.08 0.96 21.11 65.01 11.74 1.1 Aug-09 50.25 48.98 49.52 0.77 3.15 34.34 58.18 3.31 0.25 Sep-09 50.68 48.82 0.02 0.32 11.53 69.93 15.82 2.38 Oct-09 50.85 48.57 49.53 1.57 4.23 37.14 47.45 8.21 1.4 Nov-09 50.57 48.58 49.77 0.06 0.19 4.35 76.25 18.12 1.02 Dec-09 50.38 49.2 49.75 0.04 0.15 7.48 70.9 20.7 0.73 Jan-10 50.47 49.18 49.76 0.24 6.34 74.6 17.42 1.34 Feb-10 50.27 49.08 49.59 0.46 2.39 20.32 71.33 5.29 0.23 Mar-10 50.2 48.78 2.91 9.07 50.78 35.53 1.59 0.12 Apr-10 50.56 49.45 2.83 7.19 40.91 45.55 3.27 50.0 TO 50.2 HZ > 50.2 HZ May-10 50.88 49.84 0.28 2.45 71.97 19.26 5.79 Jun-10 50.67 49.81 0.83 1.04 3.88 73.81 14.52 5.92 Jul-10 50.69 48.92 49.85 0.03 0.16 1.27 82.36 12.13 4.05 Aug-10 50.54 48.7 0.17 3.52 77.64 13.39 5.24 Sep-10 48.84 49.92 1.33 64.25 26.49 7.62 Oct-10 50.66 49.24 49.91 0.21 71.15 21.47 7.17 Nov-10 50.97 48.88 49.99 0.07 0.54 55.03 28.53 15.8 Dec-10 48.96 0.75 67.24 22.33 9.65 Jan-11 50.99 49.22 49.82 1.43 79.97 15.04 3.56 Feb-11 48.83 49.7 0.42 7.91 85.73 4.95 0.92 Mar-11 50.82 48.81 49.61 0.78 18.27 78.63 1.77 0.38 Apr-11 50.86 49.65 0.00 0.33 1.46 20.10 69.77 6.97 1.37
80
HIGH FREQUENCY OPERATION
SL NO 24.4 OF TCC GRAPHS & MSGs Staggering of loads in a co-ordinated manner have to be done during change over by Constituents. Staggering to be reviewed
81
Major Events SL NO 24.6 OF TCC MAJOR EVENTS
82
Hydro Availability SL NO 24.7 OF TCC
83
Reservoir Position LEVEL IN MTS 27/Apr/2010 27/Apr/2011 April JALAPUT
Full Reservoir Level Last 9 Years Corresponding Monthly Average Level LEVEL Last 9 Years Corresponding Monthly Average MU's ENERGY Shortfall (-ve) / Rise (+ve) IN MU w.r.t Last Year Same Day Shortfall (-ve) / Rise (+ve) w.r.t 9 years Corresponding Monthly Average 27/Apr/2010 27/Apr/2011 April MU % JALAPUT 838.40 834.61 822.17 835.24 246 83 402 319 384 156 63 SRISAILAM 270.70 263.65 247.86 247.53 --- N’SAGAR 179.90 164.82 157.34 168.71 LINGANMAKKI 554.50 549.29 540.21 541.75 1143 1287 1515 228 18 372 32 SUPA 564.00 546.38 527.89 529.21 788 748 805 57 8 17 2 IDUKKI 732.43 721.53 708.94 713.50 601 595 837 242 41 236 39 KAKKI 969.80 974.23 958.89 959.90 318 333 350 5 10 NILGIRIS 534 491 191 -300 -61 -343 -64 TOTAL 3631 3537 4100 563 16 470 13
84
Reservoir Level Graph 4100 MU on 27th Apr 2011 31.99% on 27th Apr 2011
85
Grid Voltage SL NO 24.8 OF TCC Voltages
Vemagiri MOM Vemagiri Tap Change Installation of Bus reactor at Vemagiri complex may be considered to address the high voltage problem at vemagiri
86
VAR Absorption/Injection by Generators within Capability Limits
SL NO 24.9 OF TCC Graphs
87
Operation of Talcher – Kolar HVDC Link in extended mode of operation
SL NO 27 OF TCC Report
88
CRISIS MANAGEMENT PLAN
SL NO D 2.1 OF TCC PROGRESS
89
Closing of 220/230 kV Inter State Lines
Supp Agenda 2 Point 4 OF TCC
90
VARIOUS MEETINGS WHERE ISSUE OF CLOSING AP-TN, AND INTER REGIONA LINKS WERE TAKEN UP
Sr.No. Date Meeting Point Discussed 1 06-Jun-08 6th TCC RADIALISATION OF CHIKKODI ON N-E-W GRID THROUGH CHIKKODI – KOLHAPUR LINE 2 13-Aug-08 28th OCC 3 18-Oct-08 7th TCC 4 11-Nov-08 29th OCC STATUS REVIEW ON RADIALISATION OF CHIKKODI ON N-E-W GRID THROUGH CHIKKODI – KOLHAPUR LINE (DISCUSSED IN 28TH OCCM) 5 10-Dec-08 30th OCC STATUS REVIEW ON RADIALISATION OF CHIKKODI ON N-E-W GRID THROUGH CHIKKODI – KOLHAPUR LINE (DISCUSSED IN 29TH OCCM) 6 05-Mar-09 8th TCC 7 10-Jul-09 37th OCC OUTAGE OF 220KV CHITTOR - THIRUVALEM LINE SINCE 10TH FEB – PROGRAMME FOR PUTTING LINE BACK INTO SERVICE 8 CLOSING OF SULURPET-GUMMDIPOONDI FOR REDUCING OVERLOADING OF NEYVELI - S P BUDUR LINE 9 09-Sep-09 39th OCC PROLONGED OUTAGE OF CHITTOOR-THIRUVELAM SINCE 10TH FEB 09 15:20 HRS 10 13-Oct-09 40th OCC PROLONGED OUTAGE OF CHITTOR – THIRUVALEM LINE SINCE 10TH FEB 09 15:20 HRS 11 12-Nov-09 41st OCC 12 PROLONGED OUTAGE OF SULURPET –GUMMUDIPOONIDI SINCE 24 /10/09 22:40 HRS 13 11-Dec-09 42nd OCC TN TO EXPEDITE SYNCHRONISATION OF CHITTOR-THIRUVALEM LINE 14 REVIEW OF SULURPET – GUMMIDIPOONDI O/L TRIPPING SETTINGS 15 08-Jan-10 43rd OCC 16 17 03-Feb-10 8th PCC TN TO EXPEDITE SYNCHRONISATION OF SULURPET – GUMMIDIPOONDI & CHITTOR-THIRUVALEM LINE 18 11-Feb-10 44th OCC 19 20 09-Mar-10 45th OCC 21 25-Jun-10 48th OCC 22 14-Jul-10 49th OCC CHITTOR-THIRUVALAM LINE CHARGED ON 23 08-Oct-10 52nd OCC TN TO EXPEDITE SYNCHRONISATION OF SULURPET – GUMMIDIPOONDI LINE 24 10-Dec-10 54th OCC SYNCHRONISED THE 230 kV SULURPET – GUMMIDIPOONDI LINE ON 25 10-Jan-11 55th OCC RESTRICT THE LINE LOADING TO < 100 MW ON SULURPET – GUMMIDIPOONDI LINE 26 08-Feb-11 56th OCC 27 09-Mar-11 57th OCC
91
Operation of 400 kV Lines Upto SIL derived steady State limit
Supp Agenda 2 Point 2 OF TCC PPT REPORT
92
Thank You
93
Automatic Data Reading (AMR) /Collection
To avoid all the data related delays and fulfill the deadlines set by IEGC, SRLDC had proposed to adopt AMR scheme in SR. In SR, there are about 600 SEMs installed in about 100 locations. Scheme may be implemented by PGCIL at an estimated cost of about Rs. 1.5 Crores which can be recovered through tariff in the same way as the cost of SEMs is being recovered. Outcome of the 14th commercial Sub – Committee meeting Committee in principle agreed the proposal. SRLDC suggested that cost may be recovered through tariff. 93
94
Proposal for automatic data reading
(AMR) /collection (to be implemented by POWERGRID): To avoid delays in SEM data transmission to SRLDC it is proposed to adopt AMR scheme in SR at an estimated cost of Rs.1.5Crores.Schematic representation of AMR is as below. Hardware required for each location: Modem-1 no, Data Concentrator Unit-1 no Local Computer- 1 no., Remote Computer at SRLDC – 1 no. Cost of Communication on GPRS mode : as per actual. 94
95
Bill Of Quantities Sl. No. Description Qty. * Unit Rate Rs ** Amount Rs. A For S/S with meters located in Control Room (Aprox. 120 S/S) # 1) All required hardwares i.e. Meter Interfacing Unit/Protocol Comnverter/Optical Probe/ Connectors / Cable for data transfer between meters and Data Concentrator etc. 700 Per SEM 6602 2) Data Concentrator Unit/Data Accumulator (one No. at each location) 120 No. 22000 3) GPRS Modem (One No. at each location) 6500 780000 B Common for total Scheme Meter Data Acquisition & Analysis software (For all Data Concentrator Units/Data Accumulators (Approx. 120 Nos.) and Servers at SRLDC (2 Nos.). 1 Lumpsum Training to personnel posted at all S/S where scheme will be commisioned and SRLDC. (10 Trainings with a batch of participants) 10 200000 Installation, Testing & Commissioning/Customization cost 2112 C CENTRAL LOCATION (AT SRLDC & 6 SLDCs) Central server (Including cost of required RDBMS & OS) 7 175000 UPS (2 KVA) 30000 210000 GPRS/GSM Modems 45500 D Wararnty / AMC Warranty for 1 year NIL AMC for 1st year after Warranty 806 564480 AMC for 2nd year after Warranty 800 853 682667 4) AMC for 3rd year after Warranty 900 894 804414 5) AMC for 4th year after Warranty 1000 929 929032 Total 95
96
Minutes of 14th NRPC meeting reg. AMR scheme implementation
Back 96