06 August 2015 1 EHN1 civil engineering project status (JULY) Summary: Updating of the activities carried out on-site (Done) in JULY List activities on.

Similar presentations


Presentation on theme: "06 August 2015 1 EHN1 civil engineering project status (JULY) Summary: Updating of the activities carried out on-site (Done) in JULY List activities on."— Presentation transcript:

1 06 August 2015 1 EHN1 civil engineering project status (JULY) Summary: Updating of the activities carried out on-site (Done) in JULY List activities on going (Next steps) and scheduled for AUGUST Final consideration Extension of Building 887 - 26th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

2 (1) MICRO PILES Vertical & inclined drilling along TT85: (100% completed) EHN1 civil engineering project status (JULY) Crown beam execution: (100% completed). Done (1/4): 06 August 2015 2 Extension of Building 887 - 26th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

3 (2) DIAPHRAGM WALLS -73 panels- Execution EAST side: (91% completed) EHN1 civil engineering project status (JULY) Execution SOUTH/WEST side: (67% completed) Done (2/4): 06 August 2015 3 Guide walls allowing DW excavation: (100% completed) Execution NORTH/WEST side: (100% completed) ~85% TOTAL PANELS EAST N/W S/W Extension of Building 887 - 26th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

4 Done (3/4): (3) TECHNICAL GALLERY -70 meters- EHN1 civil engineering project status (JULY) Earthworks: (100% completed). Execution TG: (72% completed). Type 3 almost done. Type 1 started Backfilling: (25% completed). 06 August 2015 4 Extension of Building 887 - 26th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

5 Done (4/4): (4) PITS EXECUTION EHN1 civil engineering project status (JULY) Crown beam execution: (22% completed). Start with E side. Excavation first ties level: (22% completed). 06 August 2015 5 Excavation head DW level: (50% completed). Start with E and N/W side areas. Excavation second ties level: (0% completed). Only for certain DW panels …Others First ties level execution: (13% completed). Not yet in tension -step by step- Task in “cohabitation” with the DWs last panels execution!! Extension of Building 887 - 26th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

6 Next Steps: Activities scheduled for August (2) DW: Whole panels completion within 1 st half of August (3) TG: Entire length, including connection with the EHN1, within end-August. (4) PITS: Excavation/Execution crown beam + Excavation/Execution for ties installation  East side portion EHN1 civil engineering project status (JULY) 06 August 2015 6 04/08/2015 => Extension of Building 887 - 26th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi

7 Final Consideration: -New long-term schedule received updated with the current on-site situation. -The compatibility/duration of the upcoming tasks will be assessed. -CE tasks have to be carried out in parallel. Execution of the two pits launched before DWs panels completion to avoid further delays. -Likely (but too early to say) CE first phase completion while metallic contractor are already on-site. Risky, but feasible thanks to the Consortium. -CE Handover unchanged for the moment (Jul-2016) -Next status of the works end-August. EHN1 civil engineering project status (JULY) 06 August 2015 7 Extension of Building 887 - 26th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi