Programme and progress. Programme Employer requirements – Sectional completion Pre-tender programme – Use for ascertaining completion risk – Subcontractor.

Similar presentations


Presentation on theme: "Programme and progress. Programme Employer requirements – Sectional completion Pre-tender programme – Use for ascertaining completion risk – Subcontractor."— Presentation transcript:

1 Programme and progress

2 Programme Employer requirements – Sectional completion Pre-tender programme – Use for ascertaining completion risk – Subcontractor activity periods – Temporary works – Enabling works – Sequence cost study planning (see next slide) Master programme – Specified requirement under ICC and NEC3 – Extent specified? – Content specified? – Measurement implications? – Work breakdown structure © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 2

3 Sequence study cost comparison © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 3

4 Contract stage programmes Short-term programmes – Monthly or weekly – Consider alternative methods Noncompliance with master programme – Effect? Types of programme – Precedence (activity on the node) – Arrow (activity on the arrow) – As planned – As Built Extensions of time – With costs – Without costs Mitigation of loss – An implied term??? © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 4

5 Master programme © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd.

6 Baseline programme © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 6

7 Baseline programme (contd.) © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 7

8 Measuring progress S curve principles – Match budget with programme – Calculate a predicted cumulative total – Compare as built with predicted Possibility of EVA – Needs WBS – Metrics Acceleration © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 8

9 Progress measurement © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 9

10 Measuring progress-value envelop e 10

11 Acceleration Short-term programmes – Monthly or weekly – Consider alternative methods Noncompliance with master programme – Effect? Types of programme – Precedence (activity on the node) – Arrow (activity on the arrow) – As planned – As Built Extensions of time – With costs – Without costs Mitigation of loss – An implied term??? © 2013 Andrew Ross and Peter Williams. Published 2013 by John Wiley & Sons, Ltd. 11


Download ppt "Programme and progress. Programme Employer requirements – Sectional completion Pre-tender programme – Use for ascertaining completion risk – Subcontractor."