Installation and Testing of Optical Harnesses John Matheson Rutherford Appleton Laboratory Schedule for test and assembly Outline of required tests Acceptance testing Assembly to discs Final testing
2
Schedule for Test and Assembly: Barrel B3: 64 harnessesB3: 64 harnesses B4: 80 harnessesB4: 80 harnesses B5: 96 harnessesB5: 96 harnesses B6: 112 harnessesB6: 112 harnesses B3: 50 days April 02 -> June 02 B4,B5,B6: Oct 02 -> Mar 03 delivery -> installation ~35 days 1 man hour for acceptance test 2hr for assy to barrel / final test
3
Schedule for Test and Assembly: Forward D1,D7,D8: 16 harnesses/discD1,D7,D8: 16 harnesses/disc D2,D3,D4,D5,D6: 24 harnesses/discD2,D3,D4,D5,D6: 24 harnesses/disc D9: 12 harnesses/discD9: 12 harnesses/disc Total 360 (2 end caps)Total 360 (2 end caps) services to discs 7/10/02 on (90 days) => 10hr/harness 3 full-time technical staff foreseen for assembly/testing of services for barrels and discs
4
Barrel Harness DORIC and VDC opto package power tapes, redundancy system many traces and connections
5
Forward Harness forward harness consists of opto packages and optical fibres only latest version - no plastic cover test LI, responsivity in DC conditions
6
Test Fixture for Forward Plug-ins equivalent to forward module design will be transferred to 6 PCBs allows testing of BER
7
What measurements do we need ? VCSEL LI curves pin diode responsivity radiation hardness (batch acceptance) BER scan/BER long term thermal cycling/burn-in (during manufacture) power tape continuity ? power tape insulation ?
8
BER testing: TTC link SLOG SLOG LITMUSLITMUS OPTIFOPTIF
9
TTC link results: BER scan vary light power into p-i-n diode allows definition of working range BER scans < 5 min
10
VCSEL LI Curves SCTLVSCTLV SLOGSLOG SCTLVSCTLV scan I using SCTLV measure photocurrent in LAPD 50% duty cycle 5 min. setup/run time LAPD DMM
11
PIN Responsivity SCTLVSCTLV SCTLVSCTLV LEDLED DMMsupply LAPD measure I in pin bias line LEDs for reproducibility LAPD used to calibrate LEDs 10 min. setup/run
12
Acceptance testing at RAL Both harnesses: responsivity 10 min VCSEL L-I curve 5 min BER scans data and TTC 30 min Barrel harness additional: HV insulation resistance 5 min continuity/shorts 5 min redundancy system 10 min Total time: barrel = 1 hr, forward = 45 min
13
Forward harness installation: assembly former services assembled to former former used to populate quadrant after 4 quadrants, align cooling blocks
14
Forward harness installation: procedure cooling pipes soldered on jig mount services on front former 1. dummy modules 2. cooling pipes 3. power tapes 4. opto-harnesses transfer services to disc fix cooling blocks temporarily connect patch panels test each quadrant whilst re- populating the former because: 1. quicker 2. next step, align and glue blocks turn disc over and repeat
15
Final testing during installation Both harnesses: responsivity 0 min VCSEL L-I curve 0 min BER scans data and TTC 30 min BER long-term 60 min Barrel harness additional: HV insulation resistance 0 min continuity/shorts 5 min redundancy system 10 min Total time: barrel = 1 hr 45 min, forward = 90 min
16
procedures for installation and testing are well defined expect 3 technicians for harnesses 1 man-hour/harness, acceptance 2 hours / harness, test + installation Schedule is achievable but requires care in execution first barrel will arrive April 02, timescale less critical will allow refinement of procedures