Download presentation
Presentation is loading. Please wait.
Published byHilda Sullivan Modified over 9 years ago
1
2014 Project Updates Building the Port of the Future Gina Barro Business Development Manager Trade Development Division
2
Port of Long Beach Premier gateway for U.S. - Asia trade Premier gateway for U.S. - Asia trade Major Southern California economic engine
3
Investing in the Future $4 billion in projects $4 billion in projects
4
Middle Harbor $1.3 billion $1.3 billion First half set to open in late 2015
5
Ship-to-Shore Cranes Four on site 8 more of the most advanced cranes on the way
6
Before Construction Pier E Pier F E 26 E 24 E 22 F 6 F 10 1 million-TEU capacity
7
Middle Harbor 3 million-TEU capacity Most technologically advanced in N. America
8
$1 billion Gerald Desmond Bridge Replacement Iconic Bridge $1.3 billion project Opening to westbound traffic as early as 2017
9
Clearing the Path Ramp demolition For information, download our LB Bridge app.
10
ITS Terminal Redevelopment 2 nd Phase will include slip development, south rail yard renovation and demolition of old terminal buildings.
11
Sustainability Green Port Policy 81% Drop in Diesel Emissions since 2005 81% Drop in Diesel Emissions since 2005
12
Shore Power Container ships plug in
13
Pier J Pier G Pier T Pier A Middle Harbor 14 Shore Power Berths
14
Upgrading Rail Green Port Gateway Green Port Gateway
15
Rail Improvements Ocean Blvd. Track Realignment Middle Harbor On-Dock Rail* *Future project Pier G Rail Yard Pier G Rail Yard Pier B On-Dock Rail Support Facility Pier B On-Dock Rail Support Facility
16
New Fireboat Stations LB Fire Station #15 LB Fire Station #20 Desmond Bridge Replacement Project Middle Harbor Redevelopment Project
17
Maintenance Dredging Projects
18
Capital Dredging Projects
19
Bright Future Long Beach -- a great place to live and work
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.