CRWR-PrePro Calculation of Hydrologic Parameters Francisco Olivera, Ph.D. Center for Research in Water Resources University of Texas at Austin Texas Department of Transportation (TxDOT) Water Resources Modeling Using GIS 2000 - Austin, Texas
2
Hydrologic Parameters zWatershed yAbstractions and routing method yParameters zStream yRouting method yParameters
3
Watershed Abstractions and Routing Method zAbstractions: rainfall/runoff transformation ySCS curve number method yInitial loss + constant rate loss zRouting: runoff/flow transformation ySoil Conservation Service (SCS) synthetic unit hydrograph
4
Watershed Abstractions Soil properties Precipitation (mm/hr) Runoff (mm/hr) Runoff = f(precipitation, soil properties, moisture conditions)
5
Watershed Routing Runoff (mm/hr) Flow (m 3 /s) Watershed
6
Watershed Routing Runoff (mm/hr) Flow (m 3 /s) Time Runoff and Flow Flow = f(Runoff, Watershed hydrologic properties) Time
7
Hydrologic Parameters zWatershed yAbstractions and routing method yParameters zStream yRouting method yParameters
8
Watershed zArea zAverage curve number zInitial + constant rate loss zLength of longest flow-path zSlope of longest flow path zLag time
9
Watershed Abstractions Average Curve Number SCS Method Initial + Constant Method Initial Loss (mm) Constant Loss (mm/hr)
10
Elevation Grid
11
Flow Length Downstream
12
Flow Length Upstream
13
Longest Flow-Path
14
Flow Length Downstream to the Watershed Outlet
15
Hydrologic Parameters zFlow length downstream to the sub-basin outlet.
16
Flow Length Upstream to the Watershed Divide
17
Hydrologic Parameters zFlow length upstream to the sub-basin divide. A NODATA cell is defined at the sub-basin outlets before running the flow length function.
18
Watershed Longest Flow-Path
19
Hydrologic Parameters zSub-basin longest flow- path. zThe longest flow-path is the geometric locus of the points for which the sum of both flow lengths is a maximum.
20
Slope of Watershed Longest Flow Path
21
Hydrologic Parameters t p :sub-basin lag-time (min) L W :length of sub-basin longest flow-path (ft) CN :average Curve Number in sub-basin S :slope of the sub-basin longest flow-path (%) t: analysis time step (min) zSub-basin lag-time according to the SCS formula:
22
Watershed Lag-Time (SCS) Flow length upstream and downstream Average Curve Number Length and slope of the longest flow-path Identification of the longest flow-path Lag-time
23
Hydrologic Parameters t p :sub-basin lag-time (min) L w :length of sub-basin longest flow-path (ft) V w :average velocity sub-basin longest flow-path (m/s) t: analysis time step (min) zSub-basin lag-time according to 0.6 L/v formula:
24
Watershed Lag-Time (L/V) Flow length upstream and downstream Longest flow-path average velocity Length of the longest flow-path Lag-time
25
Hydrologic Parameters zSub-basin parameters: Grid code, area (Km 2 ), unit hydrograph model (SCS), length of longest flow path (m), slope of longest flow path (fraction), average curve number, lag-time (min), baseflow (none).
26
Hydrologic Parameters zWatershed yAbstractions and routing method yParameters zStream yRouting method yParameters
27
Routing Method
28
Pure-Lag Method zFlow is delayed a fixed amount of time t lag. t lag : flow time in the reach I: inflow to the reach Q: outflow from the reach
29
Muskingum Method zFlow is delayed a fixed amount of time K, and redistributed around its centroid. S: storage in the reach K: flow time in the reach ( t < K < t/2X ) X: storage parameter I: inflow to the reach Q: outflow from the reach t: analysis time step
30
Routing Method Flow time (L s /V s ) L s /V s < t Muskingum Routing L s /V s > t Pure Lag Routing L s :length of the stream V s :flow velocity in the stream t: analysis time step
31
Hydrologic Parameters zWatershed yAbstractions and routing method yParameters zStream yRouting method yParameters
32
Hydrologic Parameters t lag :reach lag-time (min) L s :length of reach (m) V s :reach average velocity (m/s) zReach lag-time for Pure Lag routing:
33
Hydrologic Parameters K :Muskingum parameter K (hr) X :Muskingum parameter X L s :reach length (m) V s :reach average velocity (m/s) n :number of sub-reaches zReach lag-time and number of sub-reaches for Muskingum routing:
34
Hydrologic Parameters Pure lag routing for L s /60v s < t, otherwise Muskingum routing. zReach parameters: Grid code, sub-basin code, length(m), velocity (m/s), routing method (Lag or Muskingum), lag time (min), Muskingum X, Muskingum K (hr), number of sub-reaches.