1 Solar Probe Plus FIELDS Team Meeting Management Items 08/05/2014

2 Agenda 1. Electrical Status (All) DCB-RFS, FSW Daughterboard AEB, PREAMP TDS-LNPS, FSW DFB MAG SCM 2. Mechanical/Thermal - Bill D., David G., Paul Turin, Millan D. a. MEP b. Antennas c. Thermal 3. Systems (Goetz) Power Is Tight on Spacecraft Harness Drawings ICD Changes 4. Assurance - Fischer/Le a. Parts Ordering Documentation b. Radiation Meetings w/APL 5. Management (Harvey) a. iPDR Action Item Status - All Complete! b. Changes in the weekly report, issues c. Adding monthly liens & threats d. Quarterly Estimate At Completion e. Risks to iCDR schedule f. I&T Schedule g. Peer Review Coordination 6. Deliverables to APL MOC Products review - Delivered 8/1/14 MICDs - delayed due to CAD issues

3 Action Items All Have Been Completed !

4 PHASE C/D MILESTONES

5 ETU I&T SCHEDULE Arrival Estimates Continue to Slip Some Reductions in Work Seen (negative values) Without Reductions, Slip is Roughly 10 days / 30-day month Processors Coming in Late, Yet Needed to Start I&T

6 ETU I&T SCHEDULE June Schedule – PROTO-RTAX logistics not supportable August Schedule – After 2 months, 1.5 months delayed.

7 ETU I&T SCHEDULE August Revised Schedule DCB EM1 to be used to start I&T DCB EM2 to be swapped in at end of FIELDS1 I&T After successful CPT, PROTO RTAX are burned, assembled and tested. Peer reviews during November ICDR Slides needed early December Environments in December ICDR (Jan 14).

8 ETU I&T SCHEDULE