1 SMOV Proposal Process Initial Submission through Flight George Chapman Merle Reinhart Tony Roman February 21, 2001
2
2 Overview Proposal Implementation Team (PIT) The PIT Process PIT Schedule The Proposal – Phase 2 Tips Beyond the PIT
3
3 Proposal Implementation Team (PIT) A group of experts that meet to develop and implement proposals fast, safely and efficiently Compressed timeline for SMOV benefits from a focused group Try to accomplish via one or two meetings per proposal (more if necessary)
4
4 The PIT Process Proposal Submission –best attempt at converting Activity Summary into a proposal –no later than deadline (earlier is better) Proposal Processing PIT meeting #1 –proposal reviewed in detail –modifications identified –special implementation needs identified
5
5 The PIT Process (cont’d) Modifications & Resubmission –no later than deadline (earlier is better) Proposal Processing PIT meeting #2 (if needed) –verify expected modifications –final review of proposal and ancillary products –approval to process to flight ready state If necessary, PIT meeting #3
6
6 The PIT Schedule Submission Deadline PIT Meeting #1 Resubmission Deadline PIT Meeting #2 10+ working days 5 Working Days
7
7 The Proposal – Phase 2 Tips Use Web version of proposal for any changes –http://www.stsci.edu/public/propinfo.html Good, Detailed Descriptions Include Related Activity Summary Ids Include prerequisite Proposal Ids Default for SMOV is SCHED 100% Absolute Time constraints should be used only for visits with alternate targets SMOV3B is to be tagged as Cycle 10
8
8 The Proposal – Phase 2 tips (cont’d) Contingency Planning Each Phase 2 should allow for a launch shift of at least plus or minus 1 month Use the ON HOLD special requirement on conditional visits
9
9 The Proposal – Phase 2 Tips (cont’d) Expedited Data Flow If data is needed in a timeline fashion for analysis, then this needs to be explicitly mentioned in the visit comments. –Data to the PI within 12 hours of visit completion. –Data to the PI within 20 hours of visit completion. –Data to the PI within 32 hours of visit completion. These numbers assume ~8 hours of processing after the data is downlinked from the spacecraft until the data is available to the PI.
10
10 The Expedited Dataflow SSR PACOR-IN PACOR-OUT OPUS-OUT PI PACOR-OUT OPUS-OUT STARVIEW PACOR-OUT RealTime <<1 hr. Quicklook <2 hrs. Production <~4 hrs. <1 hr. <~1 hr. <1 hr. OPUS-IN DADS-IN <1 hr. ~1 hr. ~3 hrs. FTP Spacecraft PACOR OPUS DADS PACOR-IN Science RealTime Science Dump <1hr. to <~12 hrs. CCS-IN CCS-OUT Engineering Dump <1 hr. to <~12 hrs. ~2-4 hrs. SE OPUS-IN 24 - 48 hrs. Extraction from Warehouse CCS
11
11 Beyond the PIT Process proposal through flight ready Schedule first 4-weeks of SMOV and provide products for review before launch –First 4-weeks flight ready by launch minus eight weeks –Representative calendars are built assuming a nominal launch date and without normal science visits (SMOV only) –Provides feedback into the overall SMOV Timeline –Provides necessary input for the LRP
12
12 Beyond the PIT (cont’d) After launch, the SMOV and Operational databases are merged and the LRP rebuilt Visits are set flight ready during week T-5 Appropriate flight calendar requirements are defined during week T-4 Flight calendar building begins at week T-3 Execution
13
13 Proposal Processing Notification of submission - verify this is what is expected Preprocessor - checks for syntax errors and changes since last version, Assist Database is loaded Trans/CASM - creates the structure within the visits and links between the visits PMDB Load - loads the data into the Proposal Management DataBase
14
14 Proposal Processing (cont’d) Obset Update - computes and propagates pointing information and validates SI/SI detector state reqs GS Request - searches for suitable guide stars Visit Update - calculates windows and prepares the visit data for calendar construction Spike - computes overall schedulability of the visits PIT Galleyproof - email to PIT members indicating products ready for upcoming PIT meeting