Government Service Insurance System GSIS stand on the By WINSTON F. GARCIA President and General Manager meralco issue
2
Government Service Insurance System Major shareholders’ profile GSIS owns 26.5% of Meralco Together with other GFIs – SSS, Landbank, Philhealth and Pag- ibig – government accounts for 36.9% of Meralco shares
3
Government Service Insurance System Major shareholders’ profile Lopez holding company, FPHC, Union Fenosa and the Meralco pension fund own/ control 33.4% of Meralco
4
Government Service Insurance System Major shareholders’ profile Lopez group controls the management, while GSIS and other GFIs assume a minority role GSIS has 1.5 million members, 1/3 of which are MERALCO consumers.
5
Government Service Insurance System GSIS issues (as a shareholder) vs Lopez-controlled management 1.Insensitive to shareholders rights to profit sharing. - by end of 2007 unappropriated surplus reached PhP13.8 Billion.
6
Government Service Insurance System GSIS issues (as a shareholder) vs Lopez-controlled management a) No dividend declaration from 2001 to 2006 b) Only PhP500 Million was declared as dividends in 2008
7
Government Service Insurance System GSIS issues (as a shareholder) vs Lopez-controlled management 2. Lack of Good Corporate Governance Self-dealing transactions worth P55 billion yearly are confidential and beyond stockholders’ scrutiny -
8
Government Service Insurance System GSIS issues (as a shareholder) vs Lopez-controlled management 2. Lack of Good Corporate Governance Representatives of the Lopez Group, including the Chairman, participate actively in approving their self-dealing transactions -
9
Government Service Insurance System GSIS issues (as a shareholder) vs Lopez-controlled management 2. Lack of Good Corporate Governance Access to other transactions and documents of the company are severely restricted
10
Government Service Insurance System Issues transcending shareholder concerns Why does Meralco charge the highest electricity rate in the country? - Meralco rates are 20% to 30% more than the rest of the country
11
Government Service Insurance System To illustrate : P10.20 P8.89 P6.50 P6.44 P5.87 P7.63 P7.45 6.92 P10.20 P8.89 P6.50 P6.44 P5.87 P7.45 P7.03P6.92 * Based on May 2008 Billing.
12
Government Service Insurance System To illustrate: P7.63 P7.45 P7.50 P5.63 P4.92 P5.43 P5.22P5.21 * Based on May 2008 Billing.
13
Government Service Insurance System Anomalous because : Meralco is the biggest DU in the country, accounting for 60% of power produced in the country, with 4.4 million customers - By economies of scale and volume discount, Meralco should be cheaper.
14
Government Service Insurance System Meralco’s Excuses Lifeline subsidies to the poor household consumers - Fallacy because: a. Other DUs extend the same. b. Subsidy is less than 1% of the bill or roughly P0.05 to P0.06 centavos per kwh. -
15
Government Service Insurance System Meralco’s Excuses Taxes - Fallacy because: Other DUs pay the same rate of taxes. -
16
Government Service Insurance System Meralco’s Excuses High Cost of Napocor Rates - Fallacy because: a. Other DUs sourced 80% to 90% of their power from Napocor. b. Meralco sourced only 35% to 40% of its power needs from Napocor. -
17
Government Service Insurance System Attributable Causes Immoral and onerous IPP power supply contracts (Sta. Rita, San Lorenzo and Quezon Power) -
18
Government Service Insurance System Attributable Causes Backgrounder: - In 1997, Lopez-controlled management entered into contracts with Lopez-controlled companies to supply more than 50% of its power needs. - All cost of contracts were agreed to be passed on to consumers. - Contracts were implemented in 2002. -
19
Government Service Insurance System Attributable Causes Burdensome and immoral provisions: a. Lease of plants as capital recovery cost (capacity, fixed operating and transmission line fees) - Contracts are BOOs and not BOTs - Guaranteed purchase of all produced power -
20
Government Service Insurance System Attributable Causes Burdensome and immoral provisions: a. Lease of plants as capital recovery cost (capacity, fixed operating and transmission line fees) - Lease is grossly overpriced ($978/kw for Ilijan vs. $2,100/kw for Lopez Plants) - Cost to consumers : P108 billion (from 2002 to 2007) or an average of P18 billion per year -
21
Government Service Insurance System Attributable Causes b. Take or pay provision - Volume and rate are agreed by self- dealing parties without public participation - Amount passed on to consumers for unused gas totaled: in 2006 – P7.06 billion in 2007 – P4.89 billion -
22
Government Service Insurance System Attributable Causes c. Contractual Rate Fixing - Violates the provisions of EPIRA and its franchise Section 23 of EPIRA and Section 4 of the Meralco franchise impose the obligation to supply electricity to its captive market in the least cost manner -
23
Government Service Insurance System Attributable Causes c. Contractual Rate Fixing - To illustrate, NAPOCOR’s TOU rate as approved by ERC during off-peak ranges from P1.87 to P2.719/kwh. - Yet the contract obliges Meralco to buy power during off-peak hours at a higher rate from Lopez plants. -
24
Government Service Insurance System Computation of the Generation Charge Based on April 2008 supply month preliminary bills of power suppliers Avg. gen. cost = P4.87/kwh
25
Government Service Insurance System Attributable Causes - NAPOCOR and WESM rates appear higher because 80%-90% of their power were purchased during peak hours. - IPP power were purchased at uniform rates whether peak or off- peak. -
26
Government Service Insurance System Simulation 1: 50-50 distribution between NPC and IPPs (peak and off-peak) Reduction of 16% in gen. cost from P4.87/kwh to P4.08/kwh
27
Government Service Insurance System Simulation 2: 70% NPC, 30% IPPs Reduction of 19% in generation cost, from P4.87/ kwh to P3.93/kwh
28
Government Service Insurance System Simulation 3: 100% NPC Reduction of 24% in generation cost, from P4.87/kwh to P3.71/kwh
29
Government Service Insurance System Attributable Causes - More purchases from NAPOCOR have other cost reduction benefits. a. Transmission line charges will be reduced. -
30
Government Service Insurance System Attributable Causes b. More electricity discounts for residential consumers. EPIRA mandates maximum of 30 centavos/kwh discount to residential customers for NAPOCOR power. c. Multi-billion yearly lease rentals on Lopez plants passed on to consumers will have to be drastically reduced. -
31
Government Service Insurance System Attributable Causes Mismanagement a. Bloated bureaucracy - more than 6,000 regular employees - ratio of 4 officials for every 1 rank and file employee - costs P5.1 billion a year, or an average cost of P850,000 per employee -
32
Government Service Insurance System Attributable Causes b. Costly and unnecessary outsourcing of services mostly through subsidiaries - Miescor * All engineering construction - Corporate Information Solutions, Inc. * e-transactions -
33
Government Service Insurance System Attributable Causes - Meralco Energy, Inc. * energy systems management - Meralco Financial Services * Financial services provider - e-Meralco Ventures, Inc. * eBusiness Development - Soluziana * JV in management and information technology -
34
Government Service Insurance System Attributable Causes b. Costly and unnecessary outsourcing of services mostly through subsidiaries - costs P2.95 billion in 2007 -
35
Government Service Insurance System Attributable Causes c. Non-contributory pension plan - monthly pension for life for every retiring executive and employee, including their survivors - exhorbitantly high pension cost passed on to consumers -
36
Government Service Insurance System Meralco’s pension costs: P1.58B P1.79B P2.8B In 2008, only P1.8 billion was approved by ERC.
37
Government Service Insurance System Attributable Causes d. Non-competitive procurement process - Lopez Group controls the supply of major Meralco purchases: 1. First Philippine Industrial Corporation * service fuel requirements 2. Philippine Electric Corporation * distribution and power transformers -
38
Government Service Insurance System Attributable Causes - Lopez Group controls the supply of major Meralco purchases: 3. First Electro Dynamics Corp. * ballasts & current transformers 4. First Sumiden Circuits, Inc. * flexible printed circuits -
39
Government Service Insurance System Attributable Causes e. Systems Loss - Failure to curb system losses - 0 15 16 17 18 20062007 P15.8B P16.4B P17.3B 2005
40
Government Service Insurance System Attributable Causes - Lack of transparency * Law allows recoverable systems loss if due to technical loss or pilferage. * Yet, no accounting have been made on the occurrence of loss. -
41
Government Service Insurance System Attributable Causes - Abusive use of systems loss charges * Own use is considered systems loss. * Lease rentals are part of computing maximum allowable systems loss. -
42
Government Service Insurance System So, why does the Lopez- controlled Meralco management continue to charge its customers electricity rates which are more than 20% to 30% than what the rest of the country are paying? -
43
Government Service Insurance System Lopez Group sourced 80% to 90% of their business in Meralco and has been declaring record profits year in and year out. - In 2007, FPHC, its holding company, declared 66% increase in its net profits despite multi-billion loans. -
44
Government Service Insurance System FPHC and its subsidiaries P 107.930 B First Philippine Holdings Corp.31.807 FGHC International Limited1.462 FPH Fund Corporation2.919 First Philippine Infrastructure8.499 First Gen Corporation63.243 ABS-CBN 5.109 BENPRES Holdings 8.254 Bayan Telecomm 15.213 TOTAL P 136.506 B Lopez Group Loans
45
Government Service Insurance System Must we allow this situation to persist? -
46
Government Service Insurance System End of the Presentation Government Service Insurance System