1
RSRDC UNIT- III JAIPUR
2
ORGANISATION CHART RE Sh. A.M. Khan ARE Sh. Rajesh Gupta ARE Sh. S.K. Chejara ARE Sh. V.B. Mathur ARE Sh. Rakeev Gupta JEN Smt. Alka Mathur ACCOUNTANT Sh. B.C. Jain
3
Financial Work Load in Unit S. No. Name of WorkClient Deptt. A& F Sanction Expenditure till date Balance Work ARE – I Sh Rajesh Gupta 1USQ & LSQ at Chainpura Home1244.19816.31427.88 ARE – II Sh.S.K. Chejara 1Satsang Bhawan at Shri Radha Govind Deoji temple, Jaipur Trust400.00325.7774.23 ARE – III Sh.V.B. Mathur 1Research Hospital at RHSU, Pratap Nagar Medical1000.00677.76322.24 Total824.35 Rs. In Lacs
4
Important Works Completed during last 5 years
5
AMBEDKAR BHAWAN, JAIPUR Completion Cost – Rs. 3.83 Crs. Foundation Stone laid by Hon’ble Chief Minister on 14.04.2005 Inaugurated by Hon’ble Chief Minister on 14.04.2006
6
RAJASTHAN HEALTH SCIENCE UNIVERSITY, JAIPUR Completion Cost – Rs. 4.60 Crs. Foundation Stone laid by Hon’ble Chief Minister on 08.12.2005 Inaugurated by Hon’ble Chief Minister on 10.12.2007
7
Important Works in Progress
8
POLICE HOUSING SCHEME No. of Quarters:200 Nos. LSQ and 8 Nos. USQ Total Cost:Rs. 12.44 Crores Location:Chainpura, Jaipur Date of Start:28-02-2008 Stipulated Date of Completion:30-06-2009 Expenditure till Date:Rs. 8.16 Crores Likely Completion date:31-01-2010 Bottlenecks if any:slow progress by contractor
9
Satsang Bhawan at Shri Radha Govind Deoji temple, Jaipur Total Cost:Rs. 4.0 Crores Location: Shri Radha Govind Deoji temple, Jaipur Date of Start:July, 07 Date of Completion :September, 09 Expenditure till Date:Rs. 3.26 Crores Likely Completion date:31-12-2009 Present Status:Structure work completed, Finishing work in progress
10
Research Hospital at RHSU, Pratap Nagar, Jaipur Total Cost: Rs. 10.00 Crores Location: Pratap Nagar, Jaipur Date of Start: Jan, 08 Date of Completion: March, 09 Expenditure till Date: Rs. 6.77 Crores Likely Completion date: 30-06-2010 Bottlenecks if any : Work stopped as client has not deposited money
11
Monitoring of Toll Projects S. No. Name of WorkModeConstruction Cost Concession Period Toll Collection Agency 1Masi Bridge on Sanganer-Malpura Road (SH-12) Actual Plus Rs. 161.59 lacs 13 Years 05 Months & 01 Days(upto 22- 12-2020) Departmental (Tender for toll contract under process) 2Chomu-Ajitgarh- Shahpura Road Actual Plus Rs. 2223.15 lacs 14 Years 11 Months & 22 Days(upto 01- 09-2014) Departmental (Tender for toll contract under process) 3Chala- Neem ka Thana –Kotputli Road TenderRs. 1809.00 lacs 6 Years 02 Months & 27 Days(upto 06- 10-2010) M/s Ramfool Gurjar, Bhiwadi
12
Proposed New Works S. No. Name of WorkClient Deptt.ModeEstimated Cost 1.Buildings for different Bards near Ambedkar Bhawan Social Justice and Empowerment Deptt. Actual plus Rs. 3.40 Crores
13
THANKS