1 MuTRG-FEE Upgrade Status RIKEN/RBRC Itaru Nakagawa
2
2 Schedule
3
3 Station-1 Scaffold Construction Completed Station-2 Scaffold underway.+2weeks? Cable trays are installed Infrastructures –Ran LV/Signal Cables Oct-5,6,7,8 –Chassis Mount –Cooling Water South Arm Installation MuTRG-FEE Racks
4
4 New Cable Trays
5
5 Chassis & ADTX-FEE Cables Completed Chassis test completed (Katsuro, Ken’ichi, Yudai, Kazufumi, Murakami) –Water leak –Dry air blow –Backplane test (1 bad) –Conductivity test ADTX-FEE cable test completed (Katsuro, Kazufumi, Seiko, Yudai)
6
6 Chassis Mount Installed Before Run09 Newly Mounted St-1: Octant-1,2,3,4,5 Chassis are mounted. St-2&3: Oct-1,8,7,6,5 Chassis are mounted. Modified ground cables in St-2&3 Station-1 Station-2
7
7 Station-1 Cabling Ran St-1 LV&Fiber Cables Yudai, Kazufumi, Seiko, Itaru
8
8 Trunk Cable Setup at Rackroom Patch Bay Labeling and install Trunk cable connection at back Cable guide mount for trunk cables
9
9 Board QA Setup ready : Ken’ichi Actually QA proceed by Yudai and Seiko