CITY OF FORT COLLINS NEW FACILITIES KEN MANNON, KEN MANNON, Operations Services Director Operations Services Director
2
CITY PARK POOL REPLACEMENT $ 1.75M - SCD: MAY 2003
3
COLLINDALE CLUBHOUSE -14,660 SF $2.6 M – SCD: DEC 2002
4
CSU TRANSIT CENTER – 11 DROP/ PICKUP SITES $2.37M – PHASE I COMPLETED SEPT 2002
5
CSU TRANSIT CENTER SITE LAYOUT
6
EPIC / TWICE THE ICE - 36,400 SF $ 3.93M – SCD: MARCH 2003
7
FIRE STATION # 14 - 10,800 SF $ 2.4M - SCD: APRIL 2003
8
FOSSIL CREEK MAINT. BUILDING – 6,550 SF $ 700K – SCD: MARCH 2003
9
GARDENS ON SPRING CREEK - 4,000 SF + 10 ACRES GARDENS - $ 2.05M - SCD: SEPT 2003
10
GARDENS ON SPRING CREEK – LONG RANGE MASTER PLAN
11
NEW METER SHOP SITE - 8,500 SF $ 2.03M - SCD: DEC 2003
12
NEW N S A C - 52,000 SF CONCEPTUAL PHASE: $100,000 YR 2004 FUNDING: $8 M
13
NIX SITE MAINTENANCE FACILITY - 6,000 SF $ 2.05M - 27.48 AC COMPLETED: JUNE 2002
14
NIX SITE – FARM HOUSE – 6,500 SF $ 2.4M - SCD: OCT. 2002
15
SOUTHRIDGE GOLF CART STG – 3,250 SF $ 200,000 - SCD: EARLY 2003
16
TRAFFIC OPS BUILDING - 9,300 SF $ 2.17M - SCD: NOV. 2002
17
UTIL’S WH YD IMPRVMNT SITE – EAST SIDE $ 3.25M - SCD: SUMMER 2003