Presentation is loading. Please wait.

Presentation is loading. Please wait.

1 Rev: 5/05/07 MSE-415: B. Hawrylo Chapter 16 Managing Projects MSE-415: Product Design Lecture #3.

Similar presentations


Presentation on theme: "1 Rev: 5/05/07 MSE-415: B. Hawrylo Chapter 16 Managing Projects MSE-415: Product Design Lecture #3."— Presentation transcript:

1 1 Rev: 5/05/07 MSE-415: B. Hawrylo Chapter 16 Managing Projects MSE-415: Product Design Lecture #3

2 2 Rev: 5/05/07 MSE-415: B. Hawrylo Lecture Objectives: Homework #1 (Hand in blank paper with name if not done for attendance points) Group Formation Lab Notebook procedure Chapter 16 - Managing Projects  Fundamental characteristics of interacting tasks Agree upon design project

3 3 Rev: 5/05/07 MSE-415: B. Hawrylo Chapter 16 – Managing Projects 3 Types of tasks

4 4 Rev: 5/05/07 MSE-415: B. Hawrylo Chapter 16 – Managing Projects We’re going to talk about task-based…

5 5 Rev: 5/05/07 MSE-415: B. Hawrylo Chapter 16 – Managing Projects Project task

6 6 Rev: 5/05/07 MSE-415: B. Hawrylo Practice ABCDEFGHIJ A* BX* X C *X X X D * X E * X F X * X GX X * HX *XX IX * J XXX* Task C requires information from what tasks? Task D transfers information to what tasks? Example #1 Example #2 ABCDEFGHIJ A* X B * C * XX D * EX *X F X* G X * H X * I X * JXX X * Task E requires information from what tasks? Which tasks are interdependent coupled?

7 7 Rev: 5/05/07 MSE-415: B. Hawrylo Practice ABCDEFGHIJ A* BX* X C *X X X D * X E * X F X * X GX X * HX *XX IX * J XXX* Task C requires information from D, F, I Task D transfers information to C, G Example #1 Example #2 ABCDEFGHIJ A* X B * C * XX D * EX *X F X* G X * H X * I X * JXX X * Task E requires information A, F E, F tasks are interdependent coupled.

8 8 Rev: 5/05/07 MSE-415: B. Hawrylo Gantt Basics Basically, a timeline with tasks that can be connected to each other Can be created with simple tools like Excel, but specialised tools like Microsoft Project make life easier

9 9 Rev: 5/05/07 MSE-415: B. Hawrylo Making a Gantt chart Step 1 – list the tasks in the project

10 10 Rev: 5/05/07 MSE-415: B. Hawrylo Step 2 – add task durations Making a Gantt chart

11 11 Rev: 5/05/07 MSE-415: B. Hawrylo Step 3 – add dependencies (which tasks cannot start before another task finishes) Making a Gantt chart

12 12 Rev: 5/05/07 MSE-415: B. Hawrylo The arrows indicate dependencies. Task 1 is a predecessor of task 2 – i.e. task 2 cannot start before task 1 ends. Task 3 is dependent on task 2. Task 7 is dependent on two other tasks Electrics, plumbing and landscaping are concurrent tasks and can happen at the same time, so they overlap on the chart. All 3 can start after task 4 ends. Painting must wait for both electrics and plumbing to be finished. Task 9 has zero duration, and is a milestone Making a Gantt chart

13 13 Rev: 5/05/07 MSE-415: B. Hawrylo Step 4 – find the critical path The critical path is the sequence of tasks from beginning to end that takes the longest time to complete. It is also the shortest possible time that the project can be finished in. Any task on the critical path is called a critical task. No critical task can have its duration changed without affecting the end date of the project. Making a Gantt chart

14 14 Rev: 5/05/07 MSE-415: B. Hawrylo MS Project can work out the critical path for you! The length of the critical path is the sum of the lengths of all critical tasks (the red tasks 1,2,3,4,5,7) which is 2+3+1+1.5+2+1 = 10.5 days. In other words, the minimum amount of time required to get all tasks completed is 10.5 days The other tasks (6,8) can each run over-time before affecting the end date of the project

15 15 Rev: 5/05/07 MSE-415: B. Hawrylo The amount of time a task can be extended before it affects other tasks is called slack (or float). Task 6 can take an extra day and a half before it affects the project’s end date, so each has 1.5 day’s slack. Making a Gantt chart

16 16 Rev: 5/05/07 MSE-415: B. Hawrylo Critical tasks, by definition, can have NO slack. Tip: If ever asked Can task X’s duration be changed without affecting the end date of the project?, if it is a critical task the answer is always NO! Making a Gantt chart

17 17 Rev: 5/05/07 MSE-415: B. Hawrylo This PERT chart follows the “Activity on Arrow” style. The tasks are shown by arrows. Task name are shown by letters, in this case. The circles are called nodes. The nodes indicate the start or end of tasks. Task durations are the shown by the numbers. PERT Charts

18 18 Rev: 5/05/07 MSE-415: B. Hawrylo The path duration is: A-B-C-E-I = 2+3+1+4+3=13 A-B-D-F-I = 2+3+3+3+3=14 A-G-H-I = 2+2+5+3 = 12 Therefore, Completion time = 14 Critical path is A-B-D-F-I Slack time of A-B-C-E-1 = 1 Slack time of A-G-H-1 = 2 PERT Charts

19 19 Rev: 5/05/07 MSE-415: B. Hawrylo Pert Example A.1 B.2 C.1 D.2 E.3 F.1 G.1 H.2 I.2 J.1 K.2 L.1 M.1 What is the duration to complete path A-D-H-J-L? What is the critical path? How does the project duration change if task E is shorten to 2? How about 1? What is the best way to shorten the total duration?

20 20 Rev: 5/05/07 MSE-415: B. Hawrylo Chapter 16 – Managing Projects Baseline Project Planning The Contract Book Project Task List Team Staffing and Organization Project Schedule Project Budget Project Risk Plan

21 21 Rev: 5/05/07 MSE-415: B. Hawrylo Chapter 16 – Managing Projects The Contract Book Documents the project plan Mission Statement, Customer needs list, competitive analysis, product specifications, sketches, concept report, sales forecast, economic analyses, manufacturing plan, project plan, project performance, incentives…

22 22 Rev: 5/05/07 MSE-415: B. Hawrylo Chapter 16 – Managing Projects Project Task List List the tasks which make up the project. Estimate the amount of time required for each task TaskEstimated Person-Weeks Task 18 Task 216 Task 324

23 23 Rev: 5/05/07 MSE-415: B. Hawrylo Chapter 16 – Managing Projects Team Staffing and Organization The speed at which a team can complete a project is based upon 7 criteria. 1.There are 10 or fewer members of the team. 2.Members volunteer to serve on team. 3.Members serve on the team from the time of concept development to launch. 4.Members are assigned to the team full-time. 5.Members report directly to team leader. 6.The key functions are on the team. 7.Members are located within conversational distance to one another.

24 24 Rev: 5/05/07 MSE-415: B. Hawrylo Chapter 16 – Managing Projects Project Schedule Merger of the project task and project timeline. 1.Use the DSM or PERT to identify dependencies. 2.Position key milestones. 3.Schedule tasks, considering the project staffing and critical resources. 4.Adjust the timing of the milestone to be consistent with the time required for the tasks.

25 25 Rev: 5/05/07 MSE-415: B. Hawrylo Chapter 16 – Managing Projects Project Budget Often represented by a simple spreadsheet. 1.Staff salaries 2.Materials/services 3.Prototype Molds 4.Outside Resources 5.Travel 6.Other?

26 26 Rev: 5/05/07 MSE-415: B. Hawrylo Chapter 16 – Managing Projects Project Risk Plan Dealing with project variation Teams should compile a list of what can go wrong and how to solve problems should they occur. RiskRisk LevelActions to Minimize AModerateA1, A2, A3 BLowB1, B2 CHighC1, C2, C3, C4

27 27 Rev: 5/05/07 MSE-415: B. Hawrylo Chapter 16 – Managing Projects Modifying the Baseline Plan Accelerating the Plan 1.Start the project early. 2.Manage the project scope. Don’t allow ‘feature creep’ 3.Facilitate the exchange of essential information. 4.Complete tasks on critical path more quickly. 5.Aggregate safety times. 6.Eliminate some critical paths entirely. 7.Eliminate waiting days for critical path resources. 8.Overlap some critical tasks. 9.Pipeline large tasks 10.Outsource some tasks

28 28 Rev: 5/05/07 MSE-415: B. Hawrylo Chapter 16 – Managing Projects Modifying the Baseline Plan Accelerating the Plan 11.Perform more iterations quickly. 12.Decouple tasks to avoid iterations. 13.Consider sets of solutions.

29 29 Rev: 5/05/07 MSE-415: B. Hawrylo Chapter 16 – Managing Projects Project Execution Smooth execution of a well-planned project should pay attention to 3 components: 1.What mechanisms can be used to coordinate tasks. 2.How can the project status be assessed? 3.How can we correct undesirable deviations?

30 30 Rev: 5/05/07 MSE-415: B. Hawrylo Chapter 16 – Managing Projects What mechanisms can be used to coordinate tasks? 1.Informal Communication 2.Meetings 3.Schedule Display 4.Weekly Updates 5.Incentives 6.Process Documents

31 31 Rev: 5/05/07 MSE-415: B. Hawrylo Chapter 16 – Managing Projects Corrective Actions 1.Change the timing or frequency of meetings. 2.Change the project staff. 3.Locate the team together physically. 4.Solicit more time and effort from the team. 5.Focus more effort on critical tasks. 6.Engage outside resources. 7.Change the project scope/schedule

32 32 Rev: 5/05/07 MSE-415: B. Hawrylo Next Week September 19, 2007 Homework #2 - Handout Design and Development Project  Prepare a detailed project plan – Project timeline and major milestones – Goals, objectives and scope – Risk assessment, assumptions and critical project barriers – Milestones – Project roles and responsibilities – Estimated start and completion of each step Read Chapter 4 – Identifying Customer Needs  Product specifications Prepare for a potential quiz on chapters 1,2,3,4,16, and additional readings


Download ppt "1 Rev: 5/05/07 MSE-415: B. Hawrylo Chapter 16 Managing Projects MSE-415: Product Design Lecture #3."

Similar presentations


Ads by Google