Presentation is loading. Please wait.

Presentation is loading. Please wait.

12015-11-19 These materials are prepared only for the students enrolled in the course Distributed Software Development (DSD) at the Department of Computer.

Similar presentations


Presentation on theme: "12015-11-19 These materials are prepared only for the students enrolled in the course Distributed Software Development (DSD) at the Department of Computer."— Presentation transcript:

1 12015-11-19 These materials are prepared only for the students enrolled in the course Distributed Software Development (DSD) at the Department of Computer Science and Engineering, University of Mälardalen, Västerås, Sweden and at the Faculty of Electrical Engineering and Computing, University of Zagreb, Croatia (year 2009/2010). For all other purposes, authors’ written permission is needed! The purpose of these materials is to help students in better understanding of lectures in DSD and not their replacement! NOTICE!

2 22015-11-19 Distributed Software Development

3 32015-11-19 Project Plan : Live TV Customers : Damir Isovic (MDH) and Klas Eriksson (OneDial AB)

4 42015-11-19 Table of contents 1. Development methodology 2. Deliverables 3. Activity plan 4. Financial plan 5. Project risks

5 1. Development methodology Agile method with 3 iterations : –Alpha prototype (end of October) –Beta prototype (3rd of November) –Release Candidate (before Christmas holidays) 52015-11-19 Capture Record Send the video Studio Server Receive 1 stream Send the stream Live Broadcast Receive the stream in Real-time

6 2. Deliverables Planned report Minutes of meeting –1 team member responsible per meeting –Change of duty every meeting Weekly report –Sent to PL before12:00 Monday –Summarized and Compiled by the PL 62015-11-19 Project plan Requirements definition Design description Acceptance test plan Test report Final project report

7 3. Activity plan Use of a Gantt 6 phases : –Analysis / Software requirements – 15% –Design – 10% –Development – 30% –Testing – 30% –Documentation - 10% –Pilot Project to the customer – 5% 72015-11-19

8 4. Financial plan No budget for this project Equipement provided : –Virtual Server (Linux) –Nokia N95 8GB Our free time 82015-11-19

9 5. Project risks Lack of knowledge –Take time to do research Faulty equipments –Do backups! Member unavailable –Assure that every piece of information and code is shared, documented,… Choice of wrong technology –Study and evaluate different technologies first –Create a prototype 92015-11-19


Download ppt "12015-11-19 These materials are prepared only for the students enrolled in the course Distributed Software Development (DSD) at the Department of Computer."

Similar presentations


Ads by Google