4/21/2003CVEN 349 - Maxwell 1 Project Control: Control of Work and Cost Versus Time Part 08-04 November 19, 2015.

Similar presentations


Presentation on theme: "4/21/2003CVEN 349 - Maxwell 1 Project Control: Control of Work and Cost Versus Time Part 08-04 November 19, 2015."— Presentation transcript:

1 4/21/2003CVEN 349 - Maxwell 1 Project Control: Control of Work and Cost Versus Time Part 08-04 November 19, 2015

2 4/21/2003CVEN 349 - Maxwell 2 Purpose Describe how to use a linear approximation of the combined sets of S-Curves to: Determine current project status with respect to schedule and budget. Project budget and schedule variances at the close of the job. Recap possible counter-measures for the four possible general situations.

3 4/21/2003CVEN 349 - Maxwell 3 Learning Objectives Given a set of As-Planned and As-Built (to date) construction project control data points, be able to determine: Current Schedule and Budget Variances for a simple work package. Probable Schedule and Budget variances at the completion of the work package. Determine adjustments in work and expenditure rates to complete the work as planned. Assuming that the “non-flat part” of the S-Curves can be ignored.

4 4/21/2003CVEN 349 - Maxwell 4 Assumptions 1. A complex project can be decomposed into simple, independent Work Packages. 2. The Work Package under consideration has no ramp-up or ramp-down; i.e., work proceeds linearly. 3. The amount of work accomplished can be quickly and accurately measured. 4. The daily cost rate for the Work Package can be computed from labor rates, equipment rental rates, and material placement rates. 5. The cost and work rates can be held constant.

5 4/21/2003CVEN 349 - Maxwell 5 Example Problem: As-Planned A good example of a work package that will have small ramp-up/ramp-down effects is the construction of a large concrete slab. The project is to pour and trowel finish a 50,000sf slab, 8” thick. Forms and rebar are in place. You estimate (using the Means Manual) that your crew can place and finish 2,500sf/day at a cost of $3,000/day. That is, you plan to complete 50,000sf, in 20 days, at a cost of $60,000.

6 4/21/2003CVEN 349 - Maxwell 6 Example Problem: As-Built The project manager checks progress on a regular basis and finds: 1. At day 5, 2. 16,000 s-f have been completed, and 3. $ 18,000 has been spent.

7 4/21/2003CVEN 349 - Maxwell 7 Problem Summary Estimate (As-Planned): 20 days (PS, Planned Schedule) 50,000 sf (PW, Planned Work) $60,000 (PC, Planned Cost) Progress to date (As-Built) 5 days (AS, Actual Schedule) 16,000 sf (AW, Actual Work) $18,000 (AC, Actual Cost)

8 4/21/2003CVEN 349 - Maxwell 8 Exercise #08-04.1 Based upon a procedure similar to S-Curve analysis: 1. Individually determine the current job status with respect to schedule and budget. 2. As pairs, locate any problems and be prepared to discuss.

9 4/21/2003CVEN 349 - Maxwell 9 Answers to Exercise #08-04.1, Using “S-Curve Method” Under

10 4/21/2003CVEN 349 - Maxwell 10 Answer to Exercise #08-04.1, Using Ratios or Similar Triangles

11 4/21/2003CVEN 349 - Maxwell 11 Exercise #08-04.2 Something new with linear control: 1. As individuals determine, the schedule and budget variance upon completion? 2. As pairs, be prepared to discuss an “end game” strategy. 3. As pairs, determine the new work and spending rates to execute the “end game.”

12 4/21/2003CVEN 349 - Maxwell 12 Answers, Exercise 08-04.2

13 4/21/2003CVEN 349 - Maxwell 13 The 4 Possible Cases. 1. Most likely Over Budget Behind Schedule 2. Common Over Budget Ahead of Schedule 3. Common Under Budget Behind Schedule 4. Least Likely Under Budget Ahead of Schedule

14 4/21/2003CVEN 349 - Maxwell 14 Important Points to Remember This technique works best for well defined, short work packages will negligible ramp-up and down. Work progress must be easy to measure. Check points must be established early and often during construction. Forecasted end points are probably more meaningful than current status.

15 4/21/2003CVEN 349 - Maxwell 15 Reminder! Class Assessment Questions In 1 sentence what was the muddiest part of this module? In 1 sentence, what part of this module could be improved the most?


Download ppt "4/21/2003CVEN 349 - Maxwell 1 Project Control: Control of Work and Cost Versus Time Part 08-04 November 19, 2015."