Download presentation
1
Critical Steps in Process Design
Michel Gigon, Associate, Laporte Consultants September 28, 2006
2
Agenda Definitions and General Considerations
Critical Steps in Process Design
3
Definitions Product Development : Creation of a new product
Process Development : Development of a production method (recipe) Process Design : Design of the equipment required for the production of a product, according to a pre-determined process.
4
Process Design in the pharmaceutical industry
Process Design versus Product Life Cycle
5
YEARS Discovery Biological Tests Phase I Phase II Phase III NDA
Launch & Commercial production PRODUCT DEVELOPMENT YEARS
6
-20 0 2 4 6 8 10 YEARS Discovery Biological Tests Phase I Phase II
Phase III NDA Launch & Commercial production Process Research (1 gr – 1 kg) PRODUCT DEVELOPMENT PROCESS DEVELOPMENT YEARS Commercial Plant Transfer (100 kg- tons) Pilot Development (1 kg-100 kg) Optimisation, Capacity Increase
7
FACILITY AND EQUIPMENT
Discovery Biological Tests Phase I Phase II Phase III NDA Launch & Commercial production Process Research (1 gr – 1 kg) Pilot Plant Operation First Plant Operation Laboratory – Research Laboratory – Development PRODUCT DEVELOPMENT PROCESS DEVELOPMENT FACILITY AND EQUIPMENT YEARS Commercial Plant Transfer (100 kg- tons) Pilot Development (1 kg-100 kg) Plant Operation Optimisation, Capacity Increase
8
FACILITY AND EQUIPMENT
Discovery Biological Tests Phase I Phase II Phase III NDA Launch & Commercial production Process Research (1 gr – 1 kg) Pilot Plant Operation First Plant Operation Laboratory – Research Laboratory – Development PRODUCT DEVELOPMENT PROCESS DEVELOPMENT FACILITY AND EQUIPMENT Design, Build, Validate YEARS Commercial Plant Transfer (100 kg- tons) Pilot Development (1 kg-100 kg) Subsequent Plant Operation Optimisation, Capacity Increase PROCESS DESIGN
9
The four pivots of process design
Mechanical Science Automation Process Validation Pharmaceutical Process
10
Project Life Cycle Conceptual Design Preliminary Detailed
Equipment Manufacturing Construction Validation Support FAT Start-Up SAT
11
Conceptual design Definition of the user requirements Process
Production capacity Product specification Development phase of the product
12
Conceptual design Definition of the user requirements Process
Pilot plant : unit operations, lab procedure example First commercial plant : lab method, preliminary results from pilot plant Subsequent facility : existing process
13
Conceptual design Definition of the user requirements
Production capacity Requirements (kg/year, units/year) Batch size (kg/batch, units/lot) Titre (kg/L) Production time (days/lot) Production schedule (24/7, 8/5) Operation (by campaign, by lots) Production opening (weeks/year) Losses (%) Equipment utilisation (%)
14
Conceptual design Definition of the user requirements
Production capacity Requirements (kg/year, units/year) Batch size (kg/batch, units/lot) Titre (kg/L) Production time (days/lot) Set-up, production process, cleaning, sterilisation, testing, product change-over….
15
Conceptual design Definition of the user requirements
Production capacity …. Equipment utilisation (%) Pilot plant : % First commercial plant : 70% max Mature process : > 80%
16
Conceptual design Definition of the user requirements
Product specification Sterility Water quality Concentration Impurity levels
17
Conceptual design Definition of the user requirements
Development phase of the product Flexibility Process maturity Laboratory Pilot plant First Plant Subsequentplant
18
Conceptual design Risks Definition of the user requirements Process
Production capacity Product specification Development phase of the product Risks Inability to manufacture the product Inadequate plant capacity Lower quality product Inappropriate flexibility
19
Preliminary design Facility definition and sizing
Preliminary specifications of the process equipment Sizing of utilities Sizing of spaces Preliminary specifications of the automation system
20
Preliminary design Facility definition and sizing
Preliminary specification of the process equipment Volume, capacity Material Functionality Process paramaters Design and operation range (pressure, temperature, etc…)
21
Preliminary design Facility definition and sizing
Sizing of utilities and spaces Process equipment Spaces production, mechanical rooms, warehouse… Process support CIP, solution prep… Building utilities HVAC, Steam, chilled water, power… Process Utilities water, effluent treatment…
22
Preliminary design Facility definition and sizing
Preliminary specification of the automation system Manual vs automated operation Transfer panel vs manifold… Level of automation Local controller, unit operation control, batching, archiving General architecture
23
Preliminary design Risks Facility definition and sizing
Inadequate process equipment Insufficient space and utilities Inadequate control and automation => Production capacity cannot be met => Difficulties of operation
24
Detailed design Detailed specification of all components of the installation Mechanical components Fabrication specification Installation specification Automation Hardware Software
25
Detailed design P&ID Components List I/O List Sequences of operation
Mechanical components specification Automation components specifications Alarms Interlocks Access rights Installation drawing (3D, isometrics) Control panel drawings loop diagram wiring diagram Programming
26
Detailed design Detailed specification of all components of the installation Risks Inappropriate installation Cleaning and sterilisation issues Corrosion issues Operational difficulties Maintenance difficulties Accessibility issues
27
Construction and Fabrication
Construction follow-up Documentation follow-up Start-up and testing (FAT, SAT)
28
Construction and Fabrication
Construction follow-up Ergonomy and accessibility Slopes Dead legs Weld quality Etc…
29
Construction and Fabrication
Documentation follow-up Update of design document (P&ID, specifications) Data Sheets Isometrics Test Certificates Turn-Over Package Validation Maintenance
30
Construction and Fabrication
Start-up and testing Verification of the quality of fabrication Verification of all design hypothesis Control of process parameters Process sequences are achievable Equipment drainable, cleanable and sterilisable
31
Construction and Fabrication
Construction follow-up Documentation follow-up Start-up and testing (FAT, SAT) Risks Inadequate installation Cleaning and contamination issues Ergonomic and operational issues Inadequate documentation Validation issues Maintenance issues
32
Validation Adequate documentation facilitates protocol preparation and execution Review of validation criterion can avoid unnecessary deviation Participation in protocol execution facilitates and accelerates protocol execution
33
Questions ?
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.