Presentation is loading. Please wait.

Presentation is loading. Please wait.

1 1. Some recent views (16.5.2012) 2 Linac tunnel - 2012 3.

Similar presentations


Presentation on theme: "1 1. Some recent views (16.5.2012) 2 Linac tunnel - 2012 3."— Presentation transcript:

1 1 1

2 Some recent views (16.5.2012) 2

3 Linac tunnel - 2012 3

4 Ion source and RFQ 4 Production of the new H- source is progressing, to be installed soon in the 3 MeV test stand Radio Frequency Quadrupole (RFQ): Last segment (#2) successfully brazed Assembly of complete RFQ week of 16.7 RF measurements week of 23.7

5 Financial situation - 2012 5  Total 2012 budget (CET): 25.9 MCHF  Paid at 9.7.12: 5.5 MCHF  Paid + Committed at 9.7.12: 19.9 MCHF  High level of committments: HP-RF (4.9M), PIMS (1.3M), CV (1.5M), magnets (1M), EL (0.6M), DTL (0.6M) + others. Comittments should be moved to 2013 for items not to be delivered in 2012.

6 Financial - BE 6 From Alan Burns presentation at BEMB 9.7.12

7 Project status – from EVM 7 Linac4 global green: AC yellow: EV 50M/90M=56% of project Some delay w.r.t. original plan Good agreement between earned value and actual cost, but several discrepancies at WP level

8 Linac and infrastructure 8 Linac machine overspending by 2M (includes components paid before earning the value…) Infrastructure (CE,CV,EL) underspending by 2M (includes services where the value is earned before the bill is paid…).

9 CV and EL 9 CV EL

10 Source and RFQ 10 Source and LEBT RFQ

11 Accelerating structures 11 general DTL CCDTL PIMS

12 RF 12 LLRF HPRF

13 BI and CO 13

14 Power converters and vacuum 14

15 BID’s and Magnets 15

16 The Linac4 Safety File(s) 16 2004 2008 2014/2016 2046? Linac4 Safety File (EDMS 905423) June 2008, 91 pages All safety aspects of project, more emphases on civil engineering and machine equipment Approval for tendering of building and execution phase the project phases New Linac4 Safety Folder In preparation by Anne Funken All safety aspects of project, more emphasis on operation. Update of existing Safety File, document following recent CERN safety documentation standard (EDMS1177755, 15.6.2012). Approval for operation above 3 MeV energy (2014) Linac4 Decommissioning Report In preparation (deadline end 2012) Calculation of activation at end of life Estimate of material quantities for disposal Estimate of the costs (for financial reports)

17 Linac4 Safety Folder 17  The referential in matters of safety for Linac4 is the Safety File which dates back to 2008, https://edms.cern.ch/document/905423/1https://edms.cern.ch/document/905423/1  The update of this document is in progress to integrate the changes which occurred and detail subjects which were not yet defined:  Interlocked areas and EIS  Dumps  Ion source changes  At the same time, the contents of the document is reorganized according to the new “Quality Procedure for Safety Documentation Management”, https://edms.cern.ch/document/1177755/0.2 https://edms.cern.ch/document/1177755/0.2  The safety folder is composed of 4 main safety files (separate documents) :  Descriptive part  Demonstrative part (Risk Control Measures)  Operational part  REM part (Records, Experience, Monitoring)

18 18 Descriptive partContentStatusDeadline Section 1Goal & Motivation of the Linac4 100% Section 2Location & vicinity 100% Section 3Technical description 70% of the information collected August 2012 Section 4Project phases & organization 100% Section 5Operation phases Updates in preparation December 2012 Section 6Future evolution of the facility 100% Section 7Dismantling phase & disposal Updates in preparation December 2012 Descriptive part - progress

19 Editorial work progress 19 Demonstr ative part ContentStatusDeadline for completion Section 1Identification of hazards Updates 2012 done, editing work to start September 2012 Section 2Risks analysis - Ion source - Remaining systems -Under way for the gas injection system -Updates 2012 not started -September 2012 -December 2012 Section 3Risks control measures - Ion source - Remaining systems -Under way for the gas injection system -Updates 2012 not started -September 2012 -December 2012 Risk control measures regarding high voltage and RF power of the ion source, EDMS 1212106

20 Operational part 20  Content : list of the safety-related and operational procedures with the links to the documents  Deadline :  These procedures shall be prepared and approved prior to the commissioning and operation phases  For the ion source: the deadline is October 2012

21 Thank you for your attention 21

22 Linac4 WBS 22 7 management WPs 23 technical WPs 11 sub-WPs 7 management WPs 23 technical WPs 11 sub-WPs

23 Linac4 Safety structure The Project Leader is responsible for Safety in the Project (he can be assisted by a PSO). - WorkPackages are responsible for Safety within their WP (and follow the standard safety line Group –- Department assisted by DSO). - The Project provides the global view and the time perspective: Coordinates safety issues at the interfaces between WPs (transfer of information, coactivity, etc.) Verifies that Safety issues are correctly considered within the individual WPs. Directs safety issues in the sense of a minimisation of risks for all the different phases of the project. From SAPOCO 4.8: Project Leaders are responsible for Safety in their project. They must ensure that all Safety requirements have been taken into account from the design stage and subsequently at all stages of their project’s development through to its dismantling and final disposal.

24 Linac4 Hazard Inventory 24 Strategy for radiation protection (see next slides) Radio Frequency (352 MHz, standard precautions) Caesium for ion source, specific procedures Standard at CERN

25 Upgrade of measurement lines 25 Upgrade of the beam measurement lines at the entrance of PS Booster: - Upgrade for 160 MeV energy (new magnetic elements and new measurement technique); - Introduction of appropriate beam dumps to be used during measurements


Download ppt "1 1. Some recent views (16.5.2012) 2 Linac tunnel - 2012 3."

Similar presentations


Ads by Google