Design Kickoff Meeting Becky Houdek, MCWD 6-27-12
2
Outline Background Design concepts Expectations Process/Schedule What we need from you Questions
3
Background Project identified in District Plan Project goals: Improve riparian vegetation Stabilizes banks (deep roots) Filters runoff from land and moderates flow Provides shading and shelter Deters geese Aesthetic value Improve in-stream habitat and function Education/demonstration
4
Turf Grass vs. Native Plant Roots
5
Background Feasibility study completed last summer Gauged homeowner interest Voluntary project Neighborhood meeting, survey, site visits 29 have expressed interest Board ordered last fall Funding design, construction, 3 yrs maintenance
6
Design Concepts Balance homeowner interests/preferences with natural resource benefits Aesthetics, plant height, existing structures, etc. Vegetated streambank with 10-20 ft of native plantings that transitions to turf (minimum of 10 ft) Primarily grasses and flowers, shrubs optional Little to no rock needed In-stream habitat improvements
7
Expectations District will fund design, construction, and first 3 yrs of maintenance, then homeowners take over Plantings will take a few years to be fully established - will incorporate some plant plugs so you see some growth and color right away District rules require a declaration for any streambank projects Much of the land along creek is owned by City – will need 3-party agreement Not all properties may be suitable for this project
8
Process/Schedule Determine who is on board - Letter of intent Develop designs/planting plans: Individual site visits – mid-July Preliminary designs – Distributed late July Homeowner review and feedback (2-3 weeks) – mid-August Finalize designs – August-September Execute declarations/maintenance agreements – September Construction: In-stream/bank work – January - mid-February Planting – Spring 2013
9
What We Need From You Emails and phone numbers Flexibility and responsiveness Coordinate on-site meetings Sign up for a time For site visit: Complete plant worksheet Sign letter of intent Declaration/maintenance agreement (once designs are developed)
10
Questions? Contact information: Becky Houdek 952-641-4512 bhoudek@minnehahacreek.org Project webpage: http://www.minnehahacreek.org/projects (scroll down to Reach 14) Citizens for the Minnehaha Creek Corridor: www.minnehahacreekcorridor.org