Handing Over the Keys to a Successful Construction Project Jason Morgan, Assistant Chief, Los Angeles County Department of Public Works Chuck McCormick, Mead & Hunt Cory Hazlewood, C&S Companies
2
Handing Over the Keys to a Successful Construction Project Jason Morgan, Assistant Chief, Los Angeles County Department of Public Works
3
A Sponsor’s Perspective Elements of a “Successful” project: Solid foundation Process
4
A Sponsor’s Perspective ACIP PROJECT TIMELINE / CHECKLIST
5
A Sponsor’s Perspective ACIP PROJECT TIMELINE / CHECKLIST
6
A Sponsor’s Perspective ACIP PROJECT TIMELINE / CHECKLIST
7
A Sponsor’s Perspective ACIP PROJECT TIMELINE / CHECKLIST
8
A Sponsor’s Perspective ACIP PROJECT TIMELINE / CHECKLIST
9
A Sponsor’s Perspective ACIP PROJECT TIMELINE / CHECKLIST
10
A Sponsor’s Perspective ACIP PROJECT TIMELINE / CHECKLIST
11
A Sponsor’s Perspective Elements of a “Successful” project: Solid foundation Process Collaborative planning / relationships
12
A Sponsor’s Perspective Airport Capital Improvement Plan (ACIP) AIP Eligible Realistic (not wish list) Organized presentation Descriptive titles Cost breakdown Ranking / Master Plan / RSAT items
13
A Sponsor’s Perspective Airport Capital Improvement Plan (ACIP) AIP Eligible Realistic (not wish list) Organized presentation Descriptive titles Cost breakdown Ranking / Master Plan / RSAT items
14
A Sponsor’s Perspective Elements of a “Successful” project: Solid foundation Process Collaborative planning / relationships Appropriately designed Fully-funded (Federal & State grant funding + Local share) On-time On-budget On-scope (got what we asked for, what is best for the users) Compliant (Sponsor Assurances, Advisory Circulars, etc.) Effective Communication with FAA/ADO Routine Drawdowns (within 30 days of invoice from contractor) Project Oversight / Quality Control
15
A Sponsor’s Perspective Post Construction & Ownership: Pre-closeout requirements… Conduct final inspection Submit closeout documents & information to FAA ADO Closeout letter and final drawdown from sponsor Grant assurances Parlay your success on to the next project(s)!
17
Handing Over the Keys to a Successful Construction Project Chuck McCormick, Mead & Hunt
18
Construction Safety & Phasing Plan AC 150/5370-2F Operational Safety on Airports During Construction FAA CSPP Checklist Project Schedule
19
Construction Safety & Phasing Plan Coordination Sponnsor FAA Consultant Contact Sheet Construction Emergency Utility
20
Construction Safety & Phasing Plan SMS AC 150/5200-37 Introduction to SMS for Airport Operations FAA Order 5200.11 FAA Airports SMS for Airports
21
CSPP and SRM Process ARP SOP 1.00 FAA Evaluation of Sponsor’s Construction Safety and Phasing Plans Funded by the AIP or PFC Programs
22
Construction Safety & Phasing Plan Areas affected by Project Safety Areas Part 139 – ACSI Coordination NAVAIDS Contractor Access Wildlife Management
23
Construction Safety & Phasing Plan FOD Inspection Requirements NOTAM Changes to Phasing During Construction
25
Handing Over the Keys to a Successful Construction Project Cory Hazlewood, C&S Companies
26
FAA Advisory Circular 5100-14E Construction Phase CM Plan guidelines Contractor Control Good communication with funding agencies Pre-Con clarity Meetings FAA weekly reporting Field changes / cost Construction Process
27
Important facts on Construction Observation? Construction observation or inspection Part-time, full-time, or period observation Sponsor’s Budget not always the driver Independent Fee Estimate (IFE) Process Sponsor in house CA/CO You have Procurement options!
28
Project Close Out Field Work Acceptance - Letter Punchlist Final Acceptance- Letter Record Drawings Contractor Releases DBE Summary Warranty or Guarantee Final Construction Report Certs Summary of work Final cost and changes
29
Questions ? Handing Over the Keys to a Successful Construction Project