Download presentation
Presentation is loading. Please wait.
Published byCuthbert Winfred Carroll Modified over 9 years ago
1
Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting
2
Background Freeport 1
3
Background By 2017, Freeport area is projected to be served by two 345/138 kV autotransformers and three long 138 kV circuits 2
4
Background (cont.) 3
5
Freeport LNG has publicly announced o Liquefaction and Export Project in the Freeport area: 3 liquefaction trains 721 MW load Still need FERC authorization - Expected in 3 rd Qtr of 2014 Sign service extension agreement with CNP in 3 rd Qtr of 2014 Operational 3 rd Qtr 2017 o Pretreatment Facility (PTF) north of Freeport: Build in conjunction with Liquefaction and Export Project 109 MW load, 82 MW generator CNP CCN approved on January 27, 2014 CNP Oyster Creek Substation – BP2017 4
6
Study Case Analysis Modify SSWG 2017 base case posted in October 2013 -Increase load at 138 kV QNTANA Substation by 721 MW -Increase generation ERCOT-wide to balance the new load -Add Oyster Creek Substation with 109 MW load, 82 MW generator, and 40 MVAR capacitor bank Study Approach 5
7
Study Approach (cont.) 6
8
Phase I: Study Case Results CNP performed contingency analysis based on Section 4.1.1.2 of the ERCOT Planning Guides: NERC Category B (single contingency) NERC Category C (common mode contingencies) Contingencies relating to ERCOT Autotransformer unavailability criteria Several overloads and low voltages on 138kV system in Freeport area Some overloads higher than 150% on 138 kV lines serving as a source to QNTANA. Case does not solve under contingency loss of both Dow-Velasco autotransformers, indicating potential voltage collapse Results show that significant reinforcement is needed Study Approach (cont.) 7
9
Connection Options Option 1: Build Additional 138 kV Circuits – Rejected Option Two new 21 mile circuits, new 5 mile double-circuit, new 138kV sub, other… Estimated cost greater than $125 million Requires acquisition of 47 miles of new right-of -way Project completion unlikely by Customer’s planned load addition in Q3 2017 Option 2: Build new 345/138 kV Substation “Jones Creek Project” - Preferred New 345/138kV Sub, 2 autotransformers, circuit extensions < 1 mile, other… Estimated cost for Jones Creek Project is $79.8 million CNP has existing substation site and right-of-way for new facilities CNP can complete project by Customer’s planned load addition in Q3 2017 Provides cost-effective 345 kV injection point, minimizes new transmission line construction, minimizes landowner impact, and reduces project lead time. 8
10
Jones Creek Project 9
11
$79.8 million Jones Creek Project recommended to serve the 721 MW Freeport LNG load Jones Creek Project energization planned for BP2017 Complete in time for Freeport LNG 1 st Train Project only moves forward if Freeport LNG: Signs service extension agreement with CNP Gives Notice to Proceed Securitizes project All expected to occur in 3 rd Quarter of 2014 Summary 10
12
Questions?
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.