Presentation is loading. Please wait.

Presentation is loading. Please wait.

Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting.

Similar presentations


Presentation on theme: "Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting."— Presentation transcript:

1 Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting

2 Background Freeport 1

3 Background  By 2017, Freeport area is projected to be served by two 345/138 kV autotransformers and three long 138 kV circuits 2

4 Background (cont.) 3

5  Freeport LNG has publicly announced o Liquefaction and Export Project in the Freeport area: 3 liquefaction trains 721 MW load Still need FERC authorization - Expected in 3 rd Qtr of 2014 Sign service extension agreement with CNP in 3 rd Qtr of 2014 Operational 3 rd Qtr 2017 o Pretreatment Facility (PTF) north of Freeport: Build in conjunction with Liquefaction and Export Project 109 MW load, 82 MW generator CNP CCN approved on January 27, 2014 CNP Oyster Creek Substation – BP2017 4

6 Study Case Analysis  Modify SSWG 2017 base case posted in October 2013 -Increase load at 138 kV QNTANA Substation by 721 MW -Increase generation ERCOT-wide to balance the new load -Add Oyster Creek Substation with 109 MW load, 82 MW generator, and 40 MVAR capacitor bank Study Approach 5

7 Study Approach (cont.) 6

8 Phase I: Study Case Results  CNP performed contingency analysis based on Section 4.1.1.2 of the ERCOT Planning Guides:  NERC Category B (single contingency)  NERC Category C (common mode contingencies)  Contingencies relating to ERCOT Autotransformer unavailability criteria  Several overloads and low voltages on 138kV system in Freeport area  Some overloads higher than 150% on 138 kV lines serving as a source to QNTANA.  Case does not solve under contingency loss of both Dow-Velasco autotransformers, indicating potential voltage collapse  Results show that significant reinforcement is needed Study Approach (cont.) 7

9 Connection Options Option 1: Build Additional 138 kV Circuits – Rejected Option  Two new 21 mile circuits, new 5 mile double-circuit, new 138kV sub, other…  Estimated cost greater than $125 million  Requires acquisition of 47 miles of new right-of -way  Project completion unlikely by Customer’s planned load addition in Q3 2017 Option 2: Build new 345/138 kV Substation “Jones Creek Project” - Preferred  New 345/138kV Sub, 2 autotransformers, circuit extensions < 1 mile, other…  Estimated cost for Jones Creek Project is $79.8 million  CNP has existing substation site and right-of-way for new facilities  CNP can complete project by Customer’s planned load addition in Q3 2017  Provides cost-effective 345 kV injection point, minimizes new transmission line construction, minimizes landowner impact, and reduces project lead time. 8

10 Jones Creek Project 9

11  $79.8 million Jones Creek Project recommended to serve the 721 MW Freeport LNG load  Jones Creek Project energization planned for BP2017  Complete in time for Freeport LNG 1 st Train  Project only moves forward if Freeport LNG:  Signs service extension agreement with CNP  Gives Notice to Proceed  Securitizes project  All expected to occur in 3 rd Quarter of 2014 Summary 10

12 Questions?


Download ppt "Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting."

Similar presentations


Ads by Google