15 January 2008 S.Infante TS-EL CONTROLS ACTIVITES.

Similar presentations


Presentation on theme: "15 January 2008 S.Infante TS-EL CONTROLS ACTIVITES."— Presentation transcript:

1 15 January 2008 S.Infante TS-EL CONTROLS ACTIVITES

2 15 January 2008S.Infante OVERVIEW  Section mandate  SCADA overview  SCADA management  PLC park overview  PLC management  Summary

3 15 January 2008S.Infante SECTION MANDATE  Responsible for the monitoring and control of the CERN electrical network:  Integration of new equipment/substations, modifications, upgrade and maintenance of the Electrical Network Supervisor (ENS) System.  4 staff members. 3 from March 2008! A job post is currently open in ERT. 1 fellow from February 2008.

4 15 January 2008S.Infante ENS OVERVIEW  SCADA system dedicated to the supervision of the electrical network.  Still a mixture of new supervision systems and old supervision systems:  2 Unix Servers: SCATE X – EFACEC  >= 50 distributed concentrators: RTU/CFE  Data acquisition units: DAU/MICENE  Intelligent Electronic Devices: IED  Programmable Logic Controllers: PLC  Discreet I/O

5 RTU LHC, SPS, Meyrin DAU UPS Medium/High Voltage Protection Relays Battery Chargers Discreet I/O switchboards PLC DIRIS CFE MICENE ABB SCADA SVC2 SCATE X servers ENS current architecture TI Operators LASER TIM Remote Desktop Connection LonWorks JBus Silcon IEC Mil1553 GATED NCC Network Control Centre Web Energy ORACLE Server Energy Management TCS Insum

6 15 January 2008S.Infante ENS - NEW EQUIPMENT INTEGRATION  Small scale integration/modifications  TS-EL-CO  ASSYSTEM ( C194 contract TS-CSE) support  Large scale integration  EFACEC (B1115 contract)/TS-EL-CO

7 15 January 2008S.Infante ENS - MAINTENANCE & TROUBLESHOOTING  SCATE X servers  TS-EL-CO for first line intervention. No official piquet but 24 hour support is assured.  ongoing maintenance contract with EFACEC (24h- 7d helpline)  RTU  TS-EL-CO  ASSYSTEM (Preventive maintenance)

8 15 January 2008S.Infante ENS - MAINTENANCE & TROUBLESHOOTING cont’d  CONTROLS EQUIPMENT - Micene, DAU, IED  TS-EL-CO  Remedy ticket service in place  CFE (ongoing replacements by RTUs)  TS-EL-CO: Applications  AB-CO: HW/OS/Appl.Servers (elsrv1)/Mil1553 bus

9 15 January 2008S.Infante PLC  Electrical Process dedicated  Majority of PLCs are Schneider (Premium/Twido)  Some Siemens PLC (S7-400H)

10 15 January 2008S.Infante PLC List  Ventilation substations  Diesel Generators  48V Commutation  EDF-EOS AutoTransfert  18kV normal/secours commutation  18kV Interlocks  LV Distribution LHC experiment (11 Premium type concentrators / around 200 local Twido based I/O stations)

11 15 January 2008S.Infante PLC MANAGEMENT  Majority Programming outsourced (EuroSystem – Contract E088)  URS definition: TS-EL  HW configuration/Local MMI definition: TS-EL-CO  HW failure/card replacement: TS-EL-CO  Software modifications: EuroSystem  Spare part management: TS-EL-CO. Possibility for a CERN wide spare part management contract with Schneider. Currently managed by AB-CO (P.Gayet)

12 15 January 2008S.Infante SUMMARY  The ENS system is now up and running  The migration from the old (CFE/MICENE) to the new ENS system (SCATEX/RTU) is ongoing (80% complete)  The ENS management requires both electrical and controls specialist knowledge and close collaboration with other sections within TS/EL  Despite limited resources a 24h, 7d “piquet-type” service is achieved  Significant documentation updates are required.