1 Facility Construction Committee February 11, 2002 8:30 PM Facility Construction Department Construction Status Report Presentation to the by the
2
2 Projects Under Construction (as of February 2002) Campus Start Date Campus Start Date 1. Sta. Maria Elementary School Oct. 2001 2. Farias Elementary School Oct. 2001 3. Sanchez/Ochoa Elem. School Oct. 2001 4. Dovalina Elementary School Oct. 2001 5. Milton Elementary School Jan. 2002 6. Nixon High School Jan. 2002
3
3 Santa Maria Elementary School Architect:Cavazos & Associates Architects Architect:Cavazos & Associates Architects Contractor:Leyendecker Construction, Inc. Contractor:Leyendecker Construction, Inc. Contract amount:$4,862,700.00 Contract amount:$4,862,700.00 Construction Start:Oct. 31, 2001 Construction Start:Oct. 31, 2001 Start of School:Aug. 15, 2002 Start of School:Aug. 15, 2002 Completion Date:Aug. 31, 2002 Completion Date:Aug. 31, 2002 Change Order(s):Addition of Single Sex Restrooms at PK & K. Change Order(s):Addition of Single Sex Restrooms at PK & K.
4
4 Financial Overview – Sta. Maria Leyendecker’s Contract
5
5 Construction Time - Sta. Maria Leyendecker’s Contract
6
6 LISD: Sta. Maria: Foundation construction on going. Approximately 45,000 sq. Ft. Will be poured by 1-18-02. Additional 20,000 sf to be poured by 1-22-02. All excavations is complete, all reinforcing is on jobsite. Masonry construction projected to commence 1-23-02. Metal building delivery scheduled to commence 3-01-02. LISD: Sta. Maria: Foundation construction on going. Approximately 45,000 sq. Ft. Will be poured by 1-18-02. Additional 20,000 sf to be poured by 1-22-02. All excavations is complete, all reinforcing is on jobsite. Masonry construction projected to commence 1-23-02. Metal building delivery scheduled to commence 3-01-02. Santa Maria Elementary School
7
7
8
8 Farias Elementary School Architect:Ashley Humphries, & Sanchez Architects Architect:Ashley Humphries, & Sanchez Architects Contractor:Leyendecker Construction, Inc. Contractor:Leyendecker Construction, Inc. Contract amount:$4,926,997. Contract amount:$4,926,997. Construction Start:Oct. 31, 2001 Construction Start:Oct. 31, 2001 Days in Contract:320 Calendar Days Days in Contract:320 Calendar Days Completion Date:Aug. 31, 2002 Completion Date:Aug. 31, 2002 Change Order(s):Addition of Single Sex Restrooms at PK & K. Change Order(s):Addition of Single Sex Restrooms at PK & K.
9
9 Financial Overview – Farias Leyendecker’s Contract
10
10 Construction Time - Farias Leyendecker’s Contract
11
11 Farias Elementary School
12
12 Farias Elementary School
13
13 Sanchez/Ochoa Elementary School Architect:Sepulveda & Assoc. Architects Architect:Sepulveda & Assoc. Architects Contractor:Leyendecker Construction, Inc. Contractor:Leyendecker Construction, Inc. Contract amount:$ 5,132,719. Contract amount:$ 5,132,719. Construction Start:Oct. 31, 2001 Construction Start:Oct. 31, 2001 Number Contract Days:320 Number Contract Days:320 Completion Date:Sept. 16, 2002 Completion Date:Sept. 16, 2002 Change Order(s):None Change Order(s):None
14
14 Financial Overview – Sanchez/Ochoa Leyendecker’s Contract
15
15 Construction Time – Sanchez/Ochoa Leyendecker’s Contract
16
16 LISD: All foundation excavation is complete. All reinforcing steel is on jobsite, all beam reinforcing steel is tied and ready for installation. All of zones “D” and “E” have been poured, 14800 sf of zone “B” poured. Zone “C” to be poured week 1-21-02 along with zone “A” and pending portion of zone “B”.Metal building delivery scheduled to commence 2-15-02. LISD: All foundation excavation is complete. All reinforcing steel is on jobsite, all beam reinforcing steel is tied and ready for installation. All of zones “D” and “E” have been poured, 14800 sf of zone “B” poured. Zone “C” to be poured week 1-21-02 along with zone “A” and pending portion of zone “B”.Metal building delivery scheduled to commence 2-15-02. Sanchez/Ochoa Elementary School
17
17 Sanchez/Ochoa Elementary School
18
18 Sanchez/Ochoa Elementary School
19
19 Sanchez/Ochoa Elementary School
20
20 Sanchez/Ochoa Elementary School
21
21 Dovalina Elementary School Architect:Design Group International, Inc. Architect:Design Group International, Inc. Contractor:Leyendecker Construction, Inc. Contractor:Leyendecker Construction, Inc. Contract amount:$ 2,801,900. Contract amount:$ 2,801,900. Construction Start:Oct. 31, 2001 Construction Start:Oct. 31, 2001 Number Contract Days:304 Number Contract Days:304 Completion Date:Aug. 31, 2002 Completion Date:Aug. 31, 2002 Change Order(s):None Change Order(s):None
22
22 Financial Overview – Dovalina Leyendecker’s Contract
23
23 Construction Time - Dovalina Leyendecker’s Contract
24
24 LISD: Foundation has been poured for addition. CMU in progress and is approximately 50% complete. Metal building schedule for delivery on 1-18-02, with metal panels and insulation delivery scheduled for 1-25-02. LISD: Foundation has been poured for addition. CMU in progress and is approximately 50% complete. Metal building schedule for delivery on 1-18-02, with metal panels and insulation delivery scheduled for 1-25-02. Dovalina Elementary School
25
25 Dovalina Elementary School
26
26 Dovalina Elementary School
27
27 Milton Elementary School Architect:Turner Hickey & Assoc. Arch. Architect:Turner Hickey & Assoc. Arch. General Contractor:To be determined General Contractor:To be determined Asbestos/Demolition:M & M Contracting, Inc. Asbestos/Demolition:M & M Contracting, Inc. Contract amount:$ 183,978. Contract amount:$ 183,978. Construction Start:Jan. 27, 2002 Construction Start:Jan. 27, 2002 Number Contract Days:47 Days Number Contract Days:47 Days Completion Date:March 15, 2002 Completion Date:March 15, 2002 Change Order(s):None Change Order(s):None
28
28 Financial Overview – Milton M & M Contracting Contract Asbestos/Demolition
29
29 Construction Time – Milton M & M Contracting Contract Asbestos/Demolition
30
30 Milton Elementary School
31
31 Milton Elementary School
32
32 Milton Elementary School
33
33 J. W. Nixon High School Architect:Cavazos & Associates Architects Architect:Cavazos & Associates Architects Contractor:Leyendecker Construction, Inc. Contractor:Leyendecker Construction, Inc. Contract amount:$ 9,298,985. Contract amount:$ 9,298,985. Construction Start:Jan. 30, 2002 Construction Start:Jan. 30, 2002 Number Contract Days:551 Number Contract Days:551 Completion Date:August. 15, 2003 Completion Date:August. 15, 2003 Change Order(s):None Change Order(s):None
34
34 Financial Overview – Nixon High Leyendecker’s Contract
35
35 Construction Time – Nixon High Leyendecker’s Contract
36
36 J. W. Nixon High School
37
37 J. W. Nixon High School
38
38 End of Presentation Question & Answer Session