1
Dafili Gravity Water Supply Scheme Finn WASH-BG Programme
2
Outline Enabling Environment Location and Facts About the Project Initiation & Application Process Socio-economic and Tariff Study Engineering Design & Approval Funding Agreement, Transfer & Implementation Actual Project Cost Inauguration Ceremony Other Uses Challenges Way forward
3
Enabling Environment Proclamation 71/2008 has been issued For point sources, WASHCOs have to be formed to construct and manage them. For more complex schemes, WUAs have to be formed to manage schemes Regulations necessary to implement the Proclamation Drafted by the WMERDB Demand from Communities Sufficient source
4
Location and Facts about the Scheme Location Jigda Silassie Kebele of Mandura Woreda 25 kms north west GB Facts Water Source: Dafili Springs Total yield: 2.5l/s Water quality : Potable (as tested by WWO staff) Coverage: 324 HHs in five Gotts (villages) of Dafili sub-Kebele Present users: Humans= 1782 : Cattle heads= 1398
5
Initiation & Application Process Initiated by the communities 5 villages formed a WASHCO each 5 WASHCOs formed a WUA Each village contributed ETB 1000.00 WUA Saving account in BGCSI Deposited ETB5000.00 Applied for CDF support Desk and field appraisals were conducted WSC approved the project
6
Socio-economic and Tariff Study Will be presented by Mike
7
Engineering Design & Approval Prepared by TA Team and WWO Staff Scheme components A spring capping structure (1.5 l/s) A 50 m3 capacity sandwich reservoir 5 public fountains 5 wash stands 3 cattle troughs 3 shower units (2 of them having 4 rooms and 1 having 2 rooms) 1.627 kms pipe line (GS & HDPE) Estimated cost ETB665, 393.84 Assessed by PMC and approved by Board
8
Funding Agreement, Transfer & Implementation Funding agreement signed WUA opened a CDF account Fund transfer WSC CDF account to WUA CDF account CDF guideline Procurement Goods and services were procured by the WUA Construction & supervision April, 2011 Locally trained Artisans WWO staffs September, 2011
9
Actual Project Cost Total project cost = ETB 810,000 Communities contributed = ETB 90,000 (11.11%) Supplied local materials (stone, sand, wooden poles, etc) Provided unskilled labor o Trench excavation o Other necessary works GoF contributed = ETB 720,000
10
Inauguration Ceremony Inaugurated February 13, 2012
11
Other Uses Backyard gardening Vegetables, such as onions, potatoes, cabbage, carrots, etc Ensures the sustainability of the scheme
12
Challenges Regulations not yet in place WUA didn’t obtain legal status Non existence of the private sector in repair and maintenance Rely on the Woreda Water Office
13
Way Forward Put in place Regulations ASAP Train local Artisans in repair and maintenance Develop payment guideline
14