Harding Elementary School Exterior Repairs & Select Roofing Replacement 11/18/2014
3
General ContractorBest Contracting Services, Inc. Architect of RecordGrossman Design Group Construction ManagerWillie Robinson
4
Contract Amount $918,600 Notice of Award06/17/14 Notice to Proceed07/21/14 Completion 01/05/15
5
Fabricating & installing Surround Window flashings is 95% complete. Re-setting of Windows at Building A is 90% compete. Stucco (scratch & brown coats) at Building A-1 upper parapet walls & west wall of Theatre is complete. Installation of waterproof membrane and lathing at Building A-1 is 75% complete. Clean-up, repair and environmental testing of water intrusion areas.
6
Building A-1: South wall at storefront.
7
Building A-1: Theatre West Wall – Stucco brown coasting.
8
Building A: 1 st floor windows re-installed.
9
Building A-1: Stucco brown coat at upper parapet wall.
10
Library Past Water Intrusion Damage _2 10/28/14.
11
Computer Lab Hygienist Clean –Up 10/04/14
12
Library Water Intrusion Repairs_3 11/06/14
13
Building A-1: Theatre West Wall, stucco brown coat.