1
Aganda for today: Baselines. PS7. Short review of Project Evaluation Baselines
2
Project Evaluation. Transparancy. –What is transparancy –Transparancy is obtained through different activities Project establishment (Project Charter) Project planning (Project plan) Models and diagrams (Program design)
3
Project Evaluation. Transparancy. –Systematic project evaluation When ? How ? Techniques –Routine check –Review –Self registration –Inspection –Interview –Test
4
Project Evaluation. Transparancy. –Systematic project evaluation Problem analysing
5
Project Evaluation. Review. –Systematic project evaluation. Review. RequirementsThe Product Preparation Review ReportList of issues
6
Project Evaluation. Review. -Is the product good enough ? - The product is approved without any comments - The product is approved after a few minor corrections. No other review. - The product is not approved; major corrections are necessary, and a new review - The product is useless; management must decide what should be done. - The review could not be carried through. -FIG. 6.5
7
Project Evaluation. Technical walkthroughs. -A special kind of review. - Fig. 6.6
8
Project Evaluation. Problematic situations. -Mapping. - Diagnostic maps (Table. 6.2) - Ecological maps (Fig. 6.8) - Virtual maps
9
Baselines. PS7. -Why baselines A1. Vision and Business Case A2. Use-Case Model A3. Supplementary Specification
10
Baselines. PS7. -Why baselines A1. Vision and Business Case A2. Use-Case Model A3. Supplementary Specification
11
Baselines. PS7. Baseline -A baseline is a project state which is thoroughly described in a plan. -A project have reached a baseline when intermediate products are in well-defined states and other important prerequisites are known -A baseline is a coordinated project state which everyone in the project can refer to.
12
Baselines. PS7. Baseline description: -Name of baseline -List of 1. Intermediate products in specific states 2. Other important prerequisites -Criteria for evaluation 1. Characteristics of intermediate products, resources, user organisation, etc.
13
Baselines. PS7. Baseline description: -Procedures for evaluation 1. How should the project/activity be evaluated (review, test etc.)? 2. Who should evaluate? 3. Who are the decision-makers
14
Baselines. PS7. Exercise: Baseline –Describe a baseline for the Project Establishment phase.
15
Project documents. PS7. Configuration management Why? To maintain traceability Alleways work with the latest version
16
Project documents. PS7. Configuration management