1437 SOUTH BOULDER AVE., SUITE 1080 TULSA, OKLAHOMA 74119 918.392.5620 (P) 918.392.5621 (F) WWW.MESHEKENGR.COM Garnett Regional Detention Facility: A Success Story In Managing NAI With Competing Interests Brandon Claborn, P.E., CFM
2
CITY OF OWASSO, OK Location – 11 Miles Northeast of Tulsa, OK Population –1990 – 11,151 –2000 – 18,502 –2008 – 37,328 Recent Development –2400 Residential Lots 2002-2009 –Annual Retail Sales: –$200 Million in 2000 –$550 Million in 2007
3
RANCH CREEK BASIN
4
DRAINAGE BASIN Ranch Creek – Tributary A 344 Acres to Proposed Pond
5
1994 1994
6
2002 2002
7
2004 2004
8
2006 2006
9
2008 2008
10
EXISTING PROBLEMS Flooding Downstream of Site
11
GOALS FOR DETENTION Reduce Flooding Downstream Full Development Upstream Remove Some Existing Ponds Sell City Owned Property Protect Wildlife Habitat Enhance Quality of Life
12
COMPTETING INTERESTS Development versus Mitigation USACOE versus OKDEQ & EPA Construction Costs: Developer/City Park versus Flood Control Maintenance versus Wetland/Habitat
13
DEVELOPMENT PRESSURE 118 Acres of Undeveloped Property
14
FLOODPLAIN MITIGATION Additional Competing Interests More Frequent versus Less Frequent Floods
15
PERMITTING ISSUES CLOMR 404 Permit –On Site Meeting Prior to Design –Second On Site Meeting – Initial Design Individual 404 Permit Application –100% On Site Mitigation –4:1 Ratio for Overall Wetland Habitat 401 Certification (OKDEQ) –Required Additional Off Site Mitigation Cultural Resources Investigation Oklahoma Historical Society
16
CONSTRUCTION COSTS Sell Existing Detention Facilities Fee In Lieu of Detention Additional City Planning Required Negotiate Purchase of Property
17
GENERAL SITE ISSUES Neighborhood Meeting Public Meeting During Design Phase –Local Residents Expectations Coordination With City Departments –Upgrade Sanitary Sewer –Maintenance Access –Security (Police) –Stormwater Quality
18
SUMMARY/RECOMMENDATIONS Floodplain Management – Developing With No Adverse Impact –One Piece of the Puzzle –Reducing Flooding Is the Easy Part –Several Competing Interests –Coordinate City Departments –Comprehensive Planning Is Crucial –Leverage Resources –Work With Developers –Identify Permitting Needs Early
19