Download presentation
Presentation is loading. Please wait.
Published byNeil Mosley Modified over 9 years ago
1
D0 Collab Mtg Feb 7, 2001 D0 Detector: Status for Run 2 Wistful reminiscences Near term: Roll in, detector status, next few weeks Latest from Beams Division Post-roll-in plan: Electronics status Access requirements, logistics Open/closed running Run, shift organization Closing comments Jon Kotcher D0 Collaboration Meeting February 7, 2001
2
D0 Collab Mtg Feb 7, 2001 What Did We Roll In? Installed: u Central Muon: A- counters s Cosmic cap scintillation (trigger) counters s All PDTs refurbished, installed –Front ends available, being installed u Forward Muon: s Trusses & platform installed s All MDTs and pixels installed, aligned, surveyed s Forward shielding in place, exercised –Front ends being installed, prepped u Calorimeters: s Filled CC, ECN –In-situ thermometry, purity systems commissioned –<0.5 ppm, test dewar s 1-1.5 calorimeters instrumented for Mar 1 u End detectors (mounted on faces of end calorimeters): s Forward Preshower (FPS) –See CFT readout s Inter-Cryostat Detector (ICD) –Front ends being delivered s Luminosity Monitor (LUM) –Run 1 electronics until later in year
3
D0 Collab Mtg Feb 7, 2001 What Did We Roll In? Installed (cont’d): u Bore of Central Calorimeter (CC) s Solenoid –Cooled down, powered, commissioned in DAB s Central Preshower (CPS) –See CFT readout s Central Fiber Tracker (CFT) –All CFT & CPS waveguides installed –60/100 production VLPC cassettes installed –Analog front end not yet out to vendor s Both halves of barrel silicon, all 4 H-disks –Front end in hand, being installed Interface region, high mass cables, adapter cards, etc. u Plus much infrastructure… s VLPC cryostats, VESDA, transformers, SMT water/power/interlocks, rack preparation, truss electrical, MDT/PDT gas, bus work, helium lines… u Detectors in varying stages of commissioning Detector rolled in mechanically complete, huge amount of work… u Done on very contracted time scale, without killing anybody
4
D0 Collab Mtg Feb 7, 2001 Roll in and Beyond Rolled in Thu/Fri, Jan 25/26 Week of Jan 29: u Position detector E-W (20 mils) u Exercise muon shielding, adjust truss elevation u Open end irons, CF iron u Install/cable BLMs u Open calorimeters, erect scaffolding u Install access/egress infrastructure u Resume SMT installation Week of Feb 5: u Complete cabling over bridge u Begin shield wall assembly (air handlers, cable bridge, He U-tubes, etc.) u Test inner H-disks u Install outer H-disks u Connect cooling lines to silicon, extended testing prior to run u Begin cabling through EC winders Week of Feb 12: u Install adjustable EC beam pipe supports u Survey & adjust tracker/EC positions u Continue SMT installation Week of Feb 19 & 26: u Begin making up beam pipe couplings: position of large objects dictated by this activity u Close detector, final positioning of platform, align to TeV beam line Mar 1: ready for beam
5
D0 Collab Mtg Feb 7, 2001 News From Beams Division Helium lines in magnet string contaminated with water last week u ~ 5 dipoles, 2 quads u Replace, “not on critical path” BDiv putting forth two scenarios: u Scenario I: s Close up Feb 27 or 28 s Mar 24: 1X8 stores for few days –Detector timing s Apr 09: 36X36 for one week s Apr 16: begin considering detector-driven accesses u Scenario II: s ~ same as I, but delayed by ~ 10 days In either case, beginning of run dedicated to accelerator commissioning u Accesses driven solely by their needs Complicates, competes with completion of our electronics installation
6
D0 Collab Mtg Feb 7, 2001 Readout Status on March 1 Forward Muon: u Readout installed, ramping up Central Muon: u Expect full front end available for both scintillation counters and PDTs u Gas in place for Central & Forward (no circulation) 25%(?) of SMT hooked up, partially commissioned u Depends crucially on when run starts s If Mar 15, ~ 50% very feasible u All quadrants being prepped, installed CFT/preshower readout: u Axial AFEs (AFE-8) arrive mid Apr s Required for both trigger & SVX (digitized) CFT/PS readout s Perhaps 5-10 prototype boards installed for Apr 1 (few % total) u Installation of AFE-8 production boards starts early May? u AFE-12 (preshower) late summer earliest 1-1.5 calorimeters instrumented u System coming together
7
D0 Collab Mtg Feb 7, 2001 Readout Status on March 1 Trigger (talk by Blazey): u Level 1: s L1 CAL: 2 trigger towers, more coming s L1 muon: 2 central octants, simplified triggers –Comb. production & pre-production cards s No L1 CFT –Possibly a few prototype boards mid Apr, hit- based trigger u No Level 2 s Progress being made, but not for Mar 1 s Difficult to predict availability u Level 3: s 8 Hz to start s 50 Hz mid Mar (end Mar) s 200 Hz end May (mid Jun) s 1 kHz end June (mid Jul) u Rely primarily on min bias trigger s LUM detector, electronics installed
8
D0 Collab Mtg Feb 7, 2001 D0 Access Needs After Mar 1 Two primary considerations: u Silicon installation, commissioning s Parts in hand, driven by us s Could use 2 months to advantage now if we had it u CFT/PS front ends s AFE-8 (CFT axial): final boards not yet ordered –Specs very rigorous (7 fC), electrical/cryo testing continues –Pushing to get this order out the door Feb 19 –Arrive mid Apr, start install early May –Other components (DFE, mixer) Mar arrival s AFE-12 (PS): earliest end summer u Remaining calorimeter electronics less of an issue; muon looks good Access considerations for CFT/SMT very different u SMT: inter-cryostat gaps, CF cathedral u CFT: platform only u Trigger not an access issue (Counting House) Time estimates for completion: u SMT: about 6-8 weeks u CFT: similar (?) u CFT/SMT installation don’t necessarily overlap in time
9
D0 Collab Mtg Feb 7, 2001 Current Post Roll-in Plan Open vs. closed running: u Open: CF, muon shielding retracted, EFs open, end cals open, scaffolding in place s Offers immediate SMT access, but has limitations: –A-layer muon (rates), triggering, running solenoid requires CF closed, commission toroids, geometry of data set, etc. u Periodic closed-detector data sets beneficial How much time will we really need to ask for? u Not clear accelerator will start on Mar 1 u Will there be 1 or 2 two-week periods without our having to ask for them? u Other, shorter accesses? s Productivity of brief accesses? - integrated time not only consideration u Closed-detector running: cost to close, reopen,… D0 will begin run in closed configuration u Use every bit of remaining pre-beam time with detector open to allow SMT hookup s Close up as late as possible u Logic of making up beam pipe couplings Start closed, watch accelerator progress u Open if/when it makes sense u Efficiently exploit short accelerator down times Remain flexible in order to optimize available time
10
D0 Collab Mtg Feb 7, 2001 Getting Experiment Online, Running Significant focus, effort will be required to get to physics quality data-taking u Will need well-organized shifts, efficient use of access time Shift logistics, structure, evolution set by Kotcher, Yu, Begel u Day-to-day control room, shift operations run by Yu & Begel Lead Experiment Operators (LEOs, or DAQ Experts, or…) u D. Alton, M. Begel, H. Fox, L. Groer, S. Mattingly, A. Nomerotski, T. Nunnemann, S. Snyder, J. Yu u Critical set of people – instrumental in getting us data u Need more: requires significant knowledge, expertise, training u On call 24 hrs to keep exp’t running No formal requirement specifically for data- taking shifts u Part of overall shift-taking requirements s “Physicist shifts” u Hope we generate enough momentum without it u Sign up – it’s needed (Begel)
11
D0 Collab Mtg Feb 7, 2001 Shift Structure Scaled-down 24-hour operation starting next week or two, shifts will gradually evolve into following: u Shift Captain s Implement shift run plan, use of luminosity s Coordinate control room, final decision-making authority s Some training required s Captains approved by Kotcher u DAQ Shifter s Run experiment (DAQ), keep it afloat s Less expertise than LEOs s Some training required u Detector Shifters s Representatives from major sub-systems: Si, CFT, CMU, FMU, etc. s Experts fewer in number, will be on call when not present s Training needed for less experienced u Global Monitor s Monitor data quality – EXAMINEs, event displays, etc. s Can be commuters, little or no training u Operations Shifter s Likely covered by technical FNAL support staff s Captain should be on top of this as well
12
D0 Collab Mtg Feb 7, 2001 Concluding Remarks D0 rolled into Collision Hall mechanically complete u Hard work, dedication of talented support staff, physicists made it happen Trigger & CFT/SMT readout systems are late, in various stages of evolution u Latter two make accesses an important concern, working on this 24 hour shifts beginning soon u Tending the experiment, making it work are critically important tasks u Need more dedicated personnel here The next year be challenging, difficult at times u One year ago, hardware people would have laughed (and did!) at suggestion we’d roll in mechanically complete device in Jan ’01!
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.