The Path to Running CLAS12 BONuS12 Latifa Elouadrhiri August 21, 2015
2
2 Outline CLAS12 Construction Status Project Schedule and Tentative Run plan The path to running BONuS12
3
3 12 GeV Upgrade Project New Hall Add arc Enhanced capabilities in existing Halls Add 5 cryomodules 20 cryomodules Upgrade arc magnets and supplies CHL upgrade Completion of the 12 GeV CEBAF Upgrade was ranked the highest priority in the 2007 NSAC Long Range Plan. Upgrade is designed to build on existing facility: vast majority of accelerator and experimental equipment have continued use. Maintain capability to deliver lower pass beam energies: 2.2, 4.4, 6.6…. Project Scope (~95% complete) : Doubling the accelerator beam energy - DONE New experimental Hall D and beam line – DONE Upgrades to Experimental Halls B & C (89% & 86%) TPC = $338M
4
4 CLAS 12 Base equipment Forward Detector (FD) - TORUS magnet (6 coils) - HT Cherenkov Counter - Drift chamber system - LT Cherenkov Counter - Forward ToF System - Pre-shower calorimeter - E.M. calorimeter Central Detector (CD) - SOLENOID magnet - Barrel Silicon Tracker - Central Time-of-Flight Beamline - Targets - Moller polarimeter - Photon Tagger Upgrade to base equipment - MicroMegas - Central Neutron Detector - Forward Tagger - RICH detector (1 sector) - Polarized target (long.) - BONus12 MM CND http://www.jlab.org/Hall-B/clas12-web/ 4
5
5 CLAS 12 - Central Detector Integration of BoNus in CLAS12/CD requires early coordination with technical team.
6
6 Status of Hall B Forward Carriage FTOF1a, FTOF1b, PCAL and EC essentially operational 2+ years prior to scheduled beam commissioning. Beam Line Instrumentation Commissioned during HPS run up to Faraday cup, BPMs, harps, halo counters. Additional beam line components to be installed beginning 10/2015 TORUS Magnet Installation 6 coils and 6 pairs of hex beams installed in Hall Spare coil cryostated and factory disassembled Full Torus commissioned and field mapped 7/2016. SOLENOID Magnet 2 nd of 5 coils in fabricated Delivery of Magnet to JLab ~5/2016 Expected to be operational ~8/2016
7
CLAS Collaboration Meeting 6/17/2015 Page 7 Hall B: Detector Progress FTOF 1-a, 1-b Installed (USC) Drift Chambers (ODU, ISU, JLab) Assembled CTOF Counters Being Tested PCAL Installed (JLab, OU, W&M, NSU) SVT (Jlab and FNAL) Complete LTCC-1 with First Set of Mirrors SVT-Mechanical integration completed!
8
CLAS Collaboration Meeting 6/17/2015 Page 8 SVT- Integration and Alignment Complete
9
9 Key Dates HallKey EventProjected Date BTorus 1 st Coil Cold Mass ArrivedNovember 2014 BTorus 6 th Coil in Cryostat DoneJune 2015 BTorus InstallationOctober 2014 (‘spit’) – May 2016 BSolenoid Coil WindingMarch 2015 – November 2015 BSolenoid ArrivesMay 2016 BDetector Commission with BeamDecember 2016
10
10 Hall B Schedule Torus Assembly, Install + Test Solenoid Install + Test 8 months to CD-4B (as of 2-June) Software ready Calibration ready Documentation ready Commissioning ready First experiment ready Today
11
11 ProposalPhysicsContactRatingDaysGrou p New equipmentEnergyRun GroupTarget E12-06-108Hard exclusive electro-production of π 0, ηStolerB80 139 RICH (1 sector) Forward tagger 11 A F. Sabatié liquid H 2 E12-06-112Proton’s quark dynamics in SIDIS pion productionAvakianA60 E12-06-119Deeply Virtual Compton ScatteringSabatieA80 E12-09-003Excitation of nucleon resonances at high Q 2 GotheB+40 E12-11-005Hadron spectroscopy with forward tagger BattaglieriA-119 E12-12-001Timelike Compton Scatt. & J/ψ production in e+e- Nadel-TuronskiA-120 E12-12-007Exclusive φ meson electroproduction with CLAS12Stoler, WeissB+60 E12-11-005aPhotoproduction of the very strangest baryonGuoNR(120) E12-07-104Neutron magnetic form factorGilfoyleA-30 90 Neutron detector RICH (1 sector) Forward tagger 11B K. Hafidi liquid D 2 target PR12-11-109 (a)Dihadron DIS productionAvakian E12-09-007aStudy of partonic distributions in SIDIS kaon productionHafidiA-30 E12-09-008Boer-Mulders asymmetry in K SIDIS w/ H and D targetsContalbrigoA-56 E12-11-003DVCS on neutron targetNiccolaiA90 E12-06-109Longitudinal Spin Structure of the NucleonKuhnA80 185 Polarized target RICH (1 sector) Forward tagger 11C S. Kuhn NH 3 ND 3 E12-06- 119(b)DVCS on longitudinally polarized proton targetSabatieA120 E12-07-107Spin-Orbit Correl. with Longitudinally polarized targetAvakianA-103 PR12-11-109 (b)Dihadron studies on long. polarized targetAvakian E12-09-007(b)Study of partonic distributions using SIDIS K productionHafidiA-80 E12-09-009Spin-Orbit correlations in K production w/ pol. targetsAvakianB+103 E12-06-106Color transparency in exclusive vector meson productionHafidiB+60 11DNuclear E12-06-117Quark propagation and hadron formationBrooksA-60 11ENuclear E12-06-113Free Neutron structure at large xBueltmanA40 42 Radial TPC11FGas D 2 E12-14-001 EMC effect in spin structure functionsBrooksB+55 Pol. LiH target11G LiH TOTAL run time1466 (1586) 631 Hall B CLAS12 experiments – run groups 11
12
12 ProposalPhysicsContactRatingDaysGroupEquipmentEnergyGroupTarget C12-11-111SIDIS on transverse polarized targetContalbrigoA110 Transverse target 11GHD C12-12-009Transversity w/ di-hadron on transvere targetAvakianA110 C12-12-010DVCS with transverse polarized target in CLAS12 ElouadrhririA110 All transverse target proposals330110 C12-11-006Heavy Photon Search at Jefferson Lab (HPS)JarosA180 New setup in alcove 2.2, 6.6 HNuclear E12-11-106High Precision Measurement of the Proton Charge Radius GasparianA15 Primex1.1, 2.2 IH2 gas Beam time request from CLAS12 C! experiments + non-CLAS12 experiments 525305 Beam time from approved CLAS12 experiments (from previous page)1466631 TOTAL Beam time for all Hall B experiments1991936 C1 approved proposals & non-CLAS12 Optimistically, we may run 90 PAC days per year. To run all experiments as run groups with full beam time will require 936/90 ≈ 10 years. 12
13
13 Run Group Schedule – Tentative 6/2015 Run GroupDays2015201620172018201920202021Remai n All Run Groups936CND MM FT BONUS RICH Long. PTTrans. PT525411 HPS180* 3 5?1020135 PRad15* 15--- CLAS12 KPP 15 RG-A (proton)139* 20 4079* RG-F (BoNuS)42* 402 RG-B (deut.)90* 4050* RG-C (NH 3 )120204060 RG-C-b (ND 3 )653530 RG-E (Hadr.)60251025 RG-G (TT)110*55 RG-D (CT)60 3525 RG-K (LiD)55 --- 13
14
14 Project Phases Science – Physics Requirements R&D – Finalizing detector components choices Conceptual Design - CDR Engineering Design – TDR with well defined detector specifications Project construction Detector assembly Commissioning Operation and maintenance Simulation & Reconstruction is an important part of every phase of the project.
15
15 Project Execution Science document with well defined science requirements Technical Design Report (TDR) and detector specification Baseline cost and schedule – Resource loaded schedule with clear dependencies Labor by skill Procurement with BoE Space & Infrastructure Milestones QA/QC Risk and Risk mitigation document Software: simulation, reconstruction & calibration Geometry and commissioning document Organization with well defined roles and responsibilities with Control Change board Project Tracking/Reviews –BoNus collaboration conducted reviews and meeting –Hall B reviews –Physics Division Experimental Readiness Reviews –Funding agencies-report/reviews
16
16 Path Forward for CLAS12 BoNus12 Project Detector Technology choice: October 2015 to be presented at the CLAS12 workshop October 19-20, 2015 Produce Conceptual Design Report with estimated cost and schedule, to be presented to Hall B management by December 2015. Hall B management to conduct first review December 2015/January 2016 Form a run group of experiments: what other science can be done with BoNus12? Write the document - important for the final detector optimization
17
17 Path Forward for CLAS12 BoNus12 Project Detector Technology choice: October 2015 to be presented at the CLAS12 workshop October 19-20, 2015 Produce Conceptual Design Report with estimated cost and schedule, to be presented to Hall B management by December 2015. Hall B management to conduct first review December 2015/January 2016 Form a run group of experiments: what other science can be done with BoNus12? Write the document - important for the final detector optimization BoNus 12 is CLAS12 detector, so having dedicated group from BoNus group involved with CLAS12 software and the preparation and running of the first CLAS12 experiment is critical to the success of BoNus12 Project.
18
18 Looking Forward to an Exciting Project THANK YOU