Presentation is loading. Please wait.

Presentation is loading. Please wait.

POWER GRID CORP. OF INDIA LTD. Dr. Montek Singh Ahluwalia

Similar presentations


Presentation on theme: "POWER GRID CORP. OF INDIA LTD. Dr. Montek Singh Ahluwalia"— Presentation transcript:

1 POWER GRID CORP. OF INDIA LTD. Dr. Montek Singh Ahluwalia
WELCOMES Dr. Montek Singh Ahluwalia Dy. Chairman, Planning Commisson

2 An Analogy – Power System & Human Body
RLDC::Brain Generation :: Heart USER Voltage :: BP Frequency:: Heart beat Sub-Transmission :: Sub-Arteries Transmission :: Main Arteries Distribution :: Capillaries

3 POWERGRID MISSION Establishment and operation of Regional and National Power Grids to facilitate transfer of power within and across the Regions with reliability, security and economy on sound commercial principles

4 POWERGRID -An Overview
A neutral transmission service provider. Started Commercial Operations from Wheels 45,000 MW i.e. more than 40% of the power generated. Operates and Maintains 50,000 circuit kms of EHV transmission System 82 nos of EHVAC & HVDC sub-stations With System Availability over 99.5%.

5 TRANSFORMER CAPACITY (MVA) TURNOVER AND NET PROFIT
Growth of POWERGRID TRANSFORMER CAPACITY (MVA) GROSS FIXED ASSET (RS. CRORES) TURNOVER AND NET PROFIT MANPOWER * REVICED CERC TARIFF NORMS * MANPOWER TRANSFERRED FROM CEA

6 Efforts made by POWERGRID to Stabilize and Commercialize Power Sector
Establishment of National Grid Modernisation of RLDCs Introduction of Availability Based Tariff Mechanism to both Generators and Consumers Manning of RLDCs by Senior Level Personnel Introduction of “Open Access”

7 Need for Strong National Grid
Generation resources in pockets and remote Load Centres dispersed and distant Multiple Loops and Rings desirable to ensure Safety, Security and Reliability Demand fluctuations on daily/ seasonal variation Economy of Operations Reduction in generation reserves Thermal /Nuclear /combined gas as base operation. Costly power plants on marit order. Hydro for peaking. Reservoir/ pump stroage run of the river as base load

8 Formation of National Grid
………a continuous process Present Capacity 9,000 MW Future Capacity –30,000MW by 2012 Investment Required by :Rs. 71,000 Crores By POWERGRID :Rs. 51,000 Crore By Pvt. Investors :Rs.20,000 Crores This investment will also take care evacuation of Central Sector Share of generation planned till 2012. Creation of National Grid of 30,000 MW Capacity will lead to reduction in Capacity addition of 13,000MW i.e. saving of Rs. 50,000 Crore in investments besides fuel cost saving.

9 Derived economics of National Grid
Merit Order Pit head stations PLF increased Costly Generation - Boxed up /reduced Exchange of 18,500 MUs in equivalent to Generating Station of 3000 MW Capacity Estimated National Saving Rs. 12,000 Crores in fresh investments Rs. 1,850 Crores in fuel cost Additional Saving in Fuel Transportation Expected exchanges in : ,000 MUs Hydro plant usage– a paradigm shift Importance of Pumped Storage Plants achieved Harnessing of the diversity in occurrence of the Peak Demand amongst Regions , thus peak load flattened

10 Inter-Regional Exchanges

11 Modernisation of RLDC/SLDCs by POWERGRID
Region Taken Over from CEA ULDC Commissioning Southern Northern North-Eastern Eastern June 2005* Western March 2006* * Scheduled Target Unified Approach - Features - Hierarchical State of Art Load Despatch Centres at Regional and State/Area Level.

12 Grid Operation Hierarchy Plant/Sub Station Level
NLDC National Level ERLDC Region Level WRLDC NRLDC SRLDC NERLDC 5 Nos. State HQ Level 23 Nos. SLDC 51 Nos. SUB LDC Group of Distt. Level RTU 1160 Nos. Plant/Sub Station Level

13 AVAILABILITY BASED TARIFF (ABT)
Spearheaded by POWERGRID Features: Unique commercial mechanism linked with frequency Fixed Charges i.e. Capacity charges As per Plant Availability. Variable Charges i.e. Energy charges As per Schedule. Unscheduled Interchange(UI) i.e. deviations from schedule ( Schedule – Actual) Price as per prevailing system frequency Typical Schedule & Drawal

14 AVAILABILITY BASED TARIFF
Achievements Implemented between July 2002 and Nov.’2003 Improved quality of supply. Unutilised capacity harnessed-Pumped Storage Merit order Operation. Grid discipline Emphasis on load forecasting Discourage overdrawals during low frequency Facilitate bi-lateral trading Maximisation of generation availability

15 Grid Status – Before formation of National Grid, Modernisation of RLDCs and introduction of ABT
Large Frequency fluctuations 48.0Hz to 52 Hz. Low Voltages 400kV going down upto 300kV Frequent Grid Disturbances Sub-Optimal Operation High Technical loss Grid Operation on fire fighting instead of Optimisation & Economy

16 Open Access in inter-State Transmission
Guidelines formulated by POWERGRID in consultation with CERC and implemented w.e.f. May’2004 Non- discriminatory / Transparent Process Freedom to buy/sell power Efficient Market Mechanism to address supply / demand mismatches Encourage investment in Transmission Overwhelming response – More than 200 additional transactions effected from May’04 till Aug.’04 5300 MUs transacted through Open Access besides unscheduled interexchanges

17 MARKET DESIGN Short Term Open Access– (upto 1 year usage)
Trading of surpluses Subject to inherent design margins, margin available due to variation in power flow, in-built spare capacity available Economically priced ( ¼ th of long term transmission charges) Reliable settlement system Long Term Open Access– ( >25 year usage) Subject to System Studies and transmission planning criteria for augmentation/ new transmission Schemes Higher Priority over Short Term Open Access

18 Market Design… Trading UI – Spot Market
Unscheduled exchanges with the pool. No trader involved Price linked to system frequency which is displayed on the users screen Robust settlement system No vested interest of POWERGRID Trading Long / Short term directly or through trader under bilateral contracts.

19 International Practices in Grid Operation
Two Models TSO (Transmission System Operator) responsible for Transmission and System development and Operation. Being practiced in U.K., South Africa,France, Malaysia, Korea & other European countries ISO (Independent System Operator) Being practiced in USA, Germany, Spain on co-operative approach Transmission with multiple agencies USA now shifting towards TSO Canada mix of TSO & ISO China : TSO + Generation

20 CHALLENGES Right of Way becoming increasingly difficult on account of
Forest Clearance Tree Cutting Reduction of Land Value Being addressed as under: Design of Compact Tower & Tall Towers as per need Uprating & Upgrading of existing Transmission lines through Use of High Temperature Conductors Use of Series Capacitors with/without Thyristor Control Conversion from low voltage to high voltage Law & Order J&K,NER, Telangana, Bihar Demand Supply Gap- threatens the Grid Stability Private sector investment Time consuming process for project approval

21 Few Suggestions ……………………… to rejuvenate Power Sector.?
Institution Building Network expansion Transmission Sub. Transmission Distribution Augmentation of Load Despatch & Communication in distribution leading to Transparency and Trust Building at all levels Distributed Generation Introduction of Intra-State ABT Open Access in Intra State Transmission & Distribution Flattening of Load Curve leading to Economic power supply to agriculture in odd hours Creation of robust uniform market mechanism

22 THE NATIONAL INTEGRATOR THE FLAG BEARER OF THE POWER SECTOR
POWERGRID THE NATIONAL INTEGRATOR ELECTRICALLY & CULTURALLY THE FLAG BEARER OF THE POWER SECTOR

23 POWERGRID, INDIA Thank You

24 Grid Incidences Excluding NER

25 Frequency variation of 48.3 Hz to 51.5 Hz
Load Curve of Northern Region for Frequency variation of 48.3 Hz to 51.5 Hz FREQUENCY LOAD Load variation of 9000 to MW

26 Frequency Profile of SR
NEXT

27 Frequency Profile of ER
FREQUENCY CURVE 6th June02 6th June03 47.00 48.00 49.00 50.00 51.00 52.00 53.00 00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Time (Hrs.) Frqe (Hz.)

28 THE POWER ‘HIGHWAY’ 765 KV RING MAIN SYSTEM
CHEAP HYDRO POWER FROM THE NORTH-EAST AND PIT HEAD THERMAL POWER FROM THE EAST ENTERS THE RING AND EXITS TO POWER STARVED REGIONS

29

30 Generation PLF (Thermal) ER
Utility % PLF % increase BSEB 11.4 NIL JSEB 25 23 -8 DVC 39 44 12 Orissa 64 75 17 WBPDCL 55 56 2 CESC 68 72 5 DPL 40 41 NTPC 76 Region 52 8

31 MERIT ORDER : UNITS BOXED UP-SR
POWER STATION STATE CAPACITY(MW) FUEL VARIABLE COST TATA DIESEL KARNATAKA 79 DIESEL 308 RAYALSEEMA DGPP 27 360 YELEHANKA DIESEL 128 314 THANRBHAVI 220 NAPTHA 325 SUB-TOTAL 454 BRAHAMPURAM DPP KERALA 107 275 BSES 157 KASARGODE PCL 22 298 KAYAMKULAM 322 646 BASIN BRIDGE TAMIL NADU 120 584 P.P.NALLUR 330 415 450 TOTAL 1550

32 ULDC-THE EYES AND EARS OF THE SYSTEM OPERATOR
All constituents get the same data in real time. Transparency & Synergy in operation. Quantum leap in visibility to operator. Increased confidence & Focus on security and economy. Premptive, dynamic “early warning” systems. Grid less vulnerable to disturbances. Accurate and easy analysis of grid incidents Faster restoration after perturbation Comprehensive energy management system functions. Contingency evaluation, Security assessment and State Estimation

33 UI RATE Rate of Unscheduled Drawal/Injection Frequency (Hz) Rate (p/u)
Above 50.5 50.0 150 49.8 210 49.0 and below 570

34 KADAMPARAI PUMP OPERATION
SAVINGS OF RS 40 LAKHS EVERY DAY INVESTMENT OF 1600 CRORES SAVED GENERATOR MODE PUMP PUMP

35 Diversity of peaks NER peak 5:30 pm WR Peak 6:45 pm ER Peak 6:00 pm
68 72 76 88 92 96 80 84 S W N E NE L GEO POLITICAL POWER REGIONS B’ DESH- SRI NEPAL BHUTAN INDIA J&K HP PUNJAB HARIANA RAJASTHAN UP MP BIHAR ORISSA WB GUJARAT MAHARASHTRA KARNATAKA TAMIL NADU AP ASSAM MNP MIZ TRP NG ME LAKSHADWEEP A&N MYANMAR SKM PONDICHERY DELHI GOA DIU DAMAN NER LANKA JKND CTGR Diversity of peaks NER peak 5:30 pm ER WR Peak 6:00 pm Peak 6:45 pm

36 Schedule Vs Actual Injection at Dadri (T)
U I Actual Injection Declared Capability ά Capacity Charges Schedule ά Energy Charges Frequency NEXT

37 Schedule Vs Actual Drawal by UP
Schedule ά Energy Charges Actual Drawal U I Entitlement ά Capacity Charges Frequency

38 EUROPEAN & SOUTH AFRICAN MODEL
G G G G G T SO D D D D D This model is followed in UK by NGC, in Norway by Statenett, in Sweden by Svenska Kraftnet, in Finland by Fingrid, in Netherland by Tennet, in Denmark by Eltral/Elkrafts and in South Africa by Eskom. NEXT

39 AMERICAN MODEL G G G G G G RTO SO T T T SO D D D D D D
This model is followed in USA. Based on their experience, USA is now moving towards TSO model through RTO.

40 2003 2002

41 INTER-REGIONAL TRANSFER BY 2012
SOUTHERN REGION WESTERNREGION NORTHERN REGION NORTH-EASTERN REGION INTER-REGIONAL TRANSFER BY 2012 11,700 MW 2,650 MW 5,850 MW 4,900 MW 1,200 MW 3,700 MW EASTERN REGION 30,000 MW OF INTER-REGIONAL POWER BY 2012

42 Inter Regional Links Present IR Capacity = 9,000 MW 1650 MW 700 MW
2300 16,000 700 MW 32,700 MW 1200MW Present IR Capacity = 9,000 MW 30,500 MW 2000MW Next

43 Major inter-Regional Link
Project Cost (Rs. in Crores) Commissioning Date Approved Actual Scheduled TALCHER – KOLAR (2000 MW) ER-SR 3865 3096 June’03 Dec.’02 RAIPUR-ROURKELA (1000 MW) ER-WR 237 212 Dec.’03 Jan.’03 SASARAM-HVDC (500 MW) ER-NR 671 551 Dec.’01 June’01

44 Technical Losses w.r.t. Voltage
Power (P)= Voltage * Current = V*I Losses = (Current)2 * Resistance = I2*R Power is proportional to current, voltage remaining constant. To draw the same power at low voltage, one has to draw more current e.g.; 100 MW = 400kV * 250 Amps 100 MW = 320kV * 312 Amps Losses increases by 55% for 20%reduction in voltage. Losses doubles for about 30% reduction in voltage. e.g. Loss reduction in SR by 1% has given an annual saving of about Rs 290 crores 400 MU per day consumption in SR, 1% is 4 MU, annual 1460 Rs 2 = 290 cr

45 POWER GRID CORPORATION OF INDIA LTD. NEW DELHI


Download ppt "POWER GRID CORP. OF INDIA LTD. Dr. Montek Singh Ahluwalia"

Similar presentations


Ads by Google