Download presentation
1
Pool and Chute Fishways
Presented to: Pacific Northwest Fish Screening & Passage Workshop, 2006 Yakima, WA Presented by: Patrick D. Powers P.E. September 13, 2006
2
What is a Pool and Chute Fishway?
Hybrid type fishway that operates in two flow regimes, plunging and streaming flow
3
Background Carpenter Creek – Pool and Weir Fishway
Rainbow Creek – Pool and Weir Fishway WDFW Model Study Town Dam Pool and Chute Construction California
4
Pool and Chute - Definition
Side Walls Baffle Baffle Weir Port Floor
5
Pool and Chute - Cross Section
W Xpc d Pb b Pw
6
Pool and Chute – Profile – Plunging Flow
SoL Pw So L
7
Pool and Chute – Profile – Streaming Flow
Pb So L
8
Equations Flow over a weir Open channel flow Chezy Eq.
9
Research on streaming/plunging flow regimes
Rajaratnam, N. and Katopodis C Plunging and Streaming Flows in Pool and Weir Fishways. Journal of Hydraulic Engineering 114:
10
Streaming/Plunging Flow Regimes
Transition Plunging Streaming
11
Streaming/Plunging Flow Regimes
High Flow - Flood Streaming
12
Streaming transition flow calculations
Example: b = 2 ft L = 6 ft So = 10% Qst = 4 cfs So = 15% Qst = 6 cfs So = 20% Qst = 8 cfs
13
Case Studies - Parameters
14
Case Studies - Results
15
Fairchild Trib Q = 44 cfs D = 1.75 ft Qt = 5.3 cfs Chezy C = 31.5
Xpc = 1.2 EDF = 2.4 Passage Rating Fair
16
Fairchild Creek Q = 27 cfs D = 1.65 ft Qt = 5.3 cfs Chezy C = 20.5
Xpc = 1.6 EDF = 2.1 Passage Rating Good
17
Percival Creek Q = 24 cfs D = 1.5 ft Qt = 5.3 cfs Chezy C = 22.3
Xpc = 1.5 EDF = 1.3 Passage Rating Fair
18
Fairchild Comparison – 12 Foot Wide
44 cfs: EDF = 2.4 29 cfs: EDF = 2.1
19
Chezy C vs Qst
20
Design Criteria Xpc = Fish Passage Corridor - 0 to 2 ft EDF = 2 to 3
21
Design Process Calculate Qfp Select: W, baffle slope, drop, L, b, Pw
Calculate: Qst Select d and C Trial and error until Q = Qfp Check: EDF, Xpc
22
Benefits Reduced or No false attraction (small streams)
Self cleaning (gravel/small cobbles) Diverse passage routes for adult and juveniles Pool sizes can be reduced
23
Limitations Number of weirs fishway length Alignment Roughness values
27
Existing Design Guidelines
Draft in Progress - Pool and Chute Fishways Discussion and Design Process Revised September 11, 2001 By: Patrick D. Powers, P.E. Design Spreadsheet