Download presentation
Presentation is loading. Please wait.
Published byMarilynn Betty Anderson Modified over 9 years ago
1
SPS re-commissioning with beam K. Cornelis PS-SPS days
2
The 3 ingredients for a successful startup 1. A good cold check out 2. A good cold check out 3. A good cold check out Everything that can be checked must be checked HOWEVER
3
Certain things can only be checked with beam. Aperture and obstacles in vacuum chamber. The well functioning of beam instruments. Alignment. Feedbacks. Conditioning with beam. Optics checks and matching
4
Boundary conditions New control room New software New hardware New interlocks Modified access system A long shut-down.
5
The new control room Available as from beginning of February. Will be used for North area cold run Will be used for cold check out so that operators will become acquainted with it.
6
New Software Equipment level : SL-EQUIP to FESA MASTER TIMING MASTER TIMING Application soft : C-tree to ORACLE Wilkie to LSA TZ to LSA Worries : -Will software be ready? (under development) -The bugs -We have to know How to use it
7
Interlocks Interlocks New Hardware Interlock crates in BA1, BA4, BA6. Software interlock system : equipment calls.
8
Access Access Locks on equipment doors. Emergency stop connected to some zone limiting doors.
9
Commissioning with beam (TT10) Re-alignment in TT2 Low beta for stripping (Check matching) Tools : BPM’s, profile monitors, screens
10
Injection Tools : Kicker timing, OASIS, BCT TT10, MOPOS first turn.
11
RF capture and acceleration New timing modules in RF-cage Re-commissioning and tuning the loops is a lengthy job done by specialists. Several iterations needed, interleaved with transverse work. Tools : Soft to control timing modules, longitudinal PU‘s, OASIS, first turn and orbit measurements.
12
Closed orbit Half of the orbit PU‘s were modified during shutdown (polarity checks) Tools : CO software and analysing algorithms
13
Alignment Important for SE (orbit in sextupoles and limited bumper strength) We need accelerated beam Tools : Closed orbit Assistance from magnet people and geometers.
14
Aperture For the CNGS beam we need full aperture. Tools : Closed orbit, beam loss monitors Assistance from vacuum group in case obstructions are found.
15
Transverse feedback No major changes but power amplifier was taken out during shutdown for protection. Tools : Q-meter, OASIS.
16
Slow extraction TZ software replaced by LSA Spill feedback moved from PCR to BA1 The resonant extraction magnifies all the errors in the machine so it must be done once the machine is ‘cleaned-up‘ Takes a few hours if all the tools are available and working well. If NOT, it can take a shift or more Tools : closed orbit monitors, RF timing module control, profile monitors, control of the extraction elements.
17
TT20 Certain alignments were done during shutdown. Tools : screens, position monitors, SSIS, profile monitors, orthogonal steering on splitters and targets.
18
Conditioning New graphite beam dump in LSS1 RF cavities Tools : Vacuum monitoring available in CCC
19
North area New controls at equipment and application level. (CESAR) A cold run took place in November 2005 testing two secondary beam lines. A new cold run will take place in March 2006 involving all the lines. For commissioning with beam the EA team wants 3 days without physicists.
20
Conclusions The different steps in the beam commissioning will take more setting up and checks due to the numerous changes. Increased risk for ‘bad surprises‘. New tools may have bugs, less functionality or be only partly ready. We will need all the help we can get.
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.