Channel Rehabilitation Projects TAMWG - June ‘04 Trinity River at Hocker Flat 1/16/2003.

Similar presentations


Presentation on theme: "Channel Rehabilitation Projects TAMWG - June ‘04 Trinity River at Hocker Flat 1/16/2003."— Presentation transcript:

1 Channel Rehabilitation Projects TAMWG - June ‘04 Trinity River at Hocker Flat 1/16/2003

2 Effects of Trinity and Lewiston Dams on channel morphology and fish habitat at low flows at high flows Riparian berms

3 Rehabilitation Site Objectives  Remove encroached riparian vegetation  Take the “handcuffs” off the river  Initiate natural river processes  Re-scale floodplain for current and anticipated flow regime  Allow the river to create needed habitat variety  Revegetate in accordance with required permits

4 Hocker Flat Design and Area Delineation:  Riverine  Upland  Staging/Access

5 Design Criteria  Dry winter low water surface elevation  Feathered edges  Seasonal groundwater for revegetation  1.5 year recurrance frequency water surface elevation  Floodplain excavation  Theoretical river meander dimension  Floodplain management considerations  FEMA “Detailed Study Area” design restrictions

6 Engineering Design

7 Concept Cross-Sections

8 Hocker Flat Rehabilitation Site Property Ownership 012-120-0600 Smith 012-120-4200 Smith 012-120-4100 Merritt 012-260-2000 Bramlett 012-260-8100 Bailey 012-260-1600 Fornaciari 012-26-5600 Burke 012-260-4400 Helberg 012-120-4800 Bartoshek 012-120-4200 Smith 012-260-1400/1500 Dills 012-120-3300/3900 McLaughlin 012-140-0100/0200 McDuffey

9 Hocker Flat Schedule  Complete Public Scoping………………… July 2004  Begin Public Review Draft EA/EIR … … September 2004  Final EA/EIR …………………………... November 2004  Award Construction Contract …………... February 2005  Begin Construction …………………….. April 2005  Complete Construction ………………... September 2005  Initiate Revegetation …………………..... November 2005

10 Rehabilitation Sites Below Canyon Creek

11 Below Canyon Creek Schedule (4 sites)  Complete Public Scoping………………… January 2005  Begin Public Review Draft EA/EIR … … February 2005  Final EA/EIR …………………………... May 2005  Award Construction Contract …………... August 2005  Begin Construction …………………….. September 2005  Complete Construction ………………... February 2006  Initiate Revegetation …………………..... November 2006  Complete Revegetation …………………..... March 2007

12 Channel and Floodplain Rehabilitation Sites

13 Channel Rehabilitation Sites (24) Implementation Schedule Rehabilitation Sites 200420052006200720082009 REVEG DESIGN, NEPA/CEQA CONST. Hocker Flat Sites Below Canyon Creek 10 Sites Below Lewiston Dam Remaining 9 Sites DESIGN, NEPA/CEQA CONST. REVEG.

14 Rehabilitation Site Issues  FEMA  Realty  Revegetation  Environmental Compliance

15 Environmental Compliance  National Environmental Policy Act (NEPA) Requires federal agencies to analyze and disclose the environmental effects of their proposed actions Requires federal agencies to analyze and disclose the environmental effects of their proposed actions  California Environmental Quality Act State equivalent to NEPA….. but ALSO – State equivalent to NEPA….. but ALSO – Requires REDUCING environmental effects Requires REDUCING environmental effects Both promote efforts to minimize environmental effects via public participation and documentation

16  NEPA: Federal Lead = Agency with primary responsibility for preparing an Env. Document Lead = Agency with primary responsibility for preparing an Env. Document U.S. Bureau of Reclamation (Trinity River Restoration Program) Cooperating Agency = jurisdiction by law or special expertise U.S. Bureau of Land Management Cooperating Agency = jurisdiction by law or special expertise U.S. Bureau of Land Management  CEQA: State Lead = State Agency with primary project responsibility Lead = State Agency with primary project responsibility California Department of Water Resources Responsible Agencies Responsible Agencies Trustee Agencies Trustee Agencies

17 Environmental Documents EA/EIR Hocker Flat: Fall 2004 EA/EIR Canyon Creek Suite: Spring 2005 EA/EIR Upstream 10: Fall/Winter 2006 EA/EIR Remaining 9: Fall/Winter 2007  MASTER EIR? - Site specific details Multiple Neg. Decs. EA/EIRs

18 Environmental Permits  Army Corps of Engineers: Section 404 Clean Water Act permit  Endangered Species Compliance:  National Oceanic & Atmospheric Administration: Fisheries – Biological Opinion  US Fish & Wildlife Service  North Coast Regional Water Quality Control Board: Section 401 Water Quality Certification  California Department of Fish and Game: Section 1600 Streambed Alteration Agreement  Trinity County Ordinances: Floodplain ordinance

19 Environmental Compliance  Mercury Initial Studies Initial Studies Project Impacts to bioavailability & Trinity Project Impacts to bioavailability & Trinity  Revegetation Balance mitigation vs. function Balance mitigation vs. function  Pre-application Meetings (options to consolidate) Timing of construction Timing of construction Sediment control Sediment control Vegetation removal Vegetation removal

20 Photo of mining on Hocker flat from Jim Smith


Download ppt "Channel Rehabilitation Projects TAMWG - June ‘04 Trinity River at Hocker Flat 1/16/2003."