Download presentation
Presentation is loading. Please wait.
Published bySilvester Fisher Modified over 9 years ago
1
ATLAS TRT CO 2 cooling system project status Beaufort 12: “Hurricane” (>119 km/h) Saffir-Simpson 5: “catastrophic damage” (>250 km/h) (CO 2 distribution system: up to 300 km/h & Re = 4. 10 5 ) Joël Grognuz, 18.02.04
2
18.02.04 TRT CO 2 cooling system status, Joël Grognuz Wheels manifolds optimization Wheels manifolds optimization 24% maximum flow variation See: ATL-INDET-2004-004 Pressure drop calculations Pressure drop calculations 1 bar in total; 0.5 to 1.5 bar(abs) at inlet and outlet of the pump. inlet and outlet of the pump. System requirements: frozen System requirements: frozen see https://edms.cern.ch/file/445825/1/ see https://edms.cern.ch/file/445825/1/ Components procurement Components procurement Offers for Key components: pump, valves (No EV => no shielding needed) Most hardware components identified, budget done Prototype passive safety valves built Final 2 nd prototype layout Final 2 nd prototype layout Functionalities, regulation and safety strategy defined Like layout of the final system with two mock-ups (C-wheels) instead of 6 groups of wheels, might simplify 2 nd mock-up depending on manpower. Summary of last achievements, status
3
18.02.04 TRT CO 2 cooling system status, Joël Grognuz USA 15 ULX 16, pipes already installed gas room pump C-side A-side Racks UX Final system:
4
18.02.04 TRT CO 2 cooling system status, Joël Grognuz Prototype layout 4 states: -purge -turn on -run -emergency turn off
5
18.02.04 TRT CO 2 cooling system status, Joël Grognuz Limit for detector C: Passive safety over- pressure valve opens C: Trigger for active safety C: active valves in p stabilized by passive valves Worst case if blockage on the lines: Safety: (end-caps stand up to ± 5.5 mbar relative to ID volume) Passive safety valves:Fast active safety valves: opens at ± 4 mbar, fully opened at ± 5 mbar reaction times: opens at ± 4 mbar, fully opened at ± 5 mbar reaction times: whole system: < 500 ms whole system: < 500 ms valve: 100 ms valve: 100 ms For C-wheels with active safety: 10 liters sent to ID volume If constant flow of ±75 m 3 h -1 in ID (additional active safety failure): +3.4/ -2.2 mbar difference in ID (4 mbar allowed) (ID safety meeting next week) fast release pneumatic control safe position 180 mm Fits in membrane envelope
6
18.02.04 TRT CO 2 cooling system status, Joël Grognuz Failure modeling with simulink Volumes: C: 0.7 m 3 B: 1.5 m 3 A: 0.8 m 3 ID: 2 m 3 Volume element: uses Kv formula for valves and ideal gas assumption Laplace transform allows to solve differential equations to give time evolution
7
18.02.04 TRT CO 2 cooling system status, Joël Grognuz Failure 1: 300 m 3 h -1 line blocked Syst. off
8
18.02.04 TRT CO 2 cooling system status, Joël Grognuz Failure 2: 75 m 3 h -1 line blocked Still safe in case of active safety failure (assuming that regulations on other wheels stand the pressure changes in the ID)
9
18.02.04 TRT CO 2 cooling system status, Joël Grognuz Failure 3: 2 x 75 m 3 h -1 line blocked Almost as dangerous as 300 m 3 h -1 case because half of the flux but also half of the volume until other passive safety valves open!
10
18.02.04 TRT CO 2 cooling system status, Joël Grognuz Cleanliness Pump: (contains 1L of oil) Pump: (contains 1L of oil) Strong candidate found with double joints and gas barrier between gear box and system. (supplies 270 nm 3 h -1 with calculated pressure drops) Can use Si-free oil with low vapour pressure in the gear box (<10 -6 Torr at working Temperature). Other components: Other components: lubricants allowed, no numbers exist!
11
18.02.04 TRT CO 2 cooling system status, Joël Grognuz Tightness The requirement for N 2 content < 1% means that the low pressure side of the system has to be tight; any air leak rate will have to be compensated by a CO 2 purge 100 times larger! (problem of cost) The requirement for N 2 content < 1% means that the low pressure side of the system has to be tight; any air leak rate will have to be compensated by a CO 2 purge 100 times larger! (problem of cost)
12
18.02.04 TRT CO 2 cooling system status, Joël Grognuz Group of wheels mock-up 0.9 m 3, can be reduced by adding volumes inside. 0.9 m 3, can be reduced by adding volumes inside. C-wheels: 0.7 m 3 A-wheels: 0.8 m 3 B-wheels: 1.5 m 3 2 separations 2 separations 0.7 mbar pressure drop 0.7 mbar pressure drop 1 m 6 m 0.15 m Inlet manifold holes (80 holes) Outlet manifold holes (96 holes) Passive safety valves
13
18.02.04 TRT CO 2 cooling system status, Joël Grognuz Schedule Accept budget (possible delay)(February) Clarify manpower availability for prototype building Start procurement (March) Build “Prototype” (main circuit, at least one full rack, detector mockup, control unit) (June) If time, simulate the prototype and the full system Test prototype (July) Risk analysis (led in parallel) PRR (September)
14
18.02.04 TRT CO 2 cooling system status, Joël Grognuz Budget Summary with possible options: (piping and operation costs for final system not included)