Published byStephany Francis Modified over 9 years ago
1
Ingot Growth Dept. / Paul Internal use only 6/5 Daily Grower Status Update GRW101A: 1. Start 10 th cycle from 5/30. 2. Seeding completed on 6/3 daybreak, current weight is 2.852 kg. 3. Forecast ingot out 6/15. GRW102A: 1. Open chamber and completed PM on 5/29. 2. Take apart big cover and make copper welding for water leakage point. wait factory support to complete copper welding. 3. Check chamber and related hot zone parts GRW201A: 1. New heater & crucible completed anneal and start to cool down on5/29. 2. Plan to open chamber and do PM on Friday (6/1), and start next cycle. 3. Start pumping and heating from 6/1. 4. Seeding completed on 6/4, current weight is 0.279 kg. 5. Forecast ingot out 6/16.
2
Ingot Growth Dept. / Paul Internal use only Process Schedule Status Update
3
Ingot Growth Dept. / Paul Internal use only Back Up