Initial view on changes to Codes OTEG, 3 rd July 2006
2
Agenda Assumptions SO – TO Code Grid Code Connection and Use of System Code Process/timescales for change Only an initial view at this stage GB SQSS debate heavily influences changes required Are current arrangements appropriate offshore?
3
Assumptions ‘Offshore Users’ have equitable treatment as ‘Onshore Users’ Each offshore network has single point of connection to onshore network Offshore TOs may be nested Offshore networks may connect to onshore transmission or DNOs Offshore transmission will only be AC Must accommodate one or many new TOs Transitional arrangements may be required prior to enduring regime being implemented Any regime developed must be adaptable for the future
4
SO-TO Code (1) Section B - Governance Practicalities of extending beyond 3 TOs Section C - Transmission Services Switching Arrangements - TO acts under instruction from GBSO DNO interaction e.g. outage co-ordination Interaction between offshore TOs Section D - Planning Co-ordination Is onshore model applicable offshore?
5
SO-TO Code (2) Section E – Charging Charging Statement for each TO Section F – Communications and Data Are confidentiality provisions in STC suitable? STC Procedures Full review of existing STCPs required Requirement for new ‘Offshore STCPs?’
6
Grid Code May require further, additional, regional differences Planning processes Dealing with potential DNO interfaces Connection Conditions Driven by GB SQSS debate Review connection conditions for offshore Operating Codes Safety rules differ for different TO areas General Conditions Constitution of Grid Code Review Panel
7
Connection and Use of System Code Access Allocation of access Compensation for loss of access Exporting GSPs Current issue could be exacerbated via DNO connection Transmission Charging CUSC/Charging statements work hand in hand Same as GB regime? Bilateral Agreements Are existing onshore pro-formas appropriate?
8
Process for change - options Use normal governance arrangements for codes – Authority decision Ofgem/DTI consult – changes designated by Secretary of State Issues to consider: Timescales Complexity and scope of change Interactions between codes (cross-governance) Flexibility Ensuring all interested parties are included Utilisation of existing industry expertise Co-ordination with ongoing GB Code change processes OTEG liaison with industry panels
9
Timescales June 06Initial view on code changes Sept 06Follow on from GBSQSS group Scope required changes further Q1 07Specific identification of required changes Q2 07Industry consultation Q2/3 07Refinement of changes Finalise details of legal drafting Q3/4 07Final consultation Mid 08Go-Live for offshore regime